Investment Programme Update

Approved Committee 3 papers

AI summaryWMCA Investment Board notes the Investment Programme update, with two Change Requests approved since the January meeting and total approved grant funding of £844.3 million as at 31st January 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedProgramme update and Change Requests noted
Money£844.3 million approvedGrant funding committed as at 31st January 2026
What happens nextChange Requests under appraisalSeveral UKC and Metro extensions to be considered
Who it affectsTen schemes flagged redFor completion dates, across the programme

What was decided

The Board noted that no business cases had been approved under delegated authority by WMCA officers since the previous meeting, but two Change Requests had been approved. Report 4.8

The Board noted the Investment Programme funding status and the current affordable limit of £871 million set by WMCA Board in March 2021. Report 4.5

The Board noted the Regional Investment Programme delivery update, including the project-level summary within the Investment Programme dashboard at Appendix 2. Report 4.11, P19

Why

The report is part of a regular series of updates on the Investment Programme, with no new approvals or options presented for decision. Report P34, P35

The affordable limit and approved funding figures provide the framework within which project sponsors manage delivery and any cost escalations. Report 4.5, 4.6, 13.2

What happens next

Kingshurst Village Centre has a 15-month extension to December 2026 and the UKC Hub Low Carbon Heat Network has a 12-month extension to December 2026, both with no change to funding limits. Report 4.8, P15

Programme Assurance and Appraisal will work with Project Sponsors to submit Change Requests for the ten schemes currently at RED status, including submissions under appraisal for HS2 Parallel Designs, Rowood Drive, Balsall Common and Sustainable Energy. Report 4.17, P29, P30, P31

A paper to rebase the Metro Wednesbury to Brierley Hill Extension Phase 1 is being prepared for submission in March 2026, extending completion to Summer 2026 with no expected change to capital budget. Report 4.18, P32

The money

  • £871 million Current WMCA Investment Programme affordable limit, set March 2021 Report 4.5
  • £844.3 million Total approved grant funding as at 31st January 2026 Report 4.6
  • £760.1 million Investment Programme funding used against eligible expenditure to 31st January 2026 Report 4.10
  • £5.73m Funding limit for Kingshurst Village Centre, unchanged by Change Request Report P15
  • £0.20m Funding limit for Sustainable Energy UKC Hub Low Carbon Heat Network, unchanged by Change Request Report P15
  • £26.89m Significant expenditure April 2025 to January 2026, Coventry City Centre South Regeneration Report 4.12, P21
  • £19.94m Significant expenditure April 2025 to January 2026, Walsall to Wolverhampton Local Enhancements Package 1 Report 4.12, P21
  • £9.73m Significant expenditure April 2025 to January 2026, Camp Hill Line Local Enhancements Package 2 Report 4.12, P21

Options considered

  • Chosen: Note the Investment Programme update, funding status and two Change Requests. The Board endorsed the update as part of its standing monitoring role under the enhanced Terms of Reference. Report 4.3, P4

Implications

  • Financial: Officers are reviewing the UK Government Autumn Budget statement to identify any impact on the region's Investment Programme. Report P57
  • Financial: Funding awarded from the Investment Programme is capped, and project sponsors must manage and mitigate any gross cost escalations. Report 13.2
  • Legal: The Programme is underpinned by the Annual Devolution Deal grant from the Department for Levelling Up, Housing and Communities, which sets the terms for use of funds. Report 11.1
  • Risk: Ten schemes are at RED status for completion dates, with several Change Requests under appraisal or being prepared. Report 4.17, P27, P28, P29, P30, P31

Who and where

  • 84 projects that have passed the Assurance Process and received a financial commitment Report 4.16
  • Project sponsors of the ten schemes currently at RED status, including the UKC Interchange and UKC Infrastructure programmes Report 4.17, P27, P30
  • Constituent and non-constituent member local authorities of the WMCA Report 9.1, P61

Timeline

  • September 2025 to December 2026: Approved 15-month extension for Kingshurst Village Centre Report P15
  • December 2025 to December 2026: Approved 12-month extension for Sustainable Energy UKC Hub Low Carbon Heat Network Report P15
  • 31st January 2026: Approved grant funding totals £844.3 million, unchanged from the previous Board meeting Report 4.6
  • 31st January 2026: Investment Programme funding used against eligible expenditure totals £760.1 million Report 4.10
  • March 2026: Paper to rebase the Metro Wednesbury to Brierley Hill Extension Phase 1 expected to be submitted Report 4.18, P32
  • Summer 2026: Expected revised completion date for Metro Wednesbury to Brierley Hill Extension Phase 1 Report 4.18, P32
  • 31st March 2026: Revised submission dates indicated for Accelerated Housing Delivery, Playing Pitch and Solihull Town Centre Public Realm Improvement Report P31
  • 31st December 2029: Requested extension date for the Balsall Common Multimodal Transport Package completion Report P31

