Resolved
The Landlord Services Advisory Board supported the request for an increase in budget for the Water Hygiene Capital and Revenue Works as set out in the justification papers and recommended to Executive and Council to approve.
Landlord Services Advisory Board (Executive Working Group) approved this item on Thursday 24 April 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
The Landlord Services Advisory Board supported the request for an increase in budget for the Water Hygiene Capital and Revenue Works as set out in the justification papers and recommended to Executive and Council to approve.
Project Business Case Justification Template last updated: 4/9/2019, Owner: Corporate Form Policy/Finance
The Project Business Case needs to be approved by management before the initiation of any potential project and it is a pre-requisite to a PID
SECTION A - PROJECT DETAILS
Project Title Water Hygiene Capital and Revenue works
Service Housing Property services
Project manager Stuart Watson
Project sponsor Hugh Wagstaff
Start Date 01/04/25
Expected Completion Date 31/03/26
Expected Project Total (auto populated) £1,082,801.76 Cost centre (if known)
Project Scale / Reporting (auto populated) Corporate Project Overall Project Score 10
To start a new paragraph within a cell - Alt+ Enter Project Outline Please provide an overview of the project/business case
Both the water hygine capital and revenue works require increased budgets, as explained further below.
Capital Works Currently, there are 452 outstanding remedial actions generated from legionella risk assessments, with additional actions being identified regularly. To address these, sufficient funding is required to complete all outstanding and future recommendations.
Most of the outstanding actions pertain to cold water storage tanks located in the roof spaces of our properties, which are not boarded. To mitigate the risk of legionella, it is recommended to remove these tanks. This approach not only reduces the risk of legionella but also eliminates the need for ongoing monitoring and maintenance of the tanks, as well as the cost of installing health and safety measures such as loft boarding and lighting.
In addition to the remedial actions from risk assessments, further actions are identified during our Planned Preventive Maintenance (PPM) monitoring regimes on a monthly basis. For example, improvements are needed for some thermostatic mixing valves (TMVs) within our senior living scheme properties. These works include removing, replacing, or relocating the TMVs, as poorly maintained TMVs can harbour bacteria within their strainers.
We have consulted with contractors and obtained pricing for all current actions related to cold water storage tanks, totalling £395,000 in capital expenditure. Additionally, we anticipate further work arising from risk assessments due in the next six months, requiring an additional £450,000 in capital funding.
Further removal of cold water storage tanks are required at two of our senior living scheme properties, requiring an additional £75,000 in capital funding.
Revenue Works An additional revenue budget of £162,000 is needed to ensure all flat blocks are risk assessed, with 10% of both houses and bungalows added to our portfolio each year. This budget includes a contingency element of £33,000 to fund mitigation actions if a scheme had legionella.
Project Justification The recommendations are made in order to undertake a programme of works to eliminate / reduce the risk of legionella bacteria thriving in the water systems and devices of the Council’s homes. Please provide the objectives and include an analysis of the benefits and disbenefits. If this programme is not delivered, the Council will continue to have little knowledge of their properties' water systems and their condition. Some of these systems may have been untouched for several years and could be in poor condition, potentially resulting in a case of legionella. The worst-case scenario of a legionella outbreak would be fatalities among our residents. If a case of legionella were reported to be related to one of the Council's water systems, the Council could face public scrutiny, court cases, and heavy fines.
Disbenefits are considered to be the disruption to tenaants whilst work is ongoing How will the project meet corporate objectives and your service plan? Reference to agreed service plan and/or corporate objectives
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ADDITIONAL BUDGET REQUST FOR WATER HYGIENE WORKS TO THE COUNCIL'S HOMES REPORTReport | 800 KB | DownloadRead as text |
Follow Landlord Services Advisory Board (Executive Working Group) at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jul 2026 | Capital Programme updateRESOLVED that the Capital Programme update be noted. | Noted | Open |
| 30 Jul 2026 | Council Response to Tenant Panel Proposal on Repairs, Maintenance and Service AppointmentsRESOLVED that: · the tenant panel proposal be noted, · the principles of a standardized appointments and communicatio... | Noted | Open |
| 30 Jul 2026 | Low Carbon Heating SolutionsRESOLVED that the Low Carbon Heating Solutions report be noted. | Noted | Open |
| 30 Jul 2026 | Water Hygiene ReportRESOLVED that the monthly Water Hygiene Report be noted. | Noted | Open |
| 30 Jul 2026 | Landlord Services Improvement Plan Update [2025-26]RESOLVED that the Landlord Services Improvement Plan update was noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.