Welwyn Hatfield Borough Council
Cabinet, Tuesday 10 February 2026 at 6.30pm

Q3 CAPITAL BUDGET MONITORING REPORT 2025/26

Noted Executive 2 papers

AI summaryWelwyn Hatfield Cabinet notes £74.341m capital forecast outturn and approves £0.940m virement to fund three affordable housing property purchases.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted the capital forecast and approved virements
MoneyNot stated
What happens nextRephase £18.992m to 2026/27£1.200m General Fund, £17.792m Housing Revenue Account
Who it affectsAll wards in Welwyn HatfieldCapital schemes across General Fund and HRA

What was decided

Cabinet noted the capital forecast outturn position set out in Table 1, showing total forecast spend of £74.341m against a £101.376m budget. Report P4, P5

Cabinet noted the funding and reserve balances forecast at 31 December 2025 as set out in Table 2. Report P5

Cabinet approved a virement of £0.940m from the AHP New Schemes budget to the AHP Open Market Purchases budget to fund three affordable housing properties. Report P5

Why

Two affordable housing properties have already been purchased for £0.425m, and a further three are being acquired at a cost of £0.940m, requiring a virement from the AHP New Schemes budget to the Open Market Purchases budget.

What happens next

£1.200m of General Fund budget and £17.792m of Housing Revenue Account budget will be rephased into the 2026/27 financial year. Report 3.5, P21

Schemes rephased include Angerland football and rugby improvements, Howlands House, Burfield, Haseldine Meadows, Lockley Crescent and Howard House, with work on most continuing into 2026/27.

The report notes that small overspends on General Fund projects will be funded by borrowing.

The money

  • £101.376m Current approved capital budget Report P4, P12
  • £74.341m Forecast capital outturn 2025/26 Report P4, P19
  • £55.990m Original capital budget Report P7
  • £29.199m Re-phasing from 2024/25 Report P8
  • £15.700m Additional budget for Gatehouse purchase Report P9
  • £0.020m Additional budget for Outdoor Energy Gym Report P10
  • £0.793m Additional budget for Food Waste Recycling project Report P11
  • £0.940m Virement from AHP New Schemes to AHP Open Market Purchases
  • £18.992m Total rephasing into 2026/27 Report 3.5, P21
  • £1.200m General Fund rephasing into 2026/27 Report 3.5, P21
  • £17.792m Housing Revenue Account rephasing into 2026/27 Report 3.5, P21
  • £3.986m Affordable Housing Programme, Ludwick Green budget
  • £24.674m Major Repairs budget
  • £6.040m Insulation Improvements budget
  • £2.003m Major Repairs (other contractors) budget

Options considered

  • Chosen: Approve virement of £0.940m from AHP New Schemes to AHP Open Market Purchases. To fund the purchase of three properties for affordable housing

Implications

  • Legal: No direct legal implications, but individual projects will require legal input on procurement and contractual documentation. Report P30
  • Risk: No risk management implications arise directly from the report. Report P32
  • Staffing: No security, terrorism, procurement, climate change, health and wellbeing, communications, equality and diversity, or HR implications arise directly from the report. Report P33, P34, P35, P37, P38

Who and where

  • Residents of Welwyn Hatfield across all wards Report P1
  • Tenants in council housing affected by rephased housing schemes including Howlands House, Howard House, Haseldine Meadows, Lockley Crescent, Birchwood and Hatfield Town Centre
  • Affordable housing applicants benefiting from the three additional properties being purchased
  • Hatfield Town Council, in connection with football development at Birchwood Leisure Centre

Timeline

  • 31 December 2025: Forecast position date for capital funding and reserve balances Report P5
  • 2026/27: £1.200m General Fund and £17.792m Housing Revenue Account budget rephased into this financial year Report 3.5, P21
  • End of 2025/26: Affordable Housing Programme at Ludwick Green due to complete
  • End of March: Major Repairs planned works programme expected to complete

Plain English for the jargon

  • Virement: A transfer of budget from one scheme or cost centre to another within the council's approved budget.
  • Rephasing: Moving budgeted spend from one financial year into a later one because work will not now be completed in the original year.
  • AHP: Affordable Housing Programme, a council scheme to provide affordable housing through new builds and acquisitions.
  • HRA: Housing Revenue Account, the ring-fenced account that holds income and spending on council housing.
  • MRP: Minimum Revenue Provision, the amount the council must set aside from revenue each year to repay capital borrowing.
  • Section 106 funding: Money paid by developers through a planning agreement, earmarked for specific local infrastructure or facilities.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item555

Resolved

Decision Taken Cabinet: a) Noted the capital forecast outturn position as shown in Table 1. b) Noted the forecast position as at 31 December 2025 for funding of the capital programme and reserve balances as reflected in Table 2. c) Approved the virements set out in Section 3.2.
Word for word from the decision Welwyn Hatfield published for this meeting. Source: democracy.welhat.gov.uk

Follow this further

Built from Welwyn Hatfield's papers

What the report saysPro

Report to Cabinet

Part I Item No: 0 Main Author: Helen O’Keeffe Executive Member: Cllr Astrid Scott All Wards

