Resolved that: 1. Approval under delegated authority by WMCA Officers of the business case submission disclosed at Section 4 of the report be noted; 2. The WMCA Investment Programme funding status and current affordable limit as outlined at Section 4 of the report be noted and 3. The Regional Investment Programme delivery update detailed within this report and appendices (including the project-level summary within the WMCA Investment Programme dashboard at Appendix 2) be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Total number of schemes being reported to 84 Of the 84 schemes being reported against: 48 schemes report Green status 43 schemes report a Green status. 2 schemes continue to report Amber status 2 scheme reports an Amber status 0 schemes report Red status 5 schemes report a Red status 34 schemes completed 34 schemes completed
1 IN FLIGHT: Committed Projects (with committed funding)
Actual Approved Current Business Next BC & Committed Approved BC Approval WMCA Forecast / Actual Completion Forecast / Actual Project Business Case Approval Date Sum (£m) Start Date: Budget Status Delivery Status Comment Date Spend to Start Date Date: Completion Date Case Stage Level Expected BC / FA Aug-25 (£m) BC / FA UKC Interchange
UGC Business Plan. UGC Operating Costs - 8 Investment SOC 13/02/2018 N/A 11.04 10.35 01/04/2016 01/04/2016 31/03/2026 31/03/2026 On Track On Track Years to 31/03/24. Board
HS2 Parallel Designs - Automated People Mover Investment Project formally closed. Previous funding award Alignment and Capacity Upgrade FBC 10/08/2020 N/A - - 10/08/2020 10/08/2020 31/12/2029 31/12/2029 Completed Completed Board of £5.75m withdrawn.
£510k of IP residual funds have been transferred to the approved SOC CRSTS - HS2 Parallel Designs - Hub Movement and OBC SOC SLT 26/08/2020 1.48 0.82 26/08/2020 26/08/2020 30/06/2027 30/06/2027 On Track On Track West Coast Mainline M42 Bridge project. Connectivity TBC Change Request approved (11/08/2025) extending the date to 30/06/2027.
Birmingham International Station - Integrated Investment FBC OBC 30/04/2018 6.67 6.67 30/04/2018 30/04/2018 31/12/2022 31/12/2022 Completed Completed Project formally closed. Transport Hub Board Dec-22
Strategy: Utilities, Land Value, Car Parking SOC SLT 23/05/2017 OBC TBC 0.24 0.24 16/02/2017 16/02/2017 31/03/2023 31/03/2023 Completed Completed Project complete and benefits being monitored.
CRSTS - West Coast Mainline M42 Bridge SOC DOS 26/02/2024 OBC 0.51 - TBC TBC 30/09/2025 30/09/2025 On Track On Track
UKC Infrastructure
Management cost incurred by Solihull during the 2016/17 UKC PMO Expenditure SOC 0.44 0.44 2016/17 2016/17 2016/17 2016/17 Completed Completed inception of UKC Infrastructure SOC Phase 1 and 2. Project closure process ongoing.
Small slippage reported in the submission of the A45 Damson Parkway Junction Improvements SOC SLT 20/02/2019 Closure 1.48 1.48 06/10/2017 06/10/2017 28/02/2025 31/03/2025 Completed Completed FBC from February 2025 to March 2025. FBC Submitted. A34 Stratford Road Enhancement Study SOC SLT 19/09/2018 OBC 0.81 0.53 19/09/2018 19/09/2018 31/03/2027 31/03/2027 On Track On Track
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Investment Board at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.