Waverley Borough Council
Executive, Tuesday 10 February 2026 at 7.00pm

Procurement Pipeline

Approved Executive 2 papers

AI summaryWaverley Executive approved starting procurement for projects in Appendix 1 and delegated contract award authority to the Joint Strategic Director for Finance and Resources.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedProcurement to begin for Appendix 1 projects, with award authority delegated
MoneyNot stated
What happens nextProcurement to proceed to marketAward process and approvals to follow conclusion of tender
Who it affectsProcurement pipeline projectsContents of Appendix 1 not in supplied papers

What was decided

The Executive approved the commencement of the procurement process for the projects listed in Appendix 1 to the report. Report 2.1

The Executive delegated authority to the Joint Strategic Director for Finance and Resources, after consulting the Lead Councillor for Finance and on selection of a successful contractor, to award the contracts in Appendix 1. Report 2.1

Why

The Council's Contract Procedure Rules require the Executive to approve procurement activity that could result in a Key Decision, where the estimated value is greater than £200k or the activity significantly impacts two or more wards. Report 1.1, P2, P3, 3.1

A consolidated pipeline approach saves officer and Executive time and supports a more strategic, planned approach to procurement. Report 11.1, P39

Forward planning supports effective stakeholder management, compliance with procurement legislation, ethical procurement considering environmental and social value factors, and clear definition of how best value is achieved. Report P9, P10, P11, P12, P13, P14

What happens next

The Procurement team and the relevant Service Area will proceed to market for the procurements listed in Appendix 1. Report 4.1, P15

On conclusion of the procurement exercise, the team will proceed to the award process and obtain relevant approvals. Report 4.1, P15

Where a contract award would be a Key Decision, Executive approval will be sought by a separate report unless authority is delegated to an officer.

The money

  • £200k Threshold above which procurement requires Executive approval as a potential Key Decision Report P3
  • £100m (inc VAT) Potential in-year third party spend threshold that would trigger publication of pipeline notices under the Procurement Act 2023
  • £2m (inc VAT) Estimated value threshold for individual pipeline notices under the Procurement Act 2023

Options considered

  • Chosen: Bring a consolidated pipeline of procurement activity at periodic intervals. Saves officer and Executive time, reduces procurement time, reflects a more strategic planned approach Report 11.1, P39
  • Rejected: Bring each individual item to the Executive. Will incur more time and cost writing individual reports Report P40

Implications

  • Financial: Finance approval is sought prior to any procurements commencing; the contract values in Appendix 1 are the total anticipated over the contract period. Report P41
  • Legal: No direct legal implications arise from this report; the Procurement and Legal teams will provide project-specific advice throughout the process. Report P42, P43
  • Equalities: No equality and diversity implications for this report; the Public Sector Equality Duty applies to individual procurement decisions. Report 12.3, P45, P46, P47, P48
  • Climate: No climate change or sustainability implications for this report; these will be considered by the relevant project team for each procurement. Report 12.4, 12.5, P51
  • Risk: The new Contract Procedure Rules require more resource from the Procurement team and Service areas; without planned pipelines there is heightened risk of non-compliant spend and contracts expiring before re-procurement. Report P34, P35, 10.1, 10.2
  • Other: Local Government Reorganisation implications will be considered at the point of procurement, with contracts designed to remain flexible in scope, duration, break clauses and governance. Report P30

Who and where

  • Suppliers and potential bidders for projects listed in Appendix 1 (contents not in the supplied papers) Report 6.7, P28, P29
  • Small and medium enterprises and the voluntary, community and social enterprise sector, with attention to removing barriers to bidding Report P29
  • Guildford Borough Council, considered as a potential collaboration partner for procurement activity Report 6.3, 6.4, 8.1, P30

Timeline

  • June 2024: New Contract Procedure Rules introduced, requiring Executive agreement before procurement for Key Decisions Report 6.1, P21
  • 13 January 2026: Previous procurement pipeline presented to the Executive Report 1.2
  • 2026-02-10: Executive decision to approve commencement of procurement and delegate award authority
  • After approval: Procurement team and Service Area to proceed to market for Appendix 1 procurements Report 4.1, P15

Plain English for the jargon

  • CPRs: Contract Procedure Rules, the Council's rules governing procurement
  • Key Decision: A contract award with an estimated value above £200k or one that significantly impacts two or more wards
  • VCSE: Voluntary, Community and Social Enterprise sector
  • SMEs: Small and Medium Enterprises
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 31/25

Resolved

RESOLVED that: Commencement of the procurement process for the project(s) listed in Appendix 1 to the agenda report be approved. delegated authority be granted to the Joint Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor, to award ... EXE 31/25
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

1.1The Council’s Contract Procedure Rules (CPRs) provides that Executive must give permission to commence any procurement

1 Procurement Pipeline Report – over £200k (2025-2026)

activity which could result in the contract award being a Key Decision as the estimated value is greater than £200k or it significantly impacts two or more wards.

1.2This report provides an update of the procurement pipeline which was presented to Executive on 13 January 2026. The pipeline set out in Appendix 1 includes additional projects which are likely to result in Key Decisions and seeks Executive agreement for procurements to commence. 1.3 In addition, delegated authority is sought for the Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor following an appropriate tendering process, to enter contracts for the award of the projects set out in Appendix 1.

Recommendations

2.1That the Executive resolves to: 2.1.1 Approve commencement of the procurement process for the project(s) listed in Appendix 1 to this report. 2.1.2 Delegate authority to the Joint Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor, to award the contract(s) as listed in Appendix 1.

3 Reason(s) for recommendation:

3.1The Executive is required to approve, prior to their commencement, all procurement activity which may require a Key Decision for the contract award. It is good governance to seek approval by providing Executive with a summary of all proposed procurements that may result in a Key Decision prior to procurement procedures formally commencing.

3.2Planning procurement activity ensures:

 effective stakeholder management

 effective procurement and sourcing 2 Procurement Pipeline Report – over £200k (2025-2026)

 compliance with relevant Procurement Legislation and the Council’s own Contract Procedure Rules

 there is consideration on how contract price is to be managed in contract and what contract price model will be used

 our procurement is ethical by considering factors such as environmental and climate change impact, social value and modern-day slavery risk

 how best value is to be achieved is clearly defined, including how contract management will ensure that the Council attains best value during the life of the contract. 3.3 This report will avoid the need to submit multiple individual requests for approval to procure and award contracts, therefore being more agile in the approval process in relation to procurement activity. 3.4 When a procurement activity is concluded Executive approval for any consequent contract award which would be a Key Decision will be sought by a separate report, unless authority is specifically delegated to an officer.

4 Next steps

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
_WBC Procurement Pipeline Feb26 31/25Appendix 1 114 KB Download
PDF
Procurement PipelineReport 367 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
PF
Councillor Paul FollowsChair, present
LT
Councillor Liz Townsend BEMVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
AD
Councillor Adam DuceCommittee Member, present
TF
Councillor Tony FaircloughCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
GL
Councillor Gemma LongCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, present
PR
Councillor Paul RiversCommittee Member, present

On this subject at Waverley

Search all
  1. Procurement PipelineThis decision
  2. Procurement Pipeline Report – over £200k (2026-27)Approved
  3. Procurement Pipeline Report – over £200k (2025-2026)Approved
  4. Procurement Pipeline (March 2026 update)Approved
  5. Procurement Pipeline (January update)Approved
  6. Procurement Pipeline Report - over £200k (2025-2026)Approved

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open