Resolved
(1) Cabinet noted the capital forecast outturn position as shown in Table 1. (2) Cabinet noted the forecast position as at 30 June 2022 for funding of the capital programme and reserve balances as reflected in Table 2.
Cabinet noted this item on Tuesday 9 August 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) Cabinet noted the capital forecast outturn position as shown in Table 1. (2) Cabinet noted the forecast position as at 30 June 2022 for funding of the capital programme and reserve balances as reflected in Table 2.
1.1This report presents the capital expenditure and associated capital funding as at the end of Quarter 1 (June 2022). The report and appendices detail the changes to the original capital programme and funding plans, as a result of programme commitments and project delivery.
1.2The current approved capital budget is £176.385m (which includes the approved re- phasing of budgets from 2021/22) and the forecast outturn is £171.392m. A summary of forecast variances and re-phasing are shown in Table 1 and detailed explanations for key variances in Section 3.4.
1.3A summary of progress against key projects for which no variances have been identified is detailed within Section 3.5.
1.4A forecast of the resources available to fund the capital programme and variances of the current forecast against the available resources budgeted are set out in Section 4 of this report.
2.1That Cabinet note the capital forecast outturn position as shown in Table 1.
2.2That Cabinet note the forecast position as at 30 June 2022 for funding of the capital programme and reserve balances as reflected in Table 2.
3 Capital Programme – Expenditure Forecasts
Capital Budgets
3.1The following table tracks approved changes to the original budget during the year, which impact on reserves.
£ Original Budget £118.794m Re-phasing from 2021/22 £57.591m Current Budget £176.385m
3.2The capital expenditure position is summarised in Table 1 below and a detailed breakdown by capital scheme can be found in Appendix A. Table 1: Capital Outturn 2022/23 by Fund and Head of Service
Re- Variance phasing (Under)/ Budget Outturn to of Over 2022/23 2022/23 Budget Capital Outturn Schemes
£'000 £'000 £'000 £'000 £'000 General Fund Planning 1,031 1,031 0 0 0 Public Health and Protection 51 51 0 0 0 Public Protection, Planning and Governance 1,082 1,082 0 0 0 Resources 11,361 11,361 0 0 0 Environment 15,700 16,424 724 0 724 Policy and Culture 200 200 0 0 0 Resources, Environment & Cultural Services 27,261 27,985 724 0 724 Community & Housing Strategy 2,013 2,013 0 0 0
Housing and Communities 2,013 2,013 0 0 0
General Fund Total 30,356 31,080 724 0 724 NOW HOUSING 72,118 72,118 0 0 0 Housing Revenue Account Housing Property Services 30,436 30,436 0 0 0 Housing Operations 597 597 0 0 0 Community & Housing Strategy 42,878 37,162 (5,716) 5,716 0
Housing and Communities 73,911 68,195 (5,716) 5,716 0 Housing Revenue Account Total 73,911 68,195 (5,716) 5,716 (0)
Grand TOTAL 176,385 171,392 (4,992) 5,716 724 3.3 There is currently a requirement to re-phase £5.716m of budget into 2023/24.
3.4Key forecast variances are outlined below:
General Fund:
3.4.1 Bereavement Services £0.500m adverse forecast variance (App A ref. 44)
UK Power Networks originally planned to run an electricity supply into the site as part of this project, however despite a previous assessment done by them, they have now discovered the local network does not have enough capacity to do this. A substation therefore needs to be built at the Council’s expense. This is very frustrating from the council’s point of view but is the only option available and will incur a cost of approximately £0.500m. The business plan remains viable despite this increase in costs.
Unfortunately, some materials for the site were damaged in transit and as a result need to be manufactured again. There is no impact on the cost of the project, and the project team is working with the contractor to minimise the impact on the timeline of the project.
3.4.2 Tewin Road Depot Upgrade / Household Waste and Recycling Centre £0.400m adverse forecast variance (App A ref. 48 and 49)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
8: Q1 Appendix A v2Appendix | 133 KB | Download |
PDF |
QUARTER 1 CAPITAL BUDGET MONITORING REPORT 2022-23Report | 169 KB | DownloadRead as text |
Follow Cabinet at Welwyn Hatfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. | Approved | Open |
| 8 Sep 2026 | ApologiesNo apologies for absence were received. | Decided | Open |
| 8 Sep 2026 | Actions status reportCabinet noted the Action Status report. | Noted | Open |
| 8 Sep 2026 | Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. | Decided | Open |
| 8 Sep 2026 | Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.