AI summaryWaverley Landlord Services Advisory Board notes April 2026 performance report, with most indicators within tolerance but void turnaround, repair timeliness and tenant satisfaction below target.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo further action decided
MoneyNot stated
What happens nextContractor recruiting operativesTo improve repairs timeliness
Who it affectsWaverley council tenantsAround 3,300+ homes

What was decided

The board noted the Landlord Services Performance Scorecard and Exceptions Report for April 2026, taking no further action.

Why

The report was presented to allow the board to scrutinise landlord service performance against the agreed scorecard. Report P1, P2

Officers reported that most safety and compliance indicators sat within tolerance, while responsive repairs, tenant satisfaction, void re-let times and rent loss were flagged as exceptions requiring attention. Report P3, P4, P5, P12, P14, P15, P19, P20, P21, P22

What happens next

Officers will continue the Warm Homes Wave 3 retrofit programme (2025-2028), targeting 311 homes to at least EPC C and addressing Decent Homes failures under Criterion D by March 2028. Report P6, P8

The contractor Ian Williams is recruiting additional operatives to relieve electrical workstream pressure and improve the 28-day repair completion rate. Report P15

Tighter first-point triage, trade quality assurance and no-access escalation are being pursued to drive down void times, rent loss and overdue inspections. Report P10, P11, P18, P20

Options considered

  • Chosen: Note the performance scorecard and exceptions report. Standard scrutiny process for the advisory board.

Implications

  • Risk: Ten properties require remedial electrical works, 11 have unconfirmed EICR dates and 18 properties are overdue inspection, with three escalated to Housing Management due to hoarding-related access issues. Report P9, P10
  • Risk: 31 smoke alarms await compliance confirmation and 17 remain outstanding pending electrical checks, prompting a recording practice review with Housing Management. Report P13
  • Financial: Void rent loss stood at 1.76% against a 1.30% target, though this was an improvement on the previous month. Report P21
  • Staffing: Resource pressure in the electrical workstream has been identified, with active recruitment under way to strengthen capacity. Report P15
  • Other: Tenant satisfaction with repairs was 79% against an 85% target, with no single dominant theme among the 23 dissatisfied responses. Report P15, P16, P17

Who and where

  • Waverley Borough Council tenants living in homes with non-compliant EICRs, smoke alarms or Decent Homes failures Report P7, P9, P13
  • Tenants awaiting non-emergency responsive repairs, particularly electrical works Report P14, P15
  • Households in long-term voids being re-let Report P19, P20

Timeline

  • April 2026: 36 homes issued with fixed notices under the no-access escalation process, with three completions to date. Report P11
  • Next 5 years: Window in which Criterion C failures are to be addressed under the internal structural budget or the joint kitchen and bathroom programme once procurement completes. Report P8
  • Next week (from report): Four further properties expected to enter the no-access escalation process. Report P11
  • 1 to 30 April 2026: Reporting period covered by the scorecard. Report P1
  • 2025-2028: Warm Homes Wave 3 retrofit programme to improve 311 homes to at least EPC C and address Criterion D failures by March 2028. Report P6, P8

Plain English for the jargon

  • EPC: Energy Performance Certificate, a rating of a home's energy efficiency from A (best) to G.
  • EICR: Electrical Installation Condition Report, a periodic check of a home's electrical systems.
  • Decent Homes Standard: Government standard covering minimum housing condition criteria, including Criterion C (modern facilities) and Criterion D (energy efficiency, measured by SAP).
  • Void: A council home that is empty between tenancies and is being prepared for re-let.
  • No-access escalation: Process used when a contractor cannot gain entry to carry out inspections or works, including serving fixed notices.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

RESOLVED that: The Landlord Services Performance Scorecard and Exceptions Report be noted.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Landlord Services Advisory Board (Executive Working Group)

Landlord Services Performance Exceptions Report Reporting period: 1 to 30 April 26

Performance Performance Ref. April -26 Target indicator against target

Percentage of homes with energy SQ02 Target within performance ratings of C or 74.16% 75% tolerance above

Percentage of homes that meet DE01 99.81% 100% Target within the Decent Homes Standard tolerance

Percentage of homes for which all required electrical Target within HE01 98.86% 99.5% installation tolerance condition reports have been carried out

EPC- Some homes rated EPC D or below are being retrofitted under the Wave 3 project. This number will increase as the Wave 3 project continues. Over the 3-year programme, 311 homes will be improved to at least an EPC C.

Decent Homes - Nineproperties currently do not meet the Decent Homes Standard due to non‑compliance with Criterion C (modern facilities) and Criterion D (absence of SAP data).

