Resolved
The overall position as at Quarter 1 of 2019/20 on the capital programme, and the update of the capital funding and reserves position was noted.
Cabinet noted this item on Tuesday 6 August 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
The overall position as at Quarter 1 of 2019/20 on the capital programme, and the update of the capital funding and reserves position was noted.
1.1This report presents the capital expenditure and associated capital funding as at the end of quarter 1 2019/20. The report and appendices detail the changes to the original 2019/20 capital programme and funding plans, as a result of programme commitments and project delivery.
1.2The current approved capital budget is £63.031m including re-phasing of £28.904m from 2018/19, which was approved by Cabinet on 4 June 2019. The current forecast outturn is £63.072m. A summary of forecast variances and re phasing are shown in Table 1 and detailed explanations for key variances in section 3.3.
1.3A summary of progress against key projects for which no variances have been reported is contained within section 3.4.
1.4A forecast of the resources available to fund the capital programme and variances of the current forecast against the available resources budgeted are set out in section 4 of this report.
2.1The Cabinet note the capital forecast outturn position as at Quarter 1.
2.2That Cabinet approve re-phasing and virements for the Affordable Housing Programme set out in section 3.3.
2.3The Cabinet to note the forecast position as at 31 March 2020 for funding of the capital programme and reserve balances as reflected in Table 2
3 Capital Programme – Expenditure Forecasts
3.1The capital expenditure position is summarised in Table 1 below and a detailed breakdown by capital scheme can be found in Appendix A.
-1- Table 1: Capital Expenditure Forecast by Head of Service and Corporate Director Period 3 2019/20 Current Budget Re- Forecast (Under) / 2019/20 Forecast phasing of Description Outturn Over (including Variance Capital 2019/20 Forecast 2018/19 roll Schemes forwards) £'000 £'000 £'000 £'000 £'000 GENERAL FUND
Head of Planning 1,140 1,140 0 0 0
Head of Public Health and Protection 111 111 0 0 0 Corporate Director - Public Protection, Planning and Governance 1,252 1,252 0 0 0
Head of Resources 24,435 24,435 0 0 0
Head of Environment 9,032 5,480 (3,552) 3,552 (0)
Head of Policy and Culture 245 245 0 0 0 Corporate Director - Resources, Environment & Cultural Services 33,712 30,160 (3,552) 3,552 (0)
Head of Community & Housing Strategy (Gen Fund) 992 992 0 0 0 Corporate Director - Housing and Communities (Gen Fund) 992 992 0 0 0
TOTAL General Fund 35,956 32,404 (3,552) 3,552 (0) HOUSING REVENUE ACCOUNT
Head of Community & Housing Strategy 12,755 16,348 3,593 (3,593) (0)
Head of Housing Property Services 14,314 14,314 0 0 0
Head of Housing Operations 6 6 0 0 0 Corporate Director - Housing and Communities (HRA) 27,075 30,668 3,593 (3,593) (0)
TOTAL Housing Revenue Account 27,075 30,668 3,593 (3,593) (0)
TOTAL 63,031 63,072 41 (41) 0
3.2There is currently requirement to re-phase a net £41k from 2020/21 as follows:
GRF £3.552m - re phase budget into 2020-21 HRA (£3.593m) – re phase budget from/to 2020-21
The HRA capital programme will therefore increase by £3.593m in 2019/20 and decrease by same amount in 2020/21. The GRF capital programme will decrease by £3.552m in 2019/20 and increase by same amount in 2020/21. Overall this is still within the five year approved capital programme approved by Council in February 2019.
3.3Key forecast variances are outlined below:
-2- Housing Revenue Account:
3.3.1 Rephasing £3.593m - Affordable Housing Programme (129-145)
Following the final out-turn position as at 31st March 2019 , there has been a number of changes to schemes, including re-phasing of works, an increase in the number of directly delivered sites, and new schemes being approved (such as Chequersfield) early 2019, the budget requires virements to be actioned as set out in the table below:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
9a: Appendix AAppendix | 221 KB | Download |
PDF |
QUARTER 1 CAPITAL BUDGET MONITORING REPORT 2019/20Report | 556 KB | DownloadRead as text |
Follow Cabinet at Welwyn Hatfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. | Approved | Open |
| 8 Sep 2026 | ApologiesNo apologies for absence were received. | Decided | Open |
| 8 Sep 2026 | Actions status reportCabinet noted the Action Status report. | Noted | Open |
| 8 Sep 2026 | Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. | Decided | Open |
| 8 Sep 2026 | Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.