Executive, Tuesday 10 March 2026 at 7.00pm

New contract for the supply of Water, sewage and additional services

Decided Executive 1 paper

AI summaryWaverley Borough Council's Executive has approved a £211,500 water, sewerage and additional services contract for its council building, running from 16 February 2026 for up to five years.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedRecommended supplier named in exempt appendix
Money£211,500Total contract value over up to five years
What happens nextContract starts 16 February 2026Enter into contract with recommended supplier
Who it affectsCouncil building servicesWater, sewerage and additional services

What was decided

The Executive approved awarding the water, sewerage and additional services contract to the recommended supplier, starting 16 February 2026 for an initial three years with an option to extend by up to two years (one year plus one year), at a total value of £211,500. Report 2.2

The name of the recommended supplier is held in an appendix exempt from publication under paragraph 3 of Part 1 of Schedule 12A to the Local Government Act 1972. Report 2.2, 5.1

Why

The award represents best value and gives the Council greater control over service delivery, costs and performance, while reducing procurement and contract management risks. Report P5

A formal contract ensures continuity of supply and compliance with statutory duties on health, safety, water hygiene and legionella control, and supports the Council's sustainability and asset management objectives. Report 6.1, 6.2, 7.1

The procurement was carried out in collaboration with Guildford Borough Council using the Laser Energy, Water Framework Y22013, Lot 1, and is structured to allow transfer to a successor authority under any future Local Government Reorganisation. Report 8.1, 8.2

What happens next

Enter into a contract with the recommended supplier for the supply of water, sewerage and additional services for three years with the option to extend for a further two years (one year plus one year). Report 4.1, P6

The cost will be funded from within existing budgets, which are sufficient to cover the costs outlined. Report P35

Legal Services will be instructed to finalise and enter into the final form of contract. Report P38

The money

  • £211,500 Total contract value (two hundred and eleven thousand five hundred pounds) Report 2.2, P34
  • 42.3 Estimated cost Year 1 (£000s) Report P34
  • 42.3 Estimated cost Year 2 (£000s) Report P34
  • 42.3 Estimated cost Year 3 (£000s) Report P34
  • 42.3 Estimated cost Year 4, extension period (£000s) Report P34
  • 42.4 Estimated cost Year 5, extension period (£000s) Report P34
  • 211.5 Total estimated cost over five years (£000s) Report P34

Options considered

  • Rejected: Do nothing, no contract awarded. Would leave the Council exposed to increased statutory, health and safety, and environmental compliance risks, with unclear accountability and risk of service disruption, unplanned costs and adverse audit or reputational impacts. Report 9.2, P28
  • Chosen: Award the contract to the recommended supplier. Ensures safe, reliable and compliant provision of water and wastewater services with clear accountability, cost certainty, continuity of service, faster response to faults, and stronger governance and audit assurance. Report 9.3, P28

Implications

  • Legal: The procurement complied with the Procurement Act 2023, Public Contracts Regulations 2015 and the Council's Contract Procedure Rules; Legal Services will finalise the contract. Report P37, P38
  • Risk: Without a formal contract the Council would face increased statutory, regulatory, operational, financial and reputational risks, and weaker governance and audit assurance. Report 10.1, 10.2, 10.3, P24
  • Financial: The cost will be funded from within existing budgets, which are sufficient to cover the costs outlined. Report P35
  • Equalities: The Public Sector Equality Duty has been considered; no equality and diversity implications arise directly from this report. Report P46
  • Climate: No climate change or sustainability implications identified. Report P48
  • Other: Supports the Council's Corporate Strategy priorities for a More Sustainable Borough and a Resilient and Well-Managed Council. Report 7.1, P17

Who and where

  • Waverley Borough Council's council building and its water and wastewater service users Report 6.1, 6.3, P12
  • Guildford Borough Council, as the procurement collaboration partner Report 8.1, P20
  • Any future successor authority under Local Government Reorganisation, to which the contract can be transferred Report 8.2, P20

