Resolved that : 1. Approval under delegated authority by WMC Officers of the business case submission disclosed at Section 4 of the report be noted; 2. The WMCA Investment Programme funding status and the current affordable limit as outlined at Section 4 of the report be noted; 3. The Regional Investment Programme delivery update detailed within this report and appendices (including the project-level summary within the WMCA Investment Programme dashboard at Appendix 2) be noted; 4. The reduction in indirect outcomes of the Land and Property Investment Fund (‘LPIF’) as detailed at Section 4 of the report, of 121 housing units and 150 construction jobs be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
10 10 6 2 0 0 0 0 0 0 0 - 3 month variance 3 - 6 month variance 6 months or over Completed TBC 0 - 3 month 3 - 6 month 6 months or over Completed TBC variance variance Time Time
Key Movement Key Movement Total number of schemes being reported to 84 Of the 84 schemes being reported against: 50 schemes report Green status 46 schemes report a Green status. 2 schemes continue to report Amber status 0 scheme reports an Amber status 0 schemes report Red status 6 schemes report a Red status 32 schemes completed 32 schemes completed
1 IN FLIGHT: Committed Projects (with committed funding)
Business Actual Approved Forecast / Current Next BC & Committed Approved Case BC Approval WMCA Forecast / Actual Completion Actual Project Business Date Sum (£m) Start Date: Comment Approval Date Spend to Start Date Date: Completion Case Stage Expected BC / FA Level Mar-25 (£m) BC / FA Date UKC Interchange UGC Business Plan. UGC Operating Costs - 8 Investment SOC 13/02/2018 N/A 11.04 10.29 01/04/2016 01/04/2016 31/03/2026 31/03/2026 Years to 31/03/24. Board
HS2 Parallel Designs - Automated People Mover Investment Project closure process currently ongoing. Alignment and Capacity Upgrade FBC 10/08/2020 N/A 0.00 0.00 10/08/2020 10/08/2020 31/12/2029 31/12/2029 Board Previous funding award of £5.75m withdrawn. £510k of IP residual funds have been HS2 Parallel Designs - Hub Movement and OBC SOC SLT 26/08/2020 1.48 0.82 26/08/2020 26/08/2020 30/06/2025 30/06/2025 transferred to the approved SOC CRSTS - Connectivity TBC West Coast Mainline M42 Bridge project HS2 Parallel Designs - Arden Cross Multi-Storey FBC OBC WMCA Board 23/07/2021 7.30 6.59 10/08/2020 10/08/2020 30/06/2024 13/07/2023 Project closure process currently ongoing. Car Park & Balancing Ponds 2024
HS2 Parallel Designs - Roundabout Overtrace FBC WMCA Board 13/09/2019 N/A 11.36 10.12 13/09/2019 13/09/2019 31/12/2025 31/12/2025 HS2 Parallel Designs - Highway Pinch-Point FBC WMCA Board 08/11/2019 N/A 3.38 0.53 02/12/2019 02/12/2019 31/12/2024 31/12/2027 Improvements [NEC Longabout] Birmingham International Station - Integrated Investment FBC OBC 30/04/2018 6.67 6.67 30/04/2018 30/04/2018 31/12/2022 31/12/2022 Project closure process currently ongoing. Transport Hub Board Dec-22 Strategy: Utilities, Land Value, Car Parking SOC SLT 23/05/2017 OBC TBC 0.24 0.24 16/02/2017 16/02/2017 31/03/2023 31/03/2023 Project closure process currently ongoing.
CRSTS - West Coast Mainline M42 Bridge SOC DOS 26/02/2024 OBC 0.51 0.00 TBC TBC 30/06/2025 30/09/2025
2 Business Actual Approved Forecast / Current Next BC & Committed Approved Case BC Approval WMCA Forecast / Actual Completion Actual Project Business Date Sum (£m) Start Date: Comment Approval Date Spend to Start Date Date: Completion Case Stage Expected BC / FA Level Mar-25 (£m) BC / FA Date
UKC Infrastructure Management cost incurred by Solihull during the 2016/17 UKC PMO Expenditure SOC 0.44 0.44 2016/17 2016/17 2016/17 2016/17 inception of UKC Infrastructure SOC Phase 1 and 2. Project closure process ongoing. Small slippage reported in the submission of the A45 Damson Parkway Junction Improvements FBC SLT 20/02/2019 Closure 1.48 1.48 06/10/2017 06/10/2017 28/02/2025 31/03/2025 FBC from February 2025 to March 2025. FBC Submitted. A34 Stratford Road Enhancement Study SOC SLT 19/09/2018 OBC 0.81 0.53 19/09/2018 19/09/2018 31/03/2027 31/03/2027
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Investment Board at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.