Update Report: City Region Sustainable Transport Settlement - Quarter 3 2025/26

Noted Committee 1 paper

AI summaryWest Midlands Combined Authority Investment Board notes Quarter 3 progress on the City Region Sustainable Transport Settlement programme, with £574.9m spent to 31 December 2025.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQuarter 3 2025/26 CRSTS update received and noted
Money£574.9m spent to dateAgainst £1.171bn CRSTS1 capital settlement
What happens nextFurther updates to WMCA BoardRosewell Review short-term action plan updates
Who it affectsWest Midlands transport projects50 projects across constituent local authorities

What was decided

The Investment Board noted the progress on the CRSTS programme during Quarter 3 of Financial Year 2025/2026.

Why

The report is a quarterly monitoring update required as a condition of the CRSTS funding allocation, with WMCA acting as the accountable body. Report 6.7, 6.8

The programme aims to drive growth, decarbonise transport and level up services through a £1.171bn government grant plus £120.1m local contribution. Report 5.1, 5.2, 5.3

Spend is accelerating as more schemes move towards delivery, though actual spend remains less than envisaged at the January 2023 baseline. Report 7.6, 7.7

What happens next

WMCA will continue quarterly monitoring and evaluation reporting to the Department for Transport, with further spend of £73.0m forecast by 31 March 2026. Report 6.8, 7.7

Funding will be contractually committed before 31 March 2027, with some CRSTS Data Scheme Support and Monitoring expenditure continuing beyond that date with DfT approval. Report 7.7, 7.8, 7.9

Further updates on the Rosewell Review short-term action plan will be taken to future WMCA Board meetings. Report 9.3

The money

  • £5.7bn National CRSTS programme grant over five years 2022/23 to 2026/27 Report 5.1
  • £1.171bn West Midlands CRSTS1 government grant Report 5.3
  • £120.1m Local contribution from WMCA and Local Authorities Report 5.3
  • £1.209bn CRSTS funding approved against settlement as of 31 December 2025 Report P29
  • £574.9m Expenditure funded from CRSTS1 capital settlement to 31 December 2025 Report P29
  • £647.9m Forecast expenditure funded from CRSTS up to 31 March 2026 Report P29
  • £73.0m Further expenditure forecast January 2026 to March 2026 Report P29
  • £47.9m Additional funding approved since 30 September 2025 Report P29
  • £62.0m Additional spend since 30 September 2025 Report P29
  • £162m Projects rephased into West Midlands CRSTS1 allocation by May 2025 rebaseline Report 6.4
  • c. £108.5m Local Contribution achieved to date Report 7.12
  • £1.182bn Current expected capital CRSTS1 settlement resources
  • £1.467bn Full overprogrammed total reported in CRSTS1 Capital Funding chart Report P76

Options considered

  • Chosen: No options considered; report is a progress update only. The report states options analysis is not applicable for this monitoring update Report P52, P53

Implications

  • Financial: No direct financial implications from the recommendation; the report provides a status update on existing approved funding.
  • Legal: No legal implications arising from this report.
  • Equalities: No equalities implications arising from this report.
  • Risk: Most common risk types across the programme are budget (23%), schedule (18%) and operational (12%). Report 7.3, P78
  • Risk: Key risks include inflationary cost pressures, public objection to road space reallocation, and supply chain disruption. Report P37
  • Risk: Funding is capped and project sponsors must manage and mitigate any gross cost escalations. Report 18.2
  • Other: No procurement implications arising from this report.

Who and where

  • West Midlands Combined Authority as accountable body for CRSTS funding Report 6.7
  • Constituent and non-constituent local authority members of WMCA Report 7.10, P61, P71
  • Department for Transport as funding provider Report 5.1, 6.2
  • Scheme promoters across the 50 CRSTS projects and programmes Report 5.3, 7.2

Timeline

  • 10 June 2022: WMCA Board extended Investment Board remit to cover CRSTS programme Report 4.2
  • September 2023: Initial re-baseline of the CRSTS programme undertaken at DfT request Report 6.2
  • July 2024: Further changes set out capital and programme pressures and project deferrals Report 6.3
  • 9 May 2025: WMCA Board approved rebaseline report rephasing £162m of projects Report 6.4
  • August 2025: Department for Transport approval of the rebaseline received Report 6.5
  • 31 December 2025: Reporting cut-off date for Q3 progress data Report P28
  • 30 January 2026: WMCA submitted Q3 financial year 25/26 update to DfT Report 6.8
  • 13 February 2026: Rosewell Review / Transport for City Regions report considered by WMCA Board Report 9.2
  • 23 March 2026: Investment Board meeting noting Q3 2025/26 CRSTS progress
  • 31 March 2027: Deadline for CRSTS1 funding to be contractually committed Report 7.7

Plain English for the jargon

  • CRSTS: City Region Sustainable Transport Settlement, a government grant programme for transport investment in England's largest city regions
  • DfT: Department for Transport
  • WMCA: West Midlands Combined Authority
  • M&E: Monitoring and Evaluation
  • RAG: Red, Amber, Green status indicator for project performance
  • TCR: Transport for City Regions, the period following the CRSTS settlement
  • Rebaseline: A formal revision of the programme's planned cost, schedule or scope
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item154

Resolved

Resolved that : The progress on the CRSTS programme during Quarter 3 of the Financial Year 2025/2026 be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Investment Board

Background

4.1The Investment Board was established by the WMCA Board as a key element of the approvals process across the WMCA Investment Programme.

4.2On 10 June 2022, WMCA Board approved extending the role and remit of WMCA Investment Board to cover all WMCA projects (including those within the CRSTS programme), allowing investment decisions to be made for values between £5m and £20m in line with the WMCA Single Assurance Framework.

4.3The Investment Board considered and endorsed an enhanced Terms of Reference at its meeting on 24th July 2020. This set out an enhanced role supporting decision- making, greater post approval controls, performance management and effective delivery of monitoring & evaluation requirements.

4.4The enhanced Terms of Reference included the following:

• To add conditions to any funding decision that falls within its delegated authority. Minimum conditions should specify the availability period, conditions to drawdown of funds, conditions for withdrawal of support and terms of clawback, start date and completion date for the project or programme. • Where oversight of monitoring and evaluation applies to the Investment Board, to consider whether a formal review of project or programme is required, and to consider this review itself or instruct the Investment Panel to do so on its behalf.

5. Overview of the CRSTS Programme

5.1The National Infrastructure Strategy committed to investments in local transport networks to improve productivity in our largest cities. The national CRSTS programme aims to deliver transformational change through investments in public and sustainable transport infrastructure in some of England’s largest city regions through grant funding of £5.7bn over five years (2022/23 – 2026/27).

5.2The CRSTS funding is aimed at achieving the following objectives:

• Driving growth and productivity;

• Decarbonising transport; and

• Levelling up services and areas

5.3The West Midlands submitted a programme level business case consisting of 50 projects and programmes totalling an investment of over £1bn in transport improvements. This investment includes a government grant of £1.171bn, along with £120.1m as a local contribution from WMCA and Local Authorities.

5.4The CRSTS funding consolidates a number of historic funding sources (including highways maintenance) and provide a very welcome five-year planning and resourcing horizon. 6. Changes to the West Midlands Region CRSTS Programme

6.1The West Midlands CRSTS programme has continued to evolve following its establishment and subsequent approval by DfT in 2022. As to be expected with a programme of this nature, changes have been required for a number for factors which have included inflationary cost pressures, externally driven scope changes and supply chain issues.

6.2An initial re-baseline of the programme was undertaken in September 2023, which was undertaken across the programme, at the request of DfT, in order to reflect inflationary construction cost pressures.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update Report: City Region Sustainable Transport Settlement: Quarter 3 2025/26Report 390 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
PH
Councillor Peter HughesChair, present
BS
Councillor Bob SleighVice-Chair, present
MB
Councillor Mike BirdCommittee Member - Voting, present, as expected, virtual
CB
Councillor Christopher BurdenCommittee Member - Voting, present
SC
Councillor Steve ClarkCommittee Member - Voting, present
MM
Councillor Majid MahmoodCommittee Member - Voting, present
JO
Councillor Jim O'BoyleCommittee Member - Voting, present
SS
Sue SummersCommittee Member - Non-Voting, apologies

On this subject at West Midlands Combined Authority

Search all
  1. Update Report: City Region Sustainable Transport Settlement - Quarter 3 2025/26This decision
  2. Rosewell Review Phase 2/ Transport for City Regions UpdateNoted
  3. Update Report City Regions Sustainable Transport Settlement Quarter 4 FY 2025/26Noted
  4. Rosewell Review Phase 2 / Transport for City RegionsNoted
  5. Rosewell Review/Transport for City RegionsNoted
  6. Update Report: City Region Sustainable Transport Settlement - Quarter 2 2025/26Noted

More from West Midlands Combined Authority Investment Board

All decisions
MeetingDecisionOutcome
17 Aug 2026 Minutes - 20 July 2026The minutes of the meeting held on 20 July 2026 were approved as a correct record. Approved Open
17 Aug 2026 Rosewell Review Phase 2/ Transport for City Regions UpdateResolved that: 1. The principles developed to help guide the allocation of the remaining £405m of funding to the Port... Noted Open
17 Aug 2026 Investment Programme UpdateResolved that: 1. Since the previous sitting of the WMCA Investment Board there have been no change requests approved... Approved Open
17 Aug 2026 Investment Programme Dashboard- Red Rated Projects UpdateResolved that: 1. The current position of the eight red-rated projects within the Investment Programme Dashboard, inc... Noted Open
17 Aug 2026 Commercial Investment Fund DashboardResolved that: The report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies