Waverley Borough Council
Executive, Tuesday 14 October 2025 at 7.00pm

Willmer House: Timber Roof Structure Repair and Replacement at Front Facade

Approved Executive 2 papers

AI summaryWaverley Executive approved a £60,500 budget virement and recommended Council approve £610,248.05 to repair the failing timber roof structure at the Grade 1 listed Willmer House, home of the Museum of Farnham.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedExecutive approved virement, recommends Council approve full budget
Money£610,248.05 plus £60,500 virementFunded from capital receipts reserve
What happens nextFull Council decisionDue 22 October 2025
Who it affectsMuseum of Farnham and visitorsGrade 1 listed Willmer House, Farnham

What was decided

The Executive approved a virement of £60,500 of capital funding from the 2025/26 rear window joinery budget to support the cost of repairing the structural roof timbers at the front of Willmer House. Report 2.1, P9

The Executive recommended that Full Council approves a budget of £610,248.05, funded from the capital receipts reserve, to repair the timber roof frame at the front of Willmer House and commission a condition survey of the rear. Report 2.2, P11

Why

A site inspection with a structural engineer and timber conservator found extensive wet rot and insect decay in the roof timbers, with only about 30 percent of the wall plate and 40 percent of the tie beam remaining, leaving the roof structurally unsafe. Report 1.2, 6.6

The Council has a legal duty to maintain a Grade 1 listed building under the Listed Buildings Act 1990, and failure to maintain it could result in the local planning authority serving a Repairs Notice or Repairs Order. Report 3.1, 6.1, P25

Carrying out the repairs during the 2025/26 winter shutdown is the most cost-effective option, as delaying past September 2026 would require a third winter shutdown and add up to £200,000 in scaffold and contractor extension of time costs. Report 1.3

What happens next

The report will go to Full Council for consideration on 22 October 2025. Report 4.1

An application for listed building consent has been submitted, and the repair work is expected to take up to 15 weeks, starting immediately if funding is approved. Report 4.2, 6.19

A condition survey of the rear elevation will be carried out while the rear scaffold is in place, with findings expected before the end of the year and a further report to the Executive. Report 1.6, 4.3, 6.21

The money

  • £60,500 Capital virement from rear window joinery budget to roof timber repairs Report 2.1, P9
  • £610,248.05 Supplementary budget from capital receipts reserve for timber roof repairs and rear condition survey Report 2.2, P11, 13.3
  • £791,973.18 Total cost of roof repairs and associated works Report P53, 6.23
  • £670,748.05 Subtotal after deductions of remaining project monies and superseded sums Report P54, 6.23
  • £248,375.80 Supplementary estimate previously approved in June 2025 for chimney stack rebuilding Report 1.1
  • £1,720,087 Total approved budget to date for the Willmer House project Report 13.1
  • up to £200,000 Estimated additional scaffold and contractor extension of time costs if a third winter shutdown is required

Options considered

  • Rejected: Do nothing: ignore the decayed roof timbers and reinstate a new parapet wall to encase them. Risk of severe structural failure and complete collapse, and would be ill advised after significant investment in the brickwork Report 11.1
  • Rejected: Delay the timber roof repairs while investigating funding sources. Not cost effective, would risk breaching the September 2026 completion date and incurring up to £200,000 in extra costs Report 11.2
  • Chosen: Approve the roof timber repairs with minimal delay during the 2025/26 winter shutdown. Most economical solution, causes least disruption, enables grant-funded brickwork programme to complete by 30 September 2026 Report 11.3, 11.5

Implications

  • Financial: Total project cost rises to £610,248.05 in additional funding from capital receipts, beyond the existing £1,720,087 approved budget. Report 13.1, 13.3
  • Legal: The Council has a legal duty under the Listed Buildings Act 1990 to maintain the Grade 1 listed Willmer House, and listed building consent has been applied for. Report 3.1, 4.2, P25
  • Risk: Failure to complete by 30 September 2026 could mean repaying some or all Arts Council England grant money and an additional £150,000 to £200,000 in extension of time costs. Report 10.1, 13.5
  • Risk: Ecology survey on 24 September 2025 is assessing potential bat presence in the historic roof structure, which could affect the project timeline. Report 10.2, 6.18
  • Other: Rear elevation is in poor and deteriorating condition with loose bricks and failing window joinery, presenting a health and safety risk requiring further survey. Report 1.5, 10.3

Who and where

  • Visitors and users of the Museum of Farnham Report 7.1
  • Farnham residents and the wider public in the borough Report 7.1
  • Future unitary authority inheriting the property under local government reorganisation Report 8.1
  • Arts Council England as a funder under the MEND programme and 15-year covenant on the freehold Report 8.1, 10.1

