AI summaryWest Midlands Combined Authority Investment Board noted the February 2026 Investment Programme update covering 84 schemes, with 39 completed and two change requests approved since the last meeting.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedNo new business case approvals; two change requests noted
MoneyVarious project sumsNo new approvals or spending changes authorised
What happens nextOngoing deliveryProgramme monitoring continues; Q3 performance overview appended
Who it affects84 schemes reported43 Green, 2 Amber, 0 Red (one set); 35 Green, 1 Amber, 9 Red (another set)
What was decided
The Board noted that no business cases had been approved under delegated authority by WMCA Officers since the previous meeting, and that two change requests had been approved.
The Board noted the Investment Programme funding status and current affordable limit as set out in Section 4 of the report.
The Board noted the regional investment programme delivery update, including the project-level dashboard at Appendix 2 and the Quarter 3 performance overview at Appendix 3.
Why
The update provides the Board with a regular overview of progress, funding status and project-level delivery against approved business cases across the programme. Report P1, P12
Several projects have required change requests due to delays, scope changes or funding adjustments, including UKC Interchange and HS2 Hybrid Act Change. Report P14, P15
What happens next
Project teams will continue to progress change requests currently in appraisal, including extensions to Chelmsley Wood Town Centre, Rowood Drive, and Solihull Town Centre Public Realm. Report P20, P21
A paper is expected to be submitted in March 2026 to extend the Metro Wednesbury to Brierley Hill Extension Phase 2 to Summer 2026. Report P34
The money
£731k Additional funding requested for UKC Interchange via change request Report P14
£5.75m Previous funding award for HS2 Parallel Designs Automated People Mover withdrawn Report P15
£510k IP residual funds transferred to approved SOC HS2 Parallel Designs Hub Movement and CRSTS West Coast Mainline M42 Bridge Report P15
£800,900 Used from IP OBC development phase funding for A452 Chelmund's Cross OBC Report P18
£308,100 Remaining IP funding from A452 Chester Road reallocated to A452 Chelmund's Cross FBC development Report P18
£248,000 Approved from CRSTS Capital Funding for Dickens Heath to Solihull Town Centre OBC Report P20
£12.24m Additional funding approved for Coventry Regeneration to incorporate 2nd stair core Report P22
£107m Estimated additional funding from CRSTS 1 re-prioritisation and HS2 compensation for Metro Birmingham Eastside Extension Report P32
£44.2m CRSTS 2 pre-commitment for Metro Birmingham Eastside Extension Report P32
Up to £2.80m Interest on UK Battery Industrialisation Centre loan Report P25
£18.00m Loan to UK Battery Industrialisation Centre Report P25
£50 million Electric bus rollout programme (DfT approved 12-month extension) Report P26
Options considered
Noted: Approve additional £731k and 24-month extension for UKC Interchange. Change Request noted as part of the update Report P14
Noted: Approve 36-month extension and scope expansion for HS2 Hybrid Act Change. Change Request approved, funding reduced to £8.1m Report P15
Implications
Financial: Coventry City Centre South development agreement became unconditional in December 2025, enabling move from demolition to construction phase in early 2026. Report P23
Financial: Sprint A34 Walsall to Birmingham and Sprint A45 Birmingham to Airport and Solihull (Phase 1) projects were confirmed complete on 07/11/2025 with closure process initiated. Report P26
Financial: Two Friargate achieved practical completion and full handover on May 2024. Report P23
Risk: Coventry City Centre First Station Master Plan reports as At Risk while seeking government funding for Bay Platform construction. Report P22
Risk: Metro Birmingham Eastside Extension reports as At Risk, though the full scheme is on track to open to passengers in May 2028. Report P32
Who and where
Solihull Metropolitan Borough Council (projects delivered in Solihull area) Report P15, P17, P18, P19, P20, P21
Coventry City Council (City Centre South, Friargate, City Centre First, electric bus rollout) Report P22, P23, P26
Transport for West Midlands (Metro and Sprint programmes) Report P26, P27, P28, P29, P30, P31, P32, P33, P34
HS2 Ltd and UK Central Hub area promoters Report P14, P15, P20, P22
Timeline
23 March 2026: Investment Board meeting to note programme update Report P1
31st March 2026: OBC resubmission deadline confirmed by SMBC for Solihull Town Centre Public Realm Improvement Report P20
Summer 2026: Proposed extended completion date for Metro Wednesbury to Brierley Hill Extension Phase 2 Report P34
31st March 2028: Proposed revised completion date for UKC Interchange under change request Report P14
31st December 2031: Target completion date for Coventry City Centre First Station Master Plan Bay Platform Report P22
