Resolved
(1) Cabinet noted the capital forecast outturn position as at Quarter 1 as shown in Table 1. (2) Cabinet noted the forecast position as at 30 June 2021 for funding of the capital programme and reserve balances as reflected in Table 2.
Cabinet noted this item on Tuesday 10 August 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) Cabinet noted the capital forecast outturn position as at Quarter 1 as shown in Table 1. (2) Cabinet noted the forecast position as at 30 June 2021 for funding of the capital programme and reserve balances as reflected in Table 2.
1.1This report presents the capital expenditure and associated capital funding as at the end of quarter 1. The report and appendices detail the changes to the original capital programme and funding plans, as a result of programme commitments and project delivery.
1.2The current approved capital budget is £95.442m (which includes the approved re-phasing of budgets from 2020/21) and the forecast outturn is £95.442m. There are currently no forecast variances and no forecast re phasing as shown in Table 1.
1.3A summary of progress against key projects for which no variances have been reported is detailed within section 3.3.
1.4A forecast of the resources available to fund the capital programme and variances of the current forecast against the available resources budgeted are set out in section 4 of this report.
2.1That Cabinet note the capital forecast outturn position as at Quarter 1 as shown in Table 1.
2.2The Cabinet to note the forecast position as at 30 June 2021 for funding of the capital programme and reserve balances as reflected in Table 2.
3 Capital Programme – Expenditure Forecasts
3.1The capital expenditure position is summarised in Table 1 below and a detailed breakdown by capital scheme can be found in Appendix A. Table 1: Capital Outturn 2021/22 by Fund and Head of Service
Re- Forecast Variance phasing (Under)/ Budget Outturn to of Over 2021/22 2021/22 Budget Capital Outturn Schemes
£'000 £'000 £'000 £'000 £'000 General Fund Planning 1,031 1,031 0 0 0 Public Health and Protection 52 52 0 0 0
Public Protection, Planning and Governance 1,083 1,083 0 0 0 Resources 12,417 12,417 0 0 0 Environment 19,425 19,425 0 0 0 Policy and Culture 150 150 0 0 0 Resources, Environment & Cultural Services 31,992 31,992 0 0 0 Community & Housing Strategy 1,688 1,688 0 0 0
Housing and Communities 1,688 1,688 0 0 0
General Fund Total 34,763 34,763 0 0 0 Now Housing 11,548 11,548 Housing Revenue Account Total Head of Community & Housing Strategy 31,915 31,915 0 0 0 Housing Property Services 16,346 16,346 0 0 0 Housing Operations 870 870 0 0 0
Housing and Communities 49,131 49,131 0 0 0 Housing Revenue Account Total 49,131 49,131 0 0 0
Grand TOTAL 95,442 95,442 0 0 0
3.2There is currently no requirement to re-phase any budget into 2022/23 and there are no forecast variances at Quarter 1. 3.3 Progress of key capital scheme expenditure:
This section provides members with additional information on the progress of high value projects (over £2.0m) for which no variance or re-phasing has been reported, and highlights any risks identified which may cause a variance or re phasing to the project to be reported at a later date.
General Fund:
3.3.1 Redevelopment of 1 and 3-9 Town Centre Hatfield £2.344m (App A ref. no 11):
This scheme progresses well. Following the demolition of the remaining block, enabling works including hoarding, and utilities diversions have commenced with active works being undertaken on site. The deadline for spending the Homes England grant has been extended from March 2021 to March 2022.
3.3.2 Welwyn Garden City Town Centre North £3.961m (App A ref. no 13):
At the end of the quarter, it was anticipated the application would imminently be submitted for the upper deck to Campus West Car Park, and is estimated to be presented to committee in Autumn 2021. The tender for the residential developer at Campus East car park has concluded, with a recommendation being made to Cabinet.
3.3.3 Bereavement Services £7.176 (App A ref. no 39):
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
9: Capital Monitoring Appendix A v2Appendix | 55 KB | Download |
PDF |
QUARTER 1 CAPITAL BUDGET MONITORING REPORT 2021-22Report | 256 KB | DownloadRead as text |
Follow Cabinet at Welwyn Hatfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. | Approved | Open |
| 8 Sep 2026 | ApologiesNo apologies for absence were received. | Decided | Open |
| 8 Sep 2026 | Actions status reportCabinet noted the Action Status report. | Noted | Open |
| 8 Sep 2026 | Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. | Decided | Open |
| 8 Sep 2026 | Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.