(1) The proposed re-base of the CRSTS programme, as per DfT’s invitation to all Mayoral Combined Authorities in receipt of CRSTS funding, to reflect inflationary scheme cost pressures was approved. (2) It was noted that the net overprogramming value of £160.2m (15%) remained unchanged from the value agreed by the WMCA Board in June 2023. (3) The intention to undertake a ‘CRSTS stock take’ once commitments reach c.£900m to allow the WMCA and sponsors to accurately quantify the precise over-programming value and re-confirm the regional appetite for spending CRSTS2 funding at risk in line with soft contingency principles previously agreed was noted. (4) The requirements of the DfT set out within the report were noted. (5) The approval timeline was noted. (6) It was noted that WMCA/TfWM continued to manage on-going cost pressures on major transport infrastructure projects outside the CRSTS programme, as reported to WMCA Board in June 2023. (7) An early warning on Rail Package 1 (Willenhall and Darlaston Stations) due to the main contractor for the project going into administration was noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
2.1The CRSTS is a £1.050bn programme of transport improvements across the West Midlands. The programme is spread over a 5-year funding period covering financial years 2022/23 – 2026/27 with a requirement that all funding is spent and all delivery complete by the end of March 2027.
2.2In the Spring Budget it was announced that £8.8bn would be available nationally for the second round of CRSTS (CRSTS 2). The WMCA allocation for this has not yet been determined.
2.3WMCA and GMCA are also currently in dialogue with Government around the concept of receiving single thematic funding pots for specific functions (including Transport), where those funding allocations will align to Comprehensive Spending Review timelines. This has the potential to further enhance the strategic planning of Transport interventions beyond 2027.
Re-base context
2.4A number of CRSTS eligible MCA’s have raised that, given the high rate of inflation since the creation of the original programme, delivery of all the outputs outlined in initial programmes developed over 2021 and submitted in January 2022 will be unaffordable. In acknowledgment of this, the Department for Transport and HM Treasury have agreed to permit a one-time only re-base of the CRSTS programmes. This situation is consistent with previous reporting to WMCA Board where inflationary cost pressures have been highlighted.
2.5This re-base must be agreed locally before being submitted to DfT by 29th September 2022 for approval. The following conditions must be met as part of this exercise:
• Projects can be removed from the programme or added but DfT have emphasised this should not be seen as an opportunity to introduce brand new initiatives. • All projects must align with the objectives of the national CRSTS programme. • The total funding envelope must remain the same. • Overall, the target 15-20% local contribution must be met. • The outputs can be reduced. • The funding time horizons must remain the same (spend and delivery by March 2027). • The re-based programme submitted to DfT will need to demonstrate that it still delivers good value for money. WMCA re-baselining process
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.