WELWYN HATFIELD BOROUGH COUNCIL CABINET – 10 FEBRUARY 2026 REPORT OF THE EXECUTIVE DIRECTOR (FINANCE AND TRANSFORMATION)

QUARTER 3 CAPITAL BUDGET MONITORING REPORT 2025-26

1 Executive Summary 1.1 This report presents the capital expenditure and associated capital funding as at the end of Quarter 3 (December 2025). The report and appendices detail the changes to the original capital programme and funding plans, as a result of programme commitments and project delivery. 1.2 The current approved capital budget is £101.376m (which includes the approved re- phasing of budgets from 2024/25) and the forecast outturn is £74.341m. A summary of forecast variances and re-phasing are shown in Table 1 and detailed explanations for key variances in Section 3.6. 1.3 A summary of progress against key projects for which no variances have been identified is detailed within Section 3.7. 1.4 A forecast of the resources available to fund the capital programme and variances of the current forecast against the available resources budgeted are set out in Section 4 of this report.

2 Recommendations 2.1 That Cabinet note the capital forecast outturn position as shown in Table 1. 2.2 That Cabinet note the forecast position as at 31 December 2025 for funding of the capital programme and reserve balances as reflected in Table 2. 2.3 That Cabinet approve the virements set out in Section 3.2.

3 Capital Programme – Expenditure Forecasts Capital Budgets 3.1 The following table tracks approved changes to the original budget during the year (excluding fully funded virements).

£ Original Budget £55.990m

Re-phasing from 2024/25 £29.199m

Additional budget for Gatehouse purchase £15.700m

Additional budget for Outdoor Energy Gym £0.020m

Additional budget for Food Waste Recycling project £0.793m

Removal of incorrect roll-forwards from 24/25 (Hatfield Town Centre (£0.326m) Public Realm, Play Area Replacement Scheme and Hatfield Town Centre Market Place) Current Budget £101.376m 3.2 It is recommended that the following virements be approved: • That £0.940m from the AHP – New Schemes budget (App A ref. 47) be vired to the AHP – Open Market Purchases budget (App A ref. 36) to fund the purchase of three properties which are to be used for affordable housing. 3.3 The capital expenditure position is summarised in Table 1 below and a detailed breakdown by capital scheme can be found in Appendix A. Table 1 uses rounded figures so there may be slight addition discrepancies. 3.4 Table 1: Capital Outturn 2025/26 by Fund and Directorate

Re- Variance phasing (Under)/ Budget Outturn to of Over 2025/26 2025/26 Budget Capital Budget Schemes

£'000 £'000 £'000 £'000 £'000

General Fund Executive Director (Finance and Transformation) 229 170 (59) 0 (59)

Executive Director (Place) 18,652 17,628 (1,024) 1,200 176 Executive Director (Resident Services and Climate Change) 2,820 2,425 (394) 0 (394)

General Fund Total 21,701 20,224 (1,477) 1,200 (277) Housing Revenue Account

Executive Director (Place) 17,690 8,019 (9,671) 9,016 (655) Executive Director (Res Services and Climate Change) 61,985 46,098 (15,887) 8,776 (7,111) Housing Revenue Account Total 79,675 54,117 (25,558) 17,792 (7,766)

Grand TOTAL 101,376 74,341 (27,035) 18,992 (8,044)

3.5There is currently a requirement to rephase £18.992m split between funds as follows:

General Fund £1.200m – rephase budget into 2026/27 Housing Revenue Account £17.792m – rephase budget into 2026/27 Total rephasing - £18.992m into 2026/27

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 3 Appendix A Q3 2526Appendix 181 KB Download
PDF
Q3 CAPITAL BUDGET MONITORING REPORT 2025/26Report 243 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 17 attended
BC
Bernice ComptonOfficer, in attendance
RM
Roxanne MisirSecretary, apologies
SB
Councillor Sandreni BonfanteCommittee Member, present
JB
Councillor James BroachCommittee Member, absent
MH
Councillor Max HollowayCommittee Member, present
JQ
Councillor Jane QuintonCommittee Member, present
KN
Ka NgOfficer, in attendance
RB
Richard BakerOfficer, in attendance
HO
Helen O'KeeffeOfficer, apologies
JH
Jenny HowellOfficer, apologies
MS
Michael SherryCouncil Staff, in attendance
CC
Clare CadeOfficer, in attendance

All 17 on the meeting page

On this subject at Welwyn Hatfield

Search all
  1. Q3 CAPITAL BUDGET MONITORING REPORT 2025/26This decision
  2. Capital budget monitoring report q2Noted
  3. Quarter 1 Capital Budget Monitoring ReportNoted
  4. Quarter 3 capital budget monitoring report 2024-25Noted
  5. Capital Budget Monitoring Report Q2Noted
  6. Period 3 capital budget monitoring report 2024-25Noted

More from Welwyn Hatfield Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. Approved Open
8 Sep 2026 ApologiesNo apologies for absence were received. Decided Open
8 Sep 2026 Actions status reportCabinet noted the Action Status report. Noted Open
8 Sep 2026 Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. Decided Open