A. That the draft financial outturn position of the 2022/23 HRA and Capital Investment Programme be noted and that the use of HRA reserves be noted. B. That the switching of funding from HRA borrowing to HRA revenue contributions in paragraph 5.4 be noted. C. That capital slippage identified in appendix one be noted.
Word for word from the decision West Lancashire published for this meeting.Source: democracy.westlancs.gov.uk
1.1To provide a summary of the Housing Revenue Account (HRA) revenue and capital outturn positions for the 2022/23 financial year.
Recommendations
2.1That the draft financial outturn position of the 2022/23 HRA and Capital Investment Programme be noted and that the use of HRA reserves be noted.
2.2That the switching of funding from HRA borrowing to HRA revenue contributions in paragraph 5.4 be noted.
2.3That capital slippage identified in appendix one be noted.
Background
3.1The cost of living crisis has impacted both the HRA and housing capital budgets, as well as our residents. The effect on district heating scheme residents of energy price rises was reported in year, as was the effect of contract inflation on the repairs contract.
3.2This is expected to continue in 2023/24, with April 2023 CPI at 8.7% and tenant rents for the year limited to 7% This means additional budget pressure is likely. In addition, the 2023/24 local Government pay offer is greater than the amount budgeted, and is still subject to negotiation and agreement, so may increase further.
4.0HOUSING REVENUE ACCOUNT – REVENUE OUTTURN
4.1A summary of the draft HRA revenue outturn is set out in the table below. This shows that an adverse budget variance of £0.188m was achieved at the year end, which represents 0.7% of the total budget. Given the challenges during the year presented by the cost of living crisis, greater than anticipated pay settlement and increased use of agency staff to fill key vacant posts, this represents good financial performance.
2022/23 Outturn Latest Budget Area Variance Comment Budget £000 £000 Pay settlement more than budgeted and use of agency staff to cover Employee Expenses 3,884 136 vacant posts. Unbudgeted work on review of Property Services structure funded from contingency. Void repairs and 4,504 194 2022/23 contract variation. response repairs £370k District Heating scheme, overall shortfall – debtor used to balance to zero at year end. See Other premises costs 3,708 141 para 4.6 below. Pressure from other energy costs, disrepair costs and electrical testing. Transport costs 162 18 Vehicle recharges.
Budget contingency 390 -50 Most contingency used.
Stock condition costs after use of Supplies and Services 1,254 179 £238k contingency Support Services and 2,627 -75 Partly due to variable recharges internal income (net) Loan interest & Contribution towards 3,419 10 Repayment Contribution to general fund scheme Contributions to capital 7,485 -51 not utilised TVD stock increases during year. Dwelling rents -24,300 -74 68 Right to Buy (RTB) sales. Furnished lettings service, Interest on balances due to rising interest Other external income -3,133 -240 rates, 68 RTB admin fee income, contribution to hardship payments. Total 0 188 0.7% of total budget 4.2 The main budget pressures in 2022/23 were: • Pay settlement larger than budgeted by around £100k. • Use of agency staff to fill key vacant posts. • Rising energy costs. • Higher Contract inflation, particularly on the key repairs contract.
4.3These were partially offset by a favourable position on:
• Rents from additional affordable rent properties, built by TVDL and brought on- line in 2022/23 • Continued increased need for furnished tenancies in the tenant furnishing service generating income. This is partially offset by additional expenditure on growing the service • Planned maintenance revenue budgets were largely unused pending development of the new programme.
4.4The table below shows how outturn compares to in-year estimates of outturn.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.