Waverley Borough Council
Executive, Tuesday 2 June 2026 at 7.00pm

Procurement Pipeline Report – over £200k (2025-2026)

Approved Executive 2 papers

AI summaryWaverley Executive approves start of procurement for contracts over £200k listed in pipeline appendix and delegates award decisions to senior officer, ahead of reorganisation to West Surrey Council.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFor projects in Appendix 1 of the report
Moneyover £200k thresholdApplies to contracts that may be Key Decisions
What happens nextProceed to market and awardSubject to further approvals for each contract
Who it affectsSuppliers, service areas, residentsPlus transition to West Surrey Council by 1 April 2027

What was decided

The Executive approved the start of procurement for the projects listed in Appendix 1 of the report. Report P5

Delegated authority was granted to the Joint Strategic Director for Finance and Resources, after consulting the Portfolio Holder for Finance, Assets and Property, to award the contracts once a successful bidder is selected. Report P6, 1.3

The report does not commit the council to running every listed procurement or to the stated sourcing route, and individual items may be withdrawn, expedited or deferred. Report 6.6

Why

The council's Contract Procedure Rules require Executive permission before starting any procurement that could result in a Key Decision, either because the value is over £200k or it significantly affects two or more wards. Report 1.1, 3.1

A planned pipeline gives officers time for stakeholder management, market engagement, compliance, ethical and social value checks, and agreeing the contract price model before tendering. Report 3.2, P10, P11, P12, P13, P14, P15

Submitting a single pipeline report avoids the need for many separate approval papers, making the process quicker while still meeting governance duties. Report 3.3

What happens next

If approved, the Procurement team and the relevant service area will take the listed procurements to market, then run the award process and obtain the necessary approvals. Report 4.1, P18

A separate report will come back to Executive for award of any contract that remains a Key Decision, unless authority has been specifically delegated to an officer. Report 3.4

Further legal advice will be sought once a direction under section 24 of the Local Government and Public Involvement in Health Act 2007 is issued, expected by 30 June 2026, which may require Shadow West Surrey Council consent for certain contracts. Report 8.6, 8.7, 8.8, P45

The money

  • over £200k Threshold above which Executive must approve start of procurement as a potential Key Decision Report 1.1
  • greater than £100m (inc VAT) Annual third party spend level that would trigger publication of pipeline notices under the Procurement Act 2023 Report 6.5
  • over £2m (inc VAT) Estimated contract value above which individual pipeline notices would have to be published every 18 months Report 6.5

Options considered

  • Chosen: Bring a consolidated procurement pipeline to Executive at intervals, saving officer and Executive time and reducing procurement timescales. Reflects a more strategic, planned approach and is good governance Report 11.1, P55
  • Rejected: Bring each individual procurement item to Executive in a separate report. Would take more officer time and cost to write Report P56

Implications

  • Legal: No direct legal implications from the report itself, though project specific legal advice will be given during each procurement. Once a section 24 direction is in place, certain contracts above set values will need Shadow West Surrey Council consent. Report P61, P62, P63, 8.6
  • Financial: Finance approval is required before each procurement starts. Values in Appendix 1 are the total anticipated over the whole contract period, not annual costs. Report P58, P59, P60
  • Legal: The Surrey (Structural Changes) Order 2026 took effect on 10 March 2026. Contracts entered into under this approval must be necessary and proportionate for continued service delivery up to and beyond transfer to West Surrey Council on 1 April 2027. Any transaction in breach of a section 24 direction would be void and unenforceable. Report 8.3, 8.4, P39, 8.5, 8.9
  • Equalities: No equality and diversity implications for this report. The Public Sector Equality Duty will be considered by project teams for each procurement. Report 12.3, P65, P66, P69
  • Climate: No climate change or sustainability implications for this report. Such implications will be considered by the project team for each procurement. Report 12.4, 12.5
  • Risk: Risk that the new Contract Procedure Rules need more Procurement team and service area resource to draft Executive papers, and that without a planned pipeline there is a higher risk of non compliant spend and contracts expiring before re procurement. Report 10.1, 10.2
  • Staffing: The Procurement team is establishing a pipeline to prioritise resources for both Waverley Borough Council and Guildford Borough Council, and to consider collaboration with Guildford and other councils on each project. Report 6.3, 6.4, 8.1, 8.2

Who and where

  • Waverley Borough Council Procurement team and service areas Report 6.3, 10.1
  • Guildford Borough Council, as a potential collaboration partner Report 6.3, 6.4, 8.1
  • Suppliers, including small and medium enterprises and the voluntary, community and social enterprise sector Report 7.2
  • Shadow West Surrey Council and West Surrey Council, in light of reorganisation on 1 April 2027 Report 8.3, 8.5, 8.6
  • Residents receiving services that will transfer to West Surrey Council Report 8.4, 8.5

Timeline

  • 10 March 2026: Surrey (Structural Changes) Order 2026 came into effect Report 8.3
  • 14 April 2026: Previous procurement pipeline presented to Executive Report 1.2
  • expected by 30 June 2026: Anticipated issuing of a direction under section 24 of the Local Government and Public Involvement in Health Act 2007 Report 8.6
  • 1 April 2027: Vesting Day for transfer of functions to West Surrey Council Report 8.3

Plain English for the jargon

  • Key Decision: An Executive decision where the contract award value is over £200k or the matter significantly affects two or more wards.
  • Contract Procedure Rules (CPRs): The council's internal rules setting out how procurement and contract awards must be carried out, updated in June 2024.
  • Procurement Act 2023: UK legislation governing public procurement, with stronger obligations for SME and VCSE access and requirements to publish pipeline notices where annual third party spend is high.
  • Section 24 direction: A direction under the Local Government and Public Involvement in Health Act 2007 that can restrict a council entering certain contracts or financial transactions without the consent of a successor authority.
  • Shadow West Surrey Council: The shadow authority preparing for the transfer of Waverley and Guildford functions to a new West Surrey Council.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 13/25

Resolved

Resolved that Commencement of the procurement process for the project(s) listed in Appendix 1 of the agenda report be approved. Delegated authority be granted to the Joint Strategic Director for Finance and Resources, having consulted with the Portfolio Holder for Finance, Assets and Property and upon selection of a successful ... EXE 13/25
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

1.1The Council’s Contract Procedure Rules (CPRs) provides that Executive must give permission to commence any procurement activity which could result in the contract award being a Key Decision as the estimated value is greater than £200k or it significantly impacts two or more wards.

1.2This report provides an update of the procurement pipeline which was presented to Executive on 14 April 2026. The pipeline set out in Appendix 1 includes additional projects which are likely to result in Key Decisions and seeks Executive agreement for procurements to commence.

1.3In addition, delegated authority is sought for the Strategic Director for Finance and Resources, having consulted with the Portfolio Holder for Finance, Assets and Property and upon selection of a successful contractor following an appropriate tendering process, to enter contracts for the award of the projects set out in Appendix 1.

Recommendations

2.1That the Executive resolves to:

2.1.1 Approve commencement of the procurement process for the project(s) listed in Appendix 1 to this report.

2.1.2 Delegate authority to the Joint Strategic Director for Finance and Resources, having consulted with the Portfolio Holder for Finance, Assets and Property and upon selection of a successful contractor, to award the contract(s) as listed in Appendix 1.

3 Reason(s) for recommendation:

3.1The Executive is required to approve, prior to their commencement, all procurement activity which may require a Key Decision for the contract award. It is good governance to seek approval by providing Executive with a summary of all proposed procurements that may result in a Key Decision prior to procurement procedures formally commencing. 2 Procurement Pipeline Report – over £200k (2025-2026)

3.2Planning procurement activity ensures:

 effective stakeholder management

 effective procurement and sourcing

 compliance with relevant Procurement Legislation and the Council’s own Contract Procedure Rules

 there is consideration on how contract price is to be managed in contract and what contract price model will be used

 our procurement is ethical by considering factors such as environmental and climate change impact, social value and modern-day slavery risk

 how best value is to be achieved is clearly defined, including how contract management will ensure that the Council attains best value during the life of the contract.

3.3This report will avoid the need to submit multiple individual requests for approval to procure and award contracts, therefore being more agile in the approval process in relation to procurement activity.

3.4When a procurement activity is concluded Executive approval for any consequent contract award which would be a Key Decision will be sought by a separate report, unless authority is specifically delegated to an officer.

4 Next steps

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
_WBC Procurement Pipeline May26 (EX0206) 13/25Appendix 1 505 KB Download
PDF
Procurement Pipeline Report: over £200k (2025-2026)Report 1 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
PF
Councillor Paul FollowsChair, present
LT
Councillor Liz Townsend BEMVice Chair, present
JC
Councillor Janet CroweCommittee Member, apologies
AD
Councillor Adam DuceCommittee Member, present
TF
Councillor Tony FaircloughCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
GL
Councillor Gemma LongCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, apologies
PR
Councillor Paul RiversCommittee Member, present

On this subject at Waverley

Search all
  1. Procurement Pipeline Report – over £200k (2025-2026)This decision
  2. Procurement Pipeline Report – over £200k (2026-27)Approved
  3. Procurement Pipeline (March 2026 update)Approved
  4. Procurement PipelineApproved
  5. Procurement Pipeline (January update)Approved
  6. Procurement Pipeline Report - over £200k (2025-2026)Approved

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open