31st January 2042: Forecast completion date for Coventry City Centre South Report P23
Plain English for the jargon
WMCA: West Midlands Combined Authority
DSRO: Deputy Senior Responsible Owner
OBC: Outline Business Case
FBC: Full Business Case
SOC: Strategic Outline Case
IP: Investment Programme
CRSTS: City Region Sustainable Transport Settlement
Sprint: Bus priority corridor programme in the West Midlands
VLR: Very Light Rail
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item150
Resolved
Resolved That: 1. Since the previous sitting of Investment Board, there have been no approvals of any business cases under delegated authority by WMCA Officers, and approval of two Change Requests be noted. 2. The WMCA Investment Programme funding status and current affordable limit, as outlined at Section 4 of the report be noted. 3. The Regional Investment Programme delivery update detailed within this report and appendices (including the project-level summary within the WMCA Investment Programme dashboard at Appendix 2, and Quarter 3 Performance Overview at Appendix 3) be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
45 43 60 0 - 3 month variance 40 43 39 0 - 3 month variance 35 3 - 6 month variance 2 3 - 6 month variance 1 35 50 6 months or over 0 6 months or over 9 Completed 39 7 months or over 39 30 TBC 0 8 months or over 0 40 39
Schemes 35 Schemes
Total 25 84 Total 84
20 30
15 20
10 9 5 2 0 0 1 0 0 0 0 - 3 month variance 3 - 6 month variance 6 months or over Completed TBC 0 - 3 month variance 3 - 6 month variance 6 months or over 7 months or over 8 months or over
Time Time
Key Movement Key Movement
Total number of schemes being reported to 84 Of the 84 schemes being reported against: 43 schemes report Green status 35 schemes report a Green status 2 schemes continue to report Amber status 1 scheme reports an Amber status 0 schemes report Red status 9 schemes report a Red status 39 schemes completed 39 schemes completed
1 IN FLIGHT: Committed Projects (with committed funding)
Business Actual Approved Forecast / Current Next BC & Committed Case BC Approval WMCA Approved Start Date: Forecast / Actual Completion Actual Project Business Date Sum (£m) Budget Status Delivery Status Comment Approval Date Spend to Feb- BC / FA Start Date Date: Completion Case Stage Expected Level 26 (£m) BC / FA Date UKC Interchange A Change Request has been submitted requesting a time extension to 31st UGC Business Plan. UGC Operating Costs - 8 Investment SOC 13/02/2018 N/A 11.04 10.45 01/04/2016 01/04/2016 31/03/2026 31/03/2028 Off Track Off track March 2028 (24 months) and an additional £731k. Years to 31/03/24. Board
A Change Request has been approved for a 36 month extenstion to expand OBC Investment HS2 Hybrid Act Change (HS2 Parallel Designs) 13/02/2018 N/A 8.11 7.91 13/02/2018 13/02/2018 31/12/2028 31/12/2028 On Track On Track the scope of Utilities Under the Trace (UTX) design and management. This Board also includes a reduction in the funding allocation to £8.1m. HS2 Parallel Designs - Automated People Mover Investment Alignment and Capacity Upgrade FBC 10/08/2020 N/A - - 10/08/2020 10/08/2020 31/12/2029 31/12/2029 Completed Completed Project formally closed. Previous funding award of £5.75m withdrawn. Board £510k of IP residual funds have been transferred to the approved SOC HS2 Parallel Designs - Hub Movement and OBC SOC SLT 26/08/2020 1.48 0.83 26/08/2020 26/08/2020 30/06/2027 30/06/2027 On Track On Track CRSTS - West Coast Mainline M42 Bridge project. Change Request Connectivity TBC approved (11/08/2025) extending the date to 30/06/2027. HS2 Parallel Designs - Arden Cross Multi-Storey FBC OBC WMCA Board 23/07/2021 7.30 6.59 10/08/2020 10/08/2020 30/06/2024 13/07/2023 Completed Completed Project formally closed. Car Park & Balancing Ponds 2024 HS2 Parallel Designs - Roundabout Overtrace FBC WMCA Board 13/09/2019 N/A 11.37 10.48 13/09/2019 13/09/2019 31/12/2025 31/12/2025 Completed Completed Project complete, with closure process ongoing. HS2 Parallel Designs - Highway Pinch-Point FBC WMCA Board 08/11/2019 N/A 3.38 0.53 02/12/2019 02/12/2019 31/12/2027 31/12/2027 On Track On Track Improvements [NEC Longabout] Birmingham International Station - Integrated Investment FBC OBC 30/04/2018 6.67 6.67 30/04/2018 30/04/2018 31/12/2022 31/12/2022 Completed Completed Project formally closed. Transport Hub Board Dec-22 Strategy: Utilities, Land Value, Car Parking SOC SLT 23/05/2017 OBC TBC 0.24 0.24 16/02/2017 16/02/2017 31/03/2023 31/03/2023 Completed Completed Project complete and benefits being monitored.
On 4 December 2025, the CRSTS Deputy Senior Responsible Owner (DSRO) approved a 9-month project extension due to delays in CRSTS - West Coast Mainline M42 Bridge SOC DOS 26/02/2024 OBC 0.51 - TBC TBC 30/06/2026 30/06/2026 On Track On Track procurement timeframes, and consultants’ delivery of the associated work.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Investment Board at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.