Resolved
(1) The capital forecast outturn position as at Quarter 2 of 2019/20 was noted. (2) The forecast position as at 31 March 2020 for funding of the capital programme and reserve balances was noted.
Cabinet noted this item on Tuesday 5 November 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) The capital forecast outturn position as at Quarter 2 of 2019/20 was noted. (2) The forecast position as at 31 March 2020 for funding of the capital programme and reserve balances was noted.
1.1This report presents the capital expenditure and associated capital funding as at the end of quarter 2 2019/20. The report and appendices detail the changes to the original 2019/20 capital programme and funding plans, as a result of programme commitments and project delivery.
1.2The current approved capital budget is £66.624m and the current forecast outturn is £43.080m. A summary of forecast variances and re phasing are shown in Table 1 and detailed explanations for key variances in section 3.3.
1.3A summary of progress against key projects for which no variances have been reported is contained within section 3.4.
1.4A forecast of the resources available to fund the capital programme and variances of the current forecast against the available resources budgeted are set out in section 4 of this report.
2.1The Cabinet note the capital forecast outturn position as at Quarter 2 as shown in Table 1
2.2The Cabinet to note the forecast position as at 31 March 2020 for funding of the capital programme and reserve balances as reflected in Table 2
3 Capital Programme – Expenditure Forecasts
3.1The capital expenditure position is summarised in Table 1 below and a detailed breakdown by capital scheme can be found in Appendix A.
-1- Table 1: Capital Expenditure Forecast by Head of Service and Corporate Director Period 6 2019/20 Current Forecast Budget Forecast Re- (Under) / 2019/20 (incl. Forecast Description Outturn phasing Over re phasing Variance 2019/20 at Period Forecast approved at 6 Qtr 1) £'000 £'000 £'000 £'000 £'000 GENERAL FUND
Head of Planning 1,140 1,140 0 0 0
Head of Public Health and Protection 111 111 0 0 0
Corporate Director - Public Protection, Planning and Governance 1,252 1,252 0 0 0
Head of Resources 24,435 12,449 (11,986) 10,815 (1,171)
Head of Environment 9,032 4,780 (4,252) 4,252 0
Head of Policy and Culture 245 245 0 0 0
Corporate Director - Resources, Environment & Cultural Services 33,712 17,474 (16,238) 15,067 (1,171) Head of Community & Housing Strategy (Gen Fund) 992 992 0 0 0
Corporate Director - Housing and Communities (Gen Fund) 992 992 0 0 0 TOTAL General Fund 35,956 19,718 (16,238) 15,067 (1,171)
HOUSING REVENUE ACCOUNT
Head of Community & Housing Strategy 16,348 12,511 (3,837) 2,553 (1,284)
Head of Housing Property Services 14,314 10,845 (3,469) 3,469 0
Head of Housing Operations 6 6 0 0 0
Corporate Director - Housing and Communities (HRA) 30,668 23,362 (7,306) 6,022 (1,284) TOTAL Housing Revenue Account 30,668 23,362 (7,306) 6,022 (1,284) TOTAL 66,624 43,080 (23,544) 21,089 (2,455)
3.2There is currently requirement to re-phase a net £21.089m as follows:
GRF £15.067m – re-phase budget into 2020-21 HRA £6.022m – re-phase budget into 2020-21 Total net re-phasing - £21.089m
3.3Key forecast variances are outlined below:
General Fund:
3.3.1 Re-phasing of £11.986m - Resources
£1.058m – Splashlands Development (App A ref. no 12)
The tender process for the main contractor as well as the site operator has concluded, and the planning application has now been approved. Works are expected to commence later this year, and the first meeting between the -2- Council, contractor and operator has already taken place. Based on the initial scope of works and the successful contractor’s tendered programme, it is anticipated that at least £1.058m will re-phase to the next financial year. The budget profile may need to be reviewed further once contractor has provided a more detailed programme of works.
£1.303m – Hatfield Town Centre 1 & 3-9 (App A ref. no 16)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
11a: Appendix AAppendix | 99 KB | Download |
PDF |
QUARTER 2 CAPITAL BUDGET MONITORING REPORT 2019/20Report | 260 KB | DownloadRead as text |
Follow Cabinet at Welwyn Hatfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. | Approved | Open |
| 8 Sep 2026 | ApologiesNo apologies for absence were received. | Decided | Open |
| 8 Sep 2026 | Actions status reportCabinet noted the Action Status report. | Noted | Open |
| 8 Sep 2026 | Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. | Decided | Open |
| 8 Sep 2026 | Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.