Plain English for the jargon

  • WMCA: West Midlands Combined Authority
  • Investment Programme: WMCA grant-funded programme covering transport, housing, regeneration and other capital projects within the affordable limit
  • Affordable limit: The maximum amount of grant funding the WMCA Board has approved the Investment Programme can provide, currently £871 million
  • Change Request: A formal request to alter an approved project's scope, funding or timetable
  • RED status: A project flagged as having passed its original completion date without conclusion or requiring a time extension
  • Single Assurance Framework: WMCA framework setting out approval and assurance requirements, including the £5 million to £20 million Investment Board remit
  • UKC: UK Central, a programme area around the HS2 Interchange covering infrastructure, housing and regeneration schemes
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item130

Resolved

Resolved that: 1. Since the previous meeting of the Investment Board there has been no approvals of any business cases under delegated authority by WMCA Officers, and approval of two Change Requests be noted. 2. The WMCA Investment Programme funding status and current affordable limit as outlined at Section 4 of the report be noted. 3. The Regional Investment Programme delivery update detailed within this report and appendices (including the project-level summary within the Investment Programme dashboard at Appendix 2) be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting. Source: governance.wmca.org.uk

Follow this further

Built from West Midlands Combined Authority's papers

What the report saysPro

Report to Investment Board

Background

4.1The Investment Board was established by the WMCA Board as a key element of the approvals process across the Investment Programme.

4.2The Investment Board considered and endorsed an enhanced Terms of Reference at its meeting on 20th April 2020 (approved by WMCA Board 24th July 2020). This set out an enhanced role supporting decision-making, greater post approval controls, performance management and effective delivery of monitoring & evaluation requirements.

4.3The enhanced Terms of Reference included the following:

• To oversee and monitor all investments made through the Investment Programme.

• To add conditions to any funding decision that falls within its delegated authority. Minimum conditions should specify the availability period, conditions to drawdown of funds, conditions for withdrawal of support and terms of clawback, start date and completion date for the project or programme.

• Where oversight of monitoring and evaluation applies to the Investment Board, to consider whether a formal review of project or programme is required, and to consider this review itself or instruct the Investment Panel to do so on its behalf.

4.4On the 10th of June 2022, WMCA Board approved extending the role and remit of WMCA Investment Board to cover all WMCA projects (including the CRSTS programme), allowing investment decisions to be made for values between £5 million and £20 million in line with the Single Assurance Framework.

Investment Programme Affordable Limit & Gateway Status

4.5At the WMCA Board meeting on 19th March 2021, WMCA Board approved an increase to the current WMCA Investment Programme affordable limit of £70 million, from £801 million to £871 million. This remains the current limit of grant funding1 that can be provided by WMCA from the Investment Programme.

1 Excluding part of the anticipated recoverable/recyclable commitment to the West Midlands Co-Invest Equity

fund approved by WMCA Board on 23rd July 2021. Investment Programme Assurance Summary

4.6Approved grant funding awarded and administered by the WMCA to programmes within the Regional Investment Programme totals £844.3 million as at 31st January 2026 which is unchanged from the amount reported at the previous sitting of Board.

4.7These commitment values above exclude the provisional ‘ear-marked’ allocations agreed by WMCA Board in March 2021 that are yet to obtain formal approval. Commitments for some of these ear-marked items will be confirmed via the approval of further reports to WMCA Board.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
IP Update Report Feb-26 (Final)Appendix 1 93 KB Download
PDF
Investment Programme UpdateReport 212 KB DownloadRead as text
PDF
January 2026 IP Dashboard (Final)Report 333 KB Download

At this meeting

Whole meeting

Who was there

5 of 8 attended
PH
Councillor Peter HughesChair, present
BS
Councillor Bob SleighVice-Chair, apologies
MB
Councillor Mike BirdCommittee Member - Voting, present
CB
Councillor Christopher BurdenCommittee Member - Voting, present
SC
Councillor Steve ClarkCommittee Member - Voting, in attendance, virtual
MM
Councillor Majid MahmoodCommittee Member - Voting, present
JO
Councillor Jim O'BoyleCommittee Member - Voting, present
SS
Sue SummersCommittee Member - Non-Voting, apologies

On this subject at West Midlands Combined Authority

Search all
  1. Investment Programme UpdateThis decision
  2. Investment Programme UpdateApproved
  3. Investment Programme Dashboard- Red Rated Projects UpdateNoted
  4. Investment Programme UpdateApproved
  5. Investment Programme UpdateApproved
  6. Investment Programme UpdateApproved

More from West Midlands Combined Authority Investment Board

All decisions
MeetingDecisionOutcome
17 Aug 2026 Minutes - 20 July 2026The minutes of the meeting held on 20 July 2026 were approved as a correct record. Approved Open
17 Aug 2026 Rosewell Review Phase 2/ Transport for City Regions UpdateResolved that: 1. The principles developed to help guide the allocation of the remaining £405m of funding to the Port... Noted Open
17 Aug 2026 Investment Programme UpdateResolved that: 1. Since the previous sitting of the WMCA Investment Board there have been no change requests approved... Approved Open
17 Aug 2026 Investment Programme Dashboard- Red Rated Projects UpdateResolved that: 1. The current position of the eight red-rated projects within the Investment Programme Dashboard, inc... Noted Open
17 Aug 2026 Commercial Investment Fund DashboardResolved that: The report be noted. Noted Open