Draft Community Infrastructure Levy Funding Programme 2024-2026

Approved Executive 6 papers

Cabinet approved this item on Tuesday 26 September 2023. Below is the council's own wording, with the papers it was decided on.

Item115

Resolved

A. That the public consultation on a Draft CIL Funding Programme for 2023 be approved, and the shortlist of infrastructure projects identified at paragraphs 6.1 and 6.2 of this report be included in that consultation: · Holmeswood Play Area Fence Replacement, Rufford and Holmeswood Parish Council - £3,000 · Holmeswood MUGA (Phase 2), Rufford and Holmeswood Parish Council - £13,000 · Replacement Bus Shelters Rufford Holmeswood , Rufford and Holmeswood Parish Council - £9,900 · Rufford Park Play Area, Rufford and Holmeswood Parish Council - £4,500 · Aughton Surgery, - increase capacity to deliver GP and primary care NHS provision, NHS Lancashire and South Cumbria Integrated Care Board (ICB) - £50,000 · Hall Green Surgery, Skelmersdale - increase capacity to deliver GP and primary care NHS provision - £25,000 · Hants Lane Clinic, Ormskirk - increase capacity for the provision of GP and primary care services, NHS Lancashire and South Cumbria ICB - £50,000 · Fairy Glen Green Infrastructure Improvements, WLBC - £55,000 · Environmental site enhancements at Kiln Lane and Tongbarn playing fields, Skelmersdale, WLBC - £62,700 · Halsall-Scarisbrick Canal Towpath Improvements, Canal and River Trust - £175,095.14 CIL requirement · UK Shared Prosperity Fund (UKSPF) Community Grant Scheme Match Funding, WLBC - £355,000 CIL requirement · Beacon Country Park Play Area Improvements, WLBC - £346,500 B. That the public consultation on the spending of Neighbourhood CIL monies in Ormskirk be approved, and that the shortlist identified at paragraph 6.3 of this report be included in that consultation: · Whittle Drive Changing Facilities, WLBC - £40,000 · West End Park Improvements, WLBC - £80,000 · Halsall Lane Park Improvements, WLBC - £16,500 · Green Lane Rugby Pitch Improvements, Ormskirk Rugby Club - £9,261.97 · Whittle Drive Pitch Improvements, Ormskirk West End Football Club - £6,100 C. That delegated authority be given to the Head of Planning and Regulatory Services to carry out the public consultations set out in paragraphs A. and B. above.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1.1To seek authority to conduct public consultation on the draft CIL Funding Programme for 2023/24-2025/26, including options regarding which infrastructure projects might be prioritised to receive CIL funding in 2023/24 -2025/26.

2.0RECOMMENDATIONS TO EXECUTIVE OVERVIEW & SCRUTINY COMMITTEE

2.1That the Committee note the content of this report and agreed comments be passed to Cabinet for their consideration.

3.0RECOMMENDATIONS TO CABINET

3.1That Cabinet, having regard to the content of this report and to the agreed comments of Executive Overview & Scrutiny Committee, approve the public consultation on a Draft CIL Funding Programme for 2023, and that the shortlist of infrastructure projects identified at paragraphs 6.1 and 6.2 of this report be included in that consultation.

3.2That the public consultation on the spending of Neighbourhood CIL monies in Ormskirk be approved, and that the shortlist identified at paragraph 6.3 of this report be included in that consultation.

3.3That delegated authority be given to the Head of Planning and Regulatory Services to carry out the public consultations set out in paragraphs 3.1 and 3.2.

4.0BACKGROUND 4.1 The Council has been charging a Community Infrastructure Levy (CIL) on certain new developments in its area since 1st September 2014. A significant portion (70 or 80%, The Strategic Portion) of the revenue that is collected is to be used to fund the provision, improvement, replacement, operation or maintenance of infrastructure to support new development in West Lancashire.

4.215 or 25% of the revenue collected is handed over to the Parish or Town Council in which the development occurred (the higher percentage is where the Parish or Town Council has opted to make a Neighbourhood Plan) – this is known as the Neighbourhood Portion. In areas where there is no Parish Council, such as Skelmersdale and Ormskirk, any Neighbourhood Portion of CIL is retained by the Council to be spent on projects in the locality.

4.3The Council's Infrastructure Funding Statement sets out the types of infrastructure that will be provided using CIL monies. There are three main types of infrastructure identified: • Strategic transport and highways improvements – to include cycle network provision and improvements, footpaths, bus stops; • Strategic green infrastructure – including improvements to and provisions of: parks, amenity open space, play areas, outdoor sports facilities and playing pitches, semi-natural open space; • Community Facilities – including libraries, health facilities, community centres, public realm, leisure centres.

4.4The Council approved a CIL and Section 106 Governance and Expenditure Framework (The Framework) in 2015 that set out the structure of the CIL Funding Programme for the allocation and spending of developer contributions collected through CIL and Section 106 obligations; this document was last updated in 2020.

4.5The Framework explains how the Council will invite stakeholders to submit projects that they want to be funded, either in whole or part, by CIL monies collected by the Council. These projects are then considered against set criteria, shortlisted by Council Officers and added to the Infrastructure Delivery Schedule (IDS).

4.6The IDS is a working document which is regularly updated. The IDS identifies infrastructure projects and improvements which may be needed to support the growth and development set out within the West Lancashire Local Plan. It includes information on infrastructure schemes, projects costs and funding gaps along with timescales and delivery partners.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CIL Funding Programme Appendix A: Overview of all CIL BidsAppendix 87 KB Download
PDF
CIL Funding Programme Appendix B i WLBC Bids Inc AmendmentsAppendix 3.2 MB Download
PDF
CIL Funding Programme Appendix B ii Parish Council BidsAppendix 20 MB Download
PDF
CIL Funding Programme Appendix B iii External BidsAppendix 1.8 MB Download
PDF
CIL Funding Programme Appendix C: IDS 2023Appendix 188 KB Download
PDF
Draft Community Infrastructure Levy Funding Programme 2024-2026Report 209 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 42 attended
YG
Councillor Yvonne GagenLeader of the Council, present
GD
Councillor Gareth DowlingDeputy Leader of the Council, present
CC
Councillor Carl CoughlanCommittee Member, present
VC
Councillor Vickie CumminsCommittee Member, present
AM
Councillor Anne Mary FennellCommittee Member, present
NF
Councillor Neil FureyCommittee Member, present
RM
Councillor Rob MolloyCommittee Member, present
NP
Councillor Nicola Pryce-RobertsCommittee Member, present, as expected, virtual
AY
Councillor Adam YatesCommittee Member, present
JS
Jacqui Sinnott-LaceyOfficer, in attendance
CT
Chris TwomeyOfficer, expected
JP
James PierceOfficer, expected

All 42 on the meeting page

On this subject at West Lancashire

Search all
  1. Draft Community Infrastructure Levy Funding Programme 2024-2026This decision
  2. Community infrastructure levy (cil) funding programme 2025 - becconsall heritage park bid reviewDecided
  3. Community Infrastructure Levy (CIL) Funding Programme 2025Noted
  4. Allocation of community infrastructure levy (cil) funding for phase 2 upgrades to burscough wellbeing & leisure hubApproved
  5. Report on the neighbourhood community infrastructure levy (ncil) portion to parish/town councils 01 october 2024 to 31 march 2025Noted
  6. Community Infrastructure Levy (CIL) Funding Programme 2024Noted

More from West Lancashire Cabinet

All decisions
MeetingDecisionOutcome
26 Mar 2024 MINUTESThat the minutes of the Cabinet meeting held on 6 February 2024 be received as a correct record and signed by the Lea... Decided Open
26 Mar 2024 Council performance delivery – q3 2023/24A. That the Council’s performance for its key performance indicators for the quarter ended 31 December 2023 be noted.... Noted Open
26 Mar 2024 Corporate Performance Reporting 2024/25A. That the delivery plan at Appendix 1 be approved for reporting as the Council Priorities Delivery Plan. B. That th... Approved Open
26 Mar 2024 2023-24 GRA Revenue Q3 Monitoring ReportThat the 2023/24 GRA position be noted and endorsed. Noted Open
26 Mar 2024 GRA Capital Programme Q3 Monitoring ReportA. That the revised Capital Programme, including budget adjustments and re-profiling contained within Appendix A to t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies