Waverley Borough Council
Executive, Tuesday 10 March 2026 at 7.00pm

Approval to extend contract for Fire remedials and fire door installation with incumbent

Approved Executive 1 paper

AI summaryWaverley Executive approves first one-year extension of passive fire safety contract with Ian Williams Ltd, worth an estimated £775,499, to run from May 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFirst of three one-year extensions to Ian Williams Ltd
Money£775,499 estimated extension valueTotal 3+1 spend estimated at £3,384,966.33
What happens nextNot stated
Who it affectsCouncil housing tenantsStatutory fire safety works continue on homes

What was decided

The Executive approved activation of the first one-year permissible extension under the existing measured term contract for passive fire safety works with Ian Williams Ltd. Report 2.1, P6

Why

The incumbent has performed well over the three-year core term, with strong KPIs, good quality workmanship, minimal defects and positive tenant feedback. Report 3.2, 6.3, 6.4, 6.5

Extending avoids service disruption, procurement delay and mobilisation costs, and keeps total spend within the originally approved contract value. Report 1.2, 3.3, P44

The extension aligns the contract end date with Guildford Borough Council to enable a future joint long-term procurement approach, including in the context of Local Government Reorganisation. Report 1.3, 6.7, 8.1, 8.2

What happens next

The Council will formally issue notice to enact the first one-year extension to Ian Williams Ltd and update financial projections. Report 4.1, P12

KPI and contract management monitoring will continue to ensure service standards are maintained. Report 4.2

Officers will progress discussions with Guildford Borough Council to align end dates and develop a joint long-term procurement strategy, including early market engagement. Report 4.3, 8.1

The money

  • £3,750,000 Original approved measured term contract value Report P44
  • £2,368,467.33 Current expenditure under the contract Report P44
  • £241,000 Anticipated further spend during remainder of core term Report P44
  • £775,499 Estimated value of the proposed one-year extension Report P44
  • £3,384,966.33 Total anticipated expenditure across 3+1 period Report P44

Options considered

  • Rejected: Do nothing and allow the contract to conclude at the end of the core term, followed by an immediate procurement exercise. Risk of service disruption, procurement delay and impact on statutory compliance Report 11.1
  • Chosen: Activate the first permissible one-year extension with Ian Williams Ltd. Maintains continuity, statutory compliance, value for money and supports future joint procurement with Guildford Report 11.2, P43

Implications

  • Financial: Total 3+1 expenditure of £3,384,966.33 remains within the originally approved £3,750,000 contract sum and is funded from the HRA capital programme. Report P44, P45
  • Legal: The extension uses an option already provided in the original contract and does not constitute a material variation under the Public Contracts Regulations 2015; Legal will issue formal written notice. Report P47, P48, P49
  • Equalities: The Equalities Comprehensive Impact Assessment found no disproportionately adverse impact; the extension supports continued fire safety for older, disabled and other vulnerable tenants. Report P57, P58, P59, P60
  • Climate: The extension does not change the scope or scale of works; compliant fire doors and compartmentation may indirectly improve thermal performance and reduce air leakage. Report 12.4, P63, 12.5
  • Risk: Not approving could disrupt fire safety works, harm statutory compliance and create reputational risk; extending mitigates these risks and avoids mobilisation costs of a new contractor. Report 10.1, 10.2, P39
  • Other: Extension supports alignment with Guildford Borough Council and offers flexibility during Local Government Reorganisation. Report 8.1, 8.2

Who and where

  • Council housing tenants, including older and disabled residents in properties receiving fire safety works Report 6.1, P59
  • Waverley Borough Council Housing Service and Housing Revenue Account Report 6.3, P45
  • Ian Williams Ltd (incumbent contractor) Report 2.1, P6
  • Guildford Borough Council (future joint procurement partner) Report 1.3, 8.1

Timeline

  • May 2026: Core three-year contract term concludes
  • Following approval: Formal notice issued to enact the first one-year extension Report 4.1, P49
  • During the extension period: Discussions with Guildford Borough Council on aligning end dates and joint long-term procurement Report 4.3, 8.1

Plain English for the jargon

  • Passive fire safety works: Building measures such as fire doors and compartmentation that slow the spread of fire and smoke.
  • Measured term contract: A contract where work is carried out over a set period and paid for against agreed unit rates.
  • Compartmentation: Dividing a building into fire-resistant sections to contain fire and smoke.
  • Housing Revenue Account (HRA): The ringfenced account landlords must keep for income and spending on council housing.
  • Local Government Reorganisation (LGR): Changes to the structure, boundaries or governance of local authorities.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 49/25

Resolved

Resolved that the activation of the first one-year permissible extension under the existing measured term contract for passive fire safety works with Ian Williams Ltd be approved.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

1 Passive Fire Safety Works Contract Extension

1.1This report seeks approval to activate the first of three permissible one-year extensions to the Council’s existing passive fire safety contract with Ian Williams Ltd. The extension will ensure continuity in delivering statutory fire door installation, repair and compartmentation works, safeguarding residents and maintaining compliance, while remaining within the originally approved contract value.

1.2Approving the extension maintains a well-performing contractor with a strong track record of quality and tenant satisfaction, avoids disruption to essential safety works, and mitigates the compliance and mobilisation risks associated with undertaking an immediate new procurement exercise. The proposal also supports value for money and service stability during a period of organisational change.

1.3The extension enables alignment of contract end dates with Guildford Borough Council to facilitate a future joint long-term procurement approach, supporting collaboration and preparing for potential implications arising from Local Government Reorganisation. The recommendation therefore aligns with the Council’s corporate priorities of protecting residents, delivering high- quality services, and ensuring effective use of resources.

Recommendations

2.1That the Executive resolves to:

2.1.1 Approve the activation of the first one-year permissible extension under the existing measured term contract for passive fire safety works with Ian Williams Ltd.

3 Reason(s) for recommendation:

3.1Activating the first permissible one-year extension ensures continuity in the delivery of statutory passive fire safety works while maintaining compliance and safeguarding residents.

3.2The incumbent contractor, Ian Williams Ltd, has demonstrated consistently good performance over the core contract term, with strong KPIs, good quality workmanship, minimal defects, and positive tenant feedback.

2 Passive Fire Safety Works Contract Extension

3.3The anticipated total spend remains within the original contract award, representing value for money. The extension also supports the strategic objective of aligning contract end dates between the two Councils, enabling the development of a coordinated long-term procurement solution

4 Next steps

4.1Subject to approval, the Council will formally issue notice to enact the first one-year extension to Ian Williams Ltd and update financial projections accordingly.

4.2Performance monitoring through established KPI and contract management arrangements will continue to ensure service standards are maintained.

4.3Officers will also progress discussions with Guildford Borough Council to align contract end dates and develop a joint long-term procurement strategy, including early market engagement to inform future commissioning option.

5 Exemption from publication

5.1This report is not exempt from publication.

6 Background and Proposal

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval to extend contract for Fire remedials and fire door installation with incumbentReport 774 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
PF
Councillor Paul FollowsChair, present
LT
Councillor Liz Townsend BEMVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
AD
Councillor Adam DuceCommittee Member, present
TF
Councillor Tony FaircloughCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
GL
Councillor Gemma LongCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, apologies
KM
Councillor Kika MiryleesCommittee Member, present
PR
Councillor Paul RiversCommittee Member, present

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies