REVISED CAPITAL PROGRAMME AND MID YEAR REVIEW 2016/2017

Approved Committee 6 papers

Council approved this item on Wednesday 14 December 2016. Below is the council's own wording, with the papers it was decided on.

Item69

Resolved

A. That the revised Capital Programme, including the re-profiling, virements and budget adjustments contained within Appendix A to the report, be approved. B. That progress against the revised Capital Programme at the mid-year point be noted.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Council

Purpose of report

1.1To agree a Revised Capital Programme for 2016/2017 and provide Members with an overview on the progress against it at the mid-year point.

2.0RECOMMENDATIONS TO CABINET

2.1That the Revised Capital Programme, including the re-profiling, virements and budget adjustments contained within Appendix A, be approved for consideration by Council.

2.2That the progress against the Revised Capital Programme at the mid-year point be noted.

2.3That Call In is not appropriate for this item as the report is being submitted to the next meeting of the Executive Overview and Scrutiny Committee on 24th November and Council on 14th December.

3.0RECOMMENDATIONS TO EXECUTIVE OVERVIEW AND SCRUTINY COMMITTEE

3.1That the Revised Capital Programme and progress against it at the mid-year point be noted.

4.0RECOMMENDATIONS TO COUNCIL

4.1That the revised Capital Programme, including the re-profiling, virements and budget adjustments contained within Appendix A, be approved. 4.2 That progress against the Revised Capital Programme at the mid-year point be noted.

Background

5.1The GRA Capital Programme is set on a three-year rolling basis and the Programmes for 2016/2017, 2017/2018 and 2018/2019 were approved by Council in February 2016. A one year HRA Capital Programme was agreed by Council in February 2016 as a result of the difficult financial position facing the HRA. This programme will be reviewed in the light of the HRA Policy Options report agreed by Council in October 2016.

5.2In accordance with best practice, the Capital Programme is subject to revision at the mid-year point to ensure that it is based on the latest available information and to make monitoring of the Programme more meaningful. It enables Managers to review their schemes with the most up to date information and to review the resources available. It also provides a base upon which to build future Capital Programmes.

5.3Members are kept informed of the financial position of the Capital Programme through regular monitoring reports. The last such report was presented to Cabinet in September 2016 and reported on a total Capital Programme of £21.569m for 2016/2017. This comprised a GRA Programme of £5.734m and a Housing Public Sector Capital Programme of £15.835m.

6.0REVISED CAPITAL PROGRAMME

6.1Heads of Service have reviewed their respective schemes and are now proposing that changes are made as a result of more up to date information that has become available. This review process has incorporated a number of considerations including:  Re-profiling of schemes  Changes to external funding availability  Levels of anticipated funding required and available  Anticipated levels of demand

6.2The proposed changes to the 2016/2017 Programme are analysed in Appendix A. This shows an overall increase of £2.082m for the GRA, primarily as a result of the inclusion of the purchase of the Wheatsheaf Walk site in Ormskirk, which was agreed by Council in May 2016.

6.3The revised GRA Capital Programme totals £7.816m for 2016/2017 following these changes. This is analysed by service in Appendix B along with a summary of the revised capital resources available.

6.4The proposed changes to the HRA would reduce the size of the programme from £15.835m to £14.750m, primarily as the result of re-profiling expenditure on the Bathroom replacement scheme into the next financial year. 7.0 CAPITAL EXPENDITURE

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
, 08/11/2016 Cabinet, 24/11/2016 Executive Overview & Scrutiny CommitteeAppendix A 22 KB Download
PDF
, 08/11/2016 Cabinet, 24/11/2016 Executive Overview & Scrutiny CommitteeAppendix Ai 252 KB Download
PDF
, 08/11/2016 Cabinet, 24/11/2016 Executive Overview & Scrutiny CommitteeAppendix B 14 KB Download
PDF
, 08/11/2016 Cabinet, 24/11/2016 Executive Overview & Scrutiny CommitteeAppendix Bi 233 KB Download
PDF
, 08/11/2016 Cabinet, 24/11/2016 Executive Overview & Scrutiny CommitteeAppendix C 39 KB Download
PDF
REVISED CAPITAL PROGRAMME AND MID YEAR REVIEW 2016/2017Report 166 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

48 of 62 attended
LS
Councillor Liz SavageMayor, present
NF
Councillor Neil FureyDeputy Mayor, present
TA
Councillor Terry AldridgeCommittee Member, present
IA
Councillor Iain AshcroftCommittee Member, present
SB
Councillor Susan BaileyCommittee Member, present
MB
Councillor Malcolm BarronCommittee Member, present
MP
Councillor Mrs Pam BaybuttCommittee Member, apologies
MM
Councillor Mrs May BlakeCommittee Member, present
TB
Councillor Tom BlaneCommittee Member, present
JB
Councillor John BullockCommittee Member, present
JC
Councillor John CairnsCommittee Member, apologies
CC
Councillor Claire CooperCommittee Member, present

All 62 on the meeting page

On this subject at West Lancashire

Search all
  1. REVISED CAPITAL PROGRAMME AND MID YEAR REVIEW 2016/2017This decision
  2. Q2 gra revised capital programmeNoted
  3. Revised Capital ProgrammeApproved
  4. Revised capital programmeApproved
  5. Capital mid year monitoring and revised programmeApproved
  6. Revised Capital ProgrammeApproved

More from West Lancashire Council

All decisions
MeetingDecisionOutcome
15 Jul 2026 MinutesThat the minutes of the Council meetings held on Wednesday, 20 May 2026, be received as a correct record and signed b... Decided Open
15 Jul 2026 Minutes of committeesRESOLVED That the minutes of the undermentioned meetings and any recommendations contained in them, be approved: A. L... Approved Open
15 Jul 2026 Public speakingThat the Motion to extend the deadline be approved. Approved Open
15 Jul 2026 GRA Outturn 2025/26A. That the draft revenue outturn position of the 2025/26 GRA be noted. B. That it be noted that only £80k of the £86... Noted Open
15 Jul 2026 2025/26 GRA Capital OutturnRESOLVED A. That the Capital outturn position be noted, and the proposed Capital allocation set out in Appendix 1 to ... Noted Open