Timeline

  • 16 February 2026: Contract commencement date Report 2.2
  • Initial period of three years: Core contract period, with break clauses at the end of each year (Y1 to Y3) Report 2.2, 4.1, P34
  • Up to two years (one year plus one year): Optional extension period, years 4 and 5 Report 2.2, 4.1

Plain English for the jargon

  • CPRs: Waverley Borough Council's Contract Procedure Rules, governing how contracts are procured.
  • Laser Energy, Water Framework Y22013, Lot 1: The procurement framework under which the water, sewerage and additional services contract was tendered.
  • Schedule 12A, Part 1, paragraph 3: Provision of the Local Government Act 1972 used to exempt the supplier appendix from publication, on the basis of financial and business affairs of tenderers.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 54/25

Resolved

Resolved that the award of the Supply of Water, Sewerage and Additional Services contract to the recommended Supplier set out in the Appendix to the agenda report for an initial period of three years with an option to extend by up to two years (one year + one year), commencing ... EXE 54/25
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

1 The award of new contract for the Supply of Water, Sewage and Additional Services

1.1The purpose of this report is to seek approval, in accordance with Waverley Borough Council’s Contract Procedure Rules (CPRs) 8.6, to award a contract for the Supply of Water, Sewage and Additional Services.

2 Recommendation: 2.1 That the Executive resolves to:

2.2Approve the award of the Supply of Water, Sewerage and Additional Services contract to the recommended Supplier set out in the Appendix for an initial period of three years with an option to extend by up to two years (one year + one year), commencing on the 16 February 2026 at a total contract value of £211,500 (two hundred and eleven thousand five hundred pounds).

3 Reason(s) for decision: 3.1 The award of the water utilities contract to the recommended Supplier represents best value for the Council. As a council-owned facility, this option provides greater control over service delivery, costs, and performance, while reducing procurement and contract management risks. It enables quicker response to operational issues, better coordination with existing council services, and more efficient management of water usage. The arrangement supports the Council’s sustainability objectives and long-term asset management strategy and offers a stable and cost-effective solution.

4 Next steps

4.1To enter into a contract with the recommended Supplier set out in the appendix, for the supply of Water, Sewerage and Additional services for a period of three years with the option to extend for a further two years (one year + one year).

5 Exemption from publication

5.1The appendix to this report is exempt from publication by virtue of paragraph 3 of Part 1 of Schedule 12A to the Local Government Act 1972. The appendix contains information which relates to the financial and business affairs of the tenderers in the form of the tender evaluations and the public interest in disclosing the

2 The award of new contract for the Supply of Water, Sewage and Additional Services

information does not outweigh the public interest in maintaining the exemption.

6 Background and Proposal

6.1The Council is required to have appropriate contractual arrangements in place to ensure the safe, reliable, and legally compliant provision of water and wastewater services to the council building. These services are critical to the effective operation of the building and to meeting the Council’s statutory duties relating to health, safety, and environmental protection. This includes compliance with relevant legislation and guidance such as the Health and Safety at Work Act 1974, the Water Supply (Water Fittings) Regulations 1999, and approved codes of practice relating to water hygiene and legionella control.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
New contract for the supply of Water, sewage and additional servicesReport 818 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
PF
Councillor Paul FollowsChair, present
LT
Councillor Liz Townsend BEMVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
AD
Councillor Adam DuceCommittee Member, present
TF
Councillor Tony FaircloughCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
GL
Councillor Gemma LongCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, apologies
KM
Councillor Kika MiryleesCommittee Member, present
PR
Councillor Paul RiversCommittee Member, present

On this subject at Waverley

Search all
  1. New contract for the supply of Water, sewage and additional servicesThis decision
  2. New Contract for Communal Block Cleaning ServicesDecided
  3. New Contract for Roof Repair ServicesDecided
  4. New contract for Roof Repair ServicesDecided
  5. New contract for Damp, Mould and Condensation Prevention and Remediation ServicesDecided
  6. New contract for the Doors and Windows Capital investment programApproved

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies