Resolved
RESOLVED That the report from SIAS which detailed the progress made to date and changes to the Plan for the remainder of year be noted.
Audit Committee noted this item on Monday 15 January 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the report from SIAS which detailed the progress made to date and changes to the Plan for the remainder of year be noted.
Members are recommended to note the Internal Audit Progress Report and approve amendments to the Audit Plan as at 2 January 2018 Contents
1 Introduction and Background 1.1 Purpose 1.2 Background
2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.6 Proposed Amendments to Audit Plan 2.7 High Priority Recommendations 2.9 Performance Management
A Progress against the 2017/18 Audit Plan
B 2017/18 Audit Plan Projected Start Dates
C Definitions of Assurance and Recommendation Priorities
Page 1 1. Introduction and Background Purpose of Report
1.1This report provide Members with details of the:
a) Progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s Annual Audit Plan for 2017/18 as at 2 January 2018. b) Findings for the period 29 September 2017 to 2 January 2018. c) Details of changes to the planned start dates of audits from the approved 2017/18 Audit Plan. d) Proposed amendments to the approved 2017/18 Council Audit Plan. e) An update on performance management information as at 2 January 2017.
1.2The 2017/18 Annual Audit Plan was approved by the Audit Committee at its meeting on 3 April 2017.
1.3The Audit Committee receives periodic updates of progress against the Annual Internal Audit Plan. This is the third report giving feedback on the delivery of the 2017/18 Internal Audit Plan.
1.4The work of Internal Audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit provision is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed annual audit plan.
2. Audit Plan Update Delivery of Audit Plan and Key Audit Findings
2.1As at 2 January 2018, 58% of the 2017/18 Audit Plan days had been delivered (the calculation excludes contingency). Appendix A provides a status update on each individual project within the audit plan.
2.2The following final reports have been issued since our October progress report to the Committee:
Audit Title Date of Assurance Number of Issue Level Recommendations Awarding of October Substantial 2 Merits Attention Increments 2017 Private Sector October Substantial N/A Tenancy 2017 DFG Grant October N/A N/A Certification 2017
Page 2 Joint Review November N/A N/A Prevent (16/17) 2017 December 3 Medium Safeguarding Substantial 2017 1 Merits Attention 1 High Anti-Fraud December Moderate 5 Medium Arrangements 2017 1 Merits Attention Equality and December Substantial 3 Merits Attention Diversity 2017 December 2 Medium Open Data Moderate 2017 4 Merits Attention
2.3A summary is provided below of the medium priority recommendations made in the Safeguarding and Anti-Fraud Arrangement reviews.
Audit Title Control Area and Summary of Response / Recommendations Implementation Date Safeguarding Case Log Spreadsheet
We recommend that the Safeguarding Case Log 31 March 2018 spreadsheet is updated to ensure that the following information is recorded:
Date that the referral was received and the reported incident date; Date that the referral was passed to an appropriate body; Indicator confirming when / if acknowledgement was received from an appropriate body; Outcomes from phone calls relating to Safeguarding referrals; or Outcomes and dates of further involvement / action taken by WHBC. Following Up Incidents and Missing Information
We recommend that management review the 31 March 2018 current practices for following up incidents and chasing up missing information, with a view to implementing a formal process. Website – Accessibility of Safeguarding Information
We recommend that the website is reviewed and 31 December updated to ensure that there is sufficient 2017
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
SHARED INTERNAL AUDIT SERVICE (SIAS) INTERNAL AUDIT PROGRESS REPORTReport | 348 KB | DownloadRead as text |
Follow Audit Committee at Welwyn Hatfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | External audit plan and strategy 2025/26RESOLVED To note the External Audit Plan and Strategy 2025/26. | Noted | Open |
| 2 Sep 2026 | Rebuilding assurance updateTo note the Rebuilding Assurance Update. | Noted | Open |
| 2 Sep 2026 | Internal audit (sias) - progress report 2026/27To: a) Note the Internal Audit Progress Report for the period to 17 August 2026; b) Note the implementation of status... | Noted | Open |
| 2 Sep 2026 | Internal audit (sias) - annual report 2025/26To note the Shared Internal Audit Service Annual Report 2025/26. | Noted | Open |
| 2 Sep 2026 | Shared anti-fraud service (safs) - progress report 2026/27To note the progress by officers and the Shared Anti-Fraud Service to deliver the Anti-Fraud Plan. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.