The Warm Homes Wave 3 programme (2025-2028) will seek to improve those failing under Criterion D by March 2028 and those failing under Criterion C will be addressed under the internal structural budget for which a programme is currently being scoped, or under the joint kitchen and bathroom programme when procurement completes, in the next 5 years. Homes that are failing decent homes will be prioritised under these programmes.

EICR -Of the properties currently reported as having non‑compliant EICRs, 11 are recorded as satisfactory following inspection; however, formal compliance confirmation by WBC is still required and is being prioritised to update the reocrds. One property is void and electrically isolated, while 10 properties require remedial works identified during the most recent inspection cycle. A further 11 properties have unconfirmed dates for their last EICR and are being actively validated.

Page 1 of 3 Eighteen properties have now become overdue. Three of these are being managed by Housing Management due to significant access challenges associated with hoarding, with tailored engagement plans in place to progress access safely.

As part of the no‑access escalation process, 36 homes were issued with fixed notices in April, resulting in three completions to date. The remaining cases are being transferred to Housing Management to coordinate supported access and progress works to completion. An additional four properties are expected to enter this process from next week, ensuring continued momentum and strengthened oversight.

Percentage of homes for which all required HS01 98.98% 99.5% Target within smoke alarms have been tolerance installed

There are currently 31 smoke alarms awaiting confirmation of compliance, alongside a further 17 alarms that remain outstanding due to associated non‑compliant electrical checks. To address this, a meeting with Housing Management was held in April to agree improved recording practices during property visits, ensuring accurate and timely capture of compliance data. In parallel, the gas contractor are returning to 11 properties to confirm the testing dates of alarms that have already passed, allowing records to be updated correctly.

Percentage of non-emergency responsive repairs IW02 completed within 93% 95% Target not met 28 calendar days (Ian Williams)

Performance has improved strongly, with 93% of jobs completed within target timescales, demonstrating sustained progress in service delivery. A total of 54 jobs were completed outside of target, with variances primarily concentrated within the electrical workstream. This reflects current resource pressures; however, the contractor, Ian Williams, is actively recruiting additional operatives to strengthen capacity and support improved performance moving forward. Overall, this represents a positive trajectory, with targeted actions in place to address the remaining areas of pressure and further improve timeliness. Percentage of respondents who report that they are satisfied with Target not met IW06 the last repair 79% 85% service received (Ian Williams)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
April 26 Landlord Services Performance Exceptions Reported in MayReport 136 KB DownloadRead as text
PDF
Landlord Services Performance Scorecard and Exceptions Report [April 2026]Report 185 KB Download

At this meeting

Whole meeting

Who was there

14 of 18 attended
PR
Councillor Paul RiversChair, present
TD
Terry DaubneyVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
AL
Councillor Andrew LaughtonCommittee Member, apologies
JK
Councillor Jacquie KeenCommittee Member, apologies
AM
Councillor Alan MorrisonCommittee Member, present
RB
Rod BlackmoreCommittee Member, present
RS
Robert StratfordCommittee Member, present
DW
Dave WilliamsObserver, expected
DM
Dave MaddamsObserver, expected
AF
Alex FosterOfficer, present
AH
Annalisa HowsonOfficer, present

All 18 on the meeting page

On this subject at Waverley

Search all
  1. Landlord Services Performance Scorecard and Exceptions Report [April 2026]This decision
  2. Landlord Services Improvement Plan Update [2025-26]Noted
  3. Landlord Services Performance Scorecard and Exceptions Report May 2026Noted
  4. Landlord Services Improvement Plan UpdateNoted
  5. Landlord Services Improvement Plan Update [date]Noted
  6. Landlord Services Performance Scorecard and Exceptions Report March 2026Noted

More from Waverley Landlord Services Advisory Board (Executive Working Group)

All decisions
MeetingDecisionOutcome
30 Jul 2026 Capital Programme updateRESOLVED that the Capital Programme update be noted. Noted Open
30 Jul 2026 Council Response to Tenant Panel Proposal on Repairs, Maintenance and Service AppointmentsRESOLVED that: · the tenant panel proposal be noted, · the principles of a standardized appointments and communicatio... Noted Open
30 Jul 2026 Low Carbon Heating SolutionsRESOLVED that the Low Carbon Heating Solutions report be noted. Noted Open
30 Jul 2026 Water Hygiene ReportRESOLVED that the monthly Water Hygiene Report be noted. Noted Open
30 Jul 2026 Landlord Services Improvement Plan Update [2025-26]RESOLVED that the Landlord Services Improvement Plan update was noted. Noted Open