Timeline

  • 2015: Conservation condition survey by Simpson Brickwork Conservation first reported the vulnerable front facade
  • January 2025: 83-week programme of essential repair and conservation work commenced on the front facade Report 6.1
  • February 2025: Council approved £160,500 capital funding for redecoration of rear windows Report 13.2
  • 3 June 2025: Executive approved supplementary estimate of £248,375.80 for chimney stack rebuilding Report 1.1
  • 12 June 2025: Site inspection of timber roof structure with structural engineer and conservator Report 6.6
  • 4 September 2025: Structural Timber Roof Repairs Report by Ingram Consultancy Report 19.1
  • 24 September 2025: Ecology survey carried out to assess potential bat presence in the roof structure Report 10.2
  • 14 October 2025: Executive considered this report
  • 22 October 2025: Report to be considered by Full Council Report 4.1
  • November 2025 to March 2026: Planned window for timber roof repairs during winter shutdown Report 6.18
  • Before end of 2025: Expected findings of the rear condition survey Report 1.6
  • 30 September 2026: Critical completion date for the front facade project to meet grant conditions Report 11.3, 13.5

Plain English for the jargon

  • Virement: Reallocation of money from one budget heading to another within the approved budget
  • Listed building consent: Permission required from the local planning authority to alter or extend a listed building in a way that affects its special interest
  • MEND Fund: Arts Council England's Museums and Exhibitions Resilience Development fund, a major source of grant funding for the project
  • Flitch plate: A T-section stainless steel plate used to splice and reinforce decayed timber beams
  • Repairs Notice / Repairs Order: Legal tools available to a local planning authority to compel an owner to carry out works to maintain a listed building
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 75/25

Resolved

RESOLVED that the virement of £60,500 capital funding from the 2025/26 capital programme for rear window joinery to be reallocated to support the overall cost of repairing the structural roof timbers at the front of the building be approved. RECOMMENDED that Council resolves to approve a budget of £610,248.05, to ... EXE 75/25
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

1.1At a meeting on 3rd June 2025, the Executive approved the recommendations in a report regarding repair works to The Museum of Farnham, which occupies Grade 1 Listed Willmer House. This included agreeing a supplementary estimate of £248,375.80 to cover the costs of rebuilding two chimney stacks, which pose a risk to health and safety and the extension of the contract to complete the works.

1.2The report also raised concerns about the condition of the timber roof structure which, following the removal of the parapet wall is now fully exposed at the front façade interface. Since the Executive in June, there has been a detailed assessment of the timber roof frame involving a site meeting with a structural engineer and a timber frame and joinery conservator. Their findings conclude that repair and replacement of the roof timbers is essential and urgently required to restore the structural function of the roof.

1.3This report explains how the roof structure works and the urgent need for the repair work. It proposes the most cost-effective repair solution, which is for the structural timber works to take place during the 2025 winter shut down. As well as the need for an integrated scaffold covering the whole of the rear elevation. Front and rear scaffolding is necessary to support the load of the roof structure while the chimney and roof repairs are carried out.

1.4The report gives a breakdown of the costs of repairing the structural roof timbers at the front of the building only. This is because, we do not have a cost estimate for repairing the roof timbers at the back of the building yet.

1.5However, a preliminary visual inspection of the brickwork on the rear of the building has been carried out following safety concerns that bricks are coming loose around the window openings. It is clear from this cursory inspection that brickwork decay is widespread and that the condition of the external windows and door frames is declining at a rapid rate. The overall condition of the rear appears to have reached a critical point where major intervention is likely to be needed.

1.6It is therefore recommended that a condition survey is carried out while the rear scaffold is in situ to understand the extent and severity of the problems. Subject to approval, the Council expects to receive the findings of the rear survey before the end of the year.

2 Willmer House Timber Roof Structure Repairs

Recommendations

2.1That the Executive resolves to:

Approve the virement of £60,500 capital funding from the 2025/26 capital programme for rear window joinery to be reallocated to support the overall cost of repairing the structural roof timbers at the front of the building.

2.2That the Executive recommends that Council resolves to:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Structural Timber Roof Repairs Report 75/25Appendix 1 956 KB Download
PDF
Willmer House: Timber Roof Structure Repair and Replacement at Front FacadeReport 442 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
PF
Councillor Paul FollowsChair, present
TF
Councillor Tony FaircloughVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
GL
Councillor Gemma LongCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, present
PR
Councillor Paul RiversCommittee Member, apologies
LT
Councillor Liz Townsend BEMCommittee Member, present
SW
Councillor Steve WilliamsCommittee Member, present

On this subject at Waverley

Search all
  1. Willmer House: Timber Roof Structure Repair and Replacement at Front FacadeThis decision
  2. Willmer House: Timber Structure Repair and Replacement at FaçadeAgreed
  3. Progress report on the essential repair and conservation works to Grade 1 Willmer House, Museum of FarnhamApproved

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies