Future of Leisure: Feasibility Funding for Skelmersdale and Ormskirk

Approved Committee 3 papers

AI summaryWest Lancashire Council reallocates £500,000 for leisure feasibility work in Skelmersdale and Park Pool refurbishment, with further reports due in April.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedReallocation of leisure funding approved
Money£500,000Reallocated within capital programme
What happens nextApril: further reportsTo Working Group and Full Council
Who it affectsSkelmersdale and Ormskirk leisurePark Pool, Nye Bevan centres

What was decided

The Council approved the reallocation of £500,000 from the existing Leisure Facilities Project allocation within the approved capital programme, granting delegated authority to the Director of Planning, Economy and Wellbeing to procure feasibility, design and technical work for leisure provision in Skelmersdale and Park Pool refurbishment. Report P1

Further reports will come back in April to the Leisure Operations Working Group and full Council, setting out the preferred option, costs, delivery route, timescales and funding strategy, before any planning submission or external funding application. Report P1

Ormskirk's full leisure transformation is noted as Phase 2, to follow Local Government Reorganisation after new provision in Skelmersdale, and a report on essential repairs to Nye Bevan and Park Pool will go to the next Full Council meeting. Report P1

Why

To fund feasibility, design and technical work for new leisure provision in Skelmersdale and refurbishment of Park Pool. Report P1

To ensure continued operation of Nye Bevan and Park Pool centres for the coming 5 years through a programme of essential repairs. Report P1

What happens next

The Director of Planning, Economy and Wellbeing will bring further reports in April to the Leisure Operations Working Group and full Council detailing the preferred option, costs, delivery route, timescales and funding strategy. Report P1

A report on the programme of essential repairs for Nye Bevan and Park Pool centres will be brought to the next meeting of Full Council. Report P1

No planning submission or external funding application will be made until the further reports have been considered. Report P1

The money

  • £500,000 Reallocation from existing Leisure Facilities Project allocation monies within the approved capital programme for feasibility, design and technical work Report P1

Implications

  • Financial: £500,000 is reallocated within the existing capital programme to fund feasibility and design work. Report P1
  • Other: Full transformation of leisure in Ormskirk is deferred to Phase 2, to be delivered after Local Government Reorganisation and after new Skelmersdale provision is in place. Report P1
  • Other: Nye Bevan and Park Pool centres must remain operational for the coming 5 years pending further decisions. Report P1

Who and where

  • Leisure users and residents in Skelmersdale Report P1
  • Users and residents of Park Pool, Ormskirk Report P1
  • Users and residents of Nye Bevan centre Report P1

Timeline

  • April: Further reports to be brought to Leisure Operations Working Group and full Council on preferred option, costs, delivery route, timescales and funding strategy Report P1
  • Next meeting of Full Council: Report on the programme of essential repairs for Nye Bevan and Park Pool centres Report P1
  • Coming 5 years: Continued operation of Nye Bevan and Park Pool centres to be ensured Report P1

Plain English for the jargon

  • Local Government Reorganisation: The restructuring of local government arrangements, referenced as the trigger for moving to Phase 2 of the leisure transformation programme
  • Phase 2: The second stage of the leisure transformation programme, covering full transformation of leisure in Ormskirk
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item81

Resolved

A. That Council approves the reallocation of £500,000 from the existing Leisure Facilities Project allocation monies within the approved capital programme and delegated authority be granted to the Director of Planning, Economy and Wellbeing to procure and deliver feasibility, design and technical work for future delivery of leisure provision in Skelmersdale along with the refurbishment of Park Pool. B. That the Director of Planning, Economy and Wellbeing, shall subsequently bring back further reports to the Leisure Operations Working Group and full Council, in April, detailing the preferred option, associated costs, delivery route, timescales and funding strategy and before any planning submission or external funding application is made. C. That Council notes that the full transformation of leisure in Ormskirk will be delivered as Phase 2 of the leisure transformation programme following Local Government Reorganisation once new provision has been provided in Skelmersdale. D. That the Director of Planning, Economy & Wellbeing to bring a Report to the next Meeting of the Full Council setting out the programme of essential repairs for both Nye Bevan and Park Pool centres, to ensure continued operation for the coming 5 years.
Word for word from the decision West Lancashire published for this meeting. Source: democracy.westlancs.gov.uk

Follow this further

Built from West Lancashire's papers

What the report saysPro

Report to Council

FUTURE OF LEISURE: FEASIBILITY FUNDING FOR SKELMERSDALE AND ORMSKIRK Amendment to be moved by Councillor Bailey 2.1 That Council approves the reallocation of £500,000 from the existing Leisure Facilities Project allocation monies within the approved capital programme and delegated authority be granted to the Director of Planning, Economy and Wellbeing to procure and deliver feasibility, design and technical work for future delivery of leisure provision in Skelmersdale along with the refurbishment of Park Pool. 2.2 That the Director of Planning, Economy and Wellbeing, shall subsequently bring back further reports to the Leisure Operations Working Group and full Council, in April, detailing the preferred option, associated costs, delivery route, timescales and funding strategy and before any planning submission or external funding application is made. 2.3 That Council notes that the full transformation of leisure in Ormskirk will be delivered as Phase 2 of the leisure transformation programme following Local Government Reorganisation once new provision has been provided in Skelmersdale. 2.4 That the Director of Planning, Economy & Wellbeing to bring a Report to the next Meeting of the Full Council setting out the programme of essential repairs for both Nye Bevan and Park Pool centres to ensure continued operation for the coming 5 years.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Amdt Cllr Bailey FUTURE OF LEISUREReport 72 KB DownloadRead as text
PDF
Future direction of Leisure Service in Nye Bevan and Park Pool EIAReport 135 KB Download
PDF
Future of Leisure: Feasibility Funding for Skelmersdale and OrmskirkReport 141 KB Download

At this meeting

Whole meeting

Who was there

41 of 54 attended
AM
Councillor Anne Mary FennellMayor, present
SP
Councillor Suresh PatelDeputy Mayor, present
JA
Councillor Judy AbbottCommittee Member, present
TA
Councillor Terry AldridgeCommittee Member, present
MA
Councillor Mark AndersonCommittee Member, present
RB
Councillor Robert BaileyCommittee Member, present
AB
Councillor Alexander BlundellCommittee Member, present
PB
Councillor Patricia BurnsideCommittee Member, present
CC
Councillor Carl CoughlanCommittee Member, present
VC
Councillor Vickie CumminsCommittee Member, present
TD
Councillor Terence DevineCommittee Member, present
GD
Councillor Gareth DowlingCommittee Member, present

All 54 on the meeting page

On this subject at West Lancashire

Search all
  1. Future of Leisure: Feasibility Funding for Skelmersdale and OrmskirkThis decision
  2. Future Leisure Investment Programme UpdateNoted
  3. Future direction of the Wellbeing and Leisure ServiceNoted

More from West Lancashire Council

All decisions
MeetingDecisionOutcome
15 Jul 2026 MinutesThat the minutes of the Council meetings held on Wednesday, 20 May 2026, be received as a correct record and signed b... Decided Open
15 Jul 2026 Minutes of committeesRESOLVED That the minutes of the undermentioned meetings and any recommendations contained in them, be approved: A. L... Approved Open
15 Jul 2026 Public speakingThat the Motion to extend the deadline be approved. Approved Open
15 Jul 2026 GRA Outturn 2025/26A. That the draft revenue outturn position of the 2025/26 GRA be noted. B. That it be noted that only £80k of the £86... Noted Open
15 Jul 2026 2025/26 GRA Capital OutturnRESOLVED A. That the Capital outturn position be noted, and the proposed Capital allocation set out in Appendix 1 to ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies