QUARTER 2 CAPITAL BUDGET MONITORING REPORT 2019/20

Noted Executive 2 papers

Cabinet noted this item on Tuesday 5 November 2019. Below is the council's own wording, with the papers it was decided on.

Item64

Resolved

(1) The capital forecast outturn position as at Quarter 2 of 2019/20 was noted. (2) The forecast position as at 31 March 2020 for funding of the capital programme and reserve balances was noted.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1This report presents the capital expenditure and associated capital funding as at the end of quarter 2 2019/20. The report and appendices detail the changes to the original 2019/20 capital programme and funding plans, as a result of programme commitments and project delivery.

1.2The current approved capital budget is £66.624m and the current forecast outturn is £43.080m. A summary of forecast variances and re phasing are shown in Table 1 and detailed explanations for key variances in section 3.3.

1.3A summary of progress against key projects for which no variances have been reported is contained within section 3.4.

1.4A forecast of the resources available to fund the capital programme and variances of the current forecast against the available resources budgeted are set out in section 4 of this report.

Recommendations

2.1The Cabinet note the capital forecast outturn position as at Quarter 2 as shown in Table 1

2.2The Cabinet to note the forecast position as at 31 March 2020 for funding of the capital programme and reserve balances as reflected in Table 2

3 Capital Programme – Expenditure Forecasts

3.1The capital expenditure position is summarised in Table 1 below and a detailed breakdown by capital scheme can be found in Appendix A.

-1- Table 1: Capital Expenditure Forecast by Head of Service and Corporate Director Period 6 2019/20 Current Forecast Budget Forecast Re- (Under) / 2019/20 (incl. Forecast Description Outturn phasing Over re phasing Variance 2019/20 at Period Forecast approved at 6 Qtr 1) £'000 £'000 £'000 £'000 £'000 GENERAL FUND

Head of Planning 1,140 1,140 0 0 0

Head of Public Health and Protection 111 111 0 0 0

Corporate Director - Public Protection, Planning and Governance 1,252 1,252 0 0 0

Head of Resources 24,435 12,449 (11,986) 10,815 (1,171)

Head of Environment 9,032 4,780 (4,252) 4,252 0

Head of Policy and Culture 245 245 0 0 0

Corporate Director - Resources, Environment & Cultural Services 33,712 17,474 (16,238) 15,067 (1,171) Head of Community & Housing Strategy (Gen Fund) 992 992 0 0 0

Corporate Director - Housing and Communities (Gen Fund) 992 992 0 0 0 TOTAL General Fund 35,956 19,718 (16,238) 15,067 (1,171)

HOUSING REVENUE ACCOUNT

Head of Community & Housing Strategy 16,348 12,511 (3,837) 2,553 (1,284)

Head of Housing Property Services 14,314 10,845 (3,469) 3,469 0

Head of Housing Operations 6 6 0 0 0

Corporate Director - Housing and Communities (HRA) 30,668 23,362 (7,306) 6,022 (1,284) TOTAL Housing Revenue Account 30,668 23,362 (7,306) 6,022 (1,284) TOTAL 66,624 43,080 (23,544) 21,089 (2,455)

3.2There is currently requirement to re-phase a net £21.089m as follows:

GRF £15.067m – re-phase budget into 2020-21 HRA £6.022m – re-phase budget into 2020-21 Total net re-phasing - £21.089m

3.3Key forecast variances are outlined below:

General Fund:

3.3.1 Re-phasing of £11.986m - Resources

£1.058m – Splashlands Development (App A ref. no 12)

The tender process for the main contractor as well as the site operator has concluded, and the planning application has now been approved. Works are expected to commence later this year, and the first meeting between the -2- Council, contractor and operator has already taken place. Based on the initial scope of works and the successful contractor’s tendered programme, it is anticipated that at least £1.058m will re-phase to the next financial year. The budget profile may need to be reviewed further once contractor has provided a more detailed programme of works.

£1.303m – Hatfield Town Centre 1 & 3-9 (App A ref. no 16)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
11a: Appendix AAppendix 99 KB Download
PDF
QUARTER 2 CAPITAL BUDGET MONITORING REPORT 2019/20Report 260 KB DownloadRead as text

At this meeting

Whole meeting
59ACTIONS STATUS REPORTOn the agenda 60aLocalised Council Tax Support Scheme 2020/21 (Forward Plan Reference FP928)Decided 60bDuty of Care Enforcement for Fly-Tipping (Forward Plan Reference FP944)Noted 60cService Standards for Regulatory Work (Forward Plan Reference FP945)Noted 61aDigital Strategy and Revenue and Benefits Transformation Programme (Forward Plan Reference FP952)Approved 61bInsurance Services Tender - Request for Delegated Authority (Forward Plan Reference FP948)Agreed 61cProfessional Building Services - Extension of Contract (Forward Plan Reference FP949)Decided 61dAmendment of the Restrictions in the Hatfield Town Centre Car Parks (Forward Plan Reference FP940)Deferred 62aIntroduction of Resident Permit Scheme, Double Yellow Lines, Verge and Footway Prohibition and Clearway in Aldykes, HatfieldDeferred 62bIntroduction of Waiting Restrictions in Various Roads, French Horn Lane, East Ward, HatfieldApproved 63QUARTER 2 REVENUE BUDGET MONITORING REPORT 2019/20Noted
64QUARTER 2 CAPITAL BUDGET MONITORING REPORT 2019/20This decision
65QUEENSWAY HOUSE CONSULTATIONNoted 66TREASURY MANAGEMENT MID-YEAR REPORT 2019/20Noted 67EXCLUSION OF PRESS AND PUBLICDecided 68aAppointment of Contractor (Forward Plan Reference FP929)Private 68bAward of Contract for Voice and Network Infrastructure Services (Forward Plan Reference FP946)Private 68cAppointment of Asbestos Consultancy (Forward Plan Reference FP947)Private 69WELWYN GARDEN CITY NORTH DEVELOPMENTPrivate 70QUEENSWAY HOUSE CONSULTATIONPrivate

Who was there

6 of 12 attended
TK
Councillor Tony KingsburyChairman, present
DB
Councillor Duncan BellVice-Chairman, present
SB
Councillor Stephen BoultonCommittee Member, apologies
TM
Councillor Terry MitchinsonCommittee Member, present
NP
Councillor Nick PaceCommittee Member, present
BS
Councillor Bernard SarsonCommittee Member, present
FT
Councillor Fiona ThomsonCommittee Member, present
RB
Rob BridgeOfficer, in attendance
KN
Ka NgOfficer, in attendance
SR
Simone RussellOfficer, in attendance
MM
Margaret MartinusOfficer, in attendance
GS
Graham SealSecretary, in attendance

On this subject at Welwyn Hatfield

Search all
  1. QUARTER 2 CAPITAL BUDGET MONITORING REPORT 2019/20This decision
  2. Quarter 1 capital monitoring report 2026/27Noted
  3. Quarter 1 Capital Budget Monitoring ReportNoted
  4. Quarter 3 capital budget monitoring report 2024-25Noted
  5. Quarter 3 Capital Budget Monitoring Report 2023-24Noted
  6. Capital budget monitoring report - quarter 2Decided

More from Welwyn Hatfield Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. Approved Open
8 Sep 2026 ApologiesNo apologies for absence were received. Decided Open
8 Sep 2026 Actions status reportCabinet noted the Action Status report. Noted Open
8 Sep 2026 Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. Decided Open
8 Sep 2026 Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies