OutcomeApprovedDelegated business case, funding status, and delivery update
Money£844.3 million approved, £720.9 million spentOf £871 million affordable limit, as at 30 September 2025
What happens nextProject sponsors to submit Change RequestsFive schemes at RED status require extensions
Who it affects84 approved WMCA Investment Programme projectsIncluding five at RED status for completion dates
What was decided
The Board noted approval under delegated authority by WMCA Officers of a business case submission disclosed in Section 4 of the report.
The Board noted the WMCA Investment Programme funding status and current affordable limit, as set out in Section 4 of the report.
The Board noted the Regional Investment Programme delivery update in the report and appendices, including the project-level summary in the WMCA Investment Programme dashboard at Appendix 2.
Why
The Investment Board oversees and monitors all investments made through the Investment Programme under its enhanced Terms of Reference, approved by WMCA Board in July 2020. Report P4, 4.2
Its role was extended in June 2022 to cover all WMCA projects, including CRSTS, allowing investment decisions for values between £5 million and £20 million under the Single Assurance Framework. Report 4.4
What happens next
Programme Assurance and Appraisal team will work with project sponsors to bring forward requests to extend completion dates for the five schemes at RED status. Report 4.18, P27
WMCA Officers are reviewing the UK Government Autumn Budget statement to assess any impact on the region's Investment Programme. Report P48
The money
£871 million Current WMCA Investment Programme affordable limit of grant funding Report 4.5
£844.3 million Approved grant funding awarded and administered by WMCA to programmes as at 30 September 2025 Report 4.6
£720.9 million WMCA Investment Programme funding used to 30 September 2025 against funding commitments Report 4.11
£248,000 Additional grant funding approved under delegated authority for Walking, Cycling and Green Infrastructure Investment Programme from CRSTS Capital Funding Report 4.9
£960,000 Existing grant award from the Investment Programme across 2 Walking, Cycling and Green Infrastructure projects Report 4.9
£12.16m Expenditure from April to September 2025 on Rail Walsall to Wolverhampton Local Enhancements Package 1 Report 4.13
£4.75m Expenditure from April to September 2025 on Coventry City Centre South Regeneration Report 4.13
£3.87m Expenditure from April to September 2025 on Rail Camp Hill Line Local Enhancements Package 2 Report 4.13
Options considered
Chosen: Approve the £248,000 change request to extend the Walking, Cycling and Green Infrastructure Investment Programme duration. Allows time to complete the OBC for the Dickens Heath to Solihull Town Centre project by 31 August 2026 Report 4.9
Implications
Financial: No direct financial implications arise from the recommendations; the affordable limit remains £871 million and approved commitments stand at £844.3 million as at 30 September 2025. Report 10.1, 4.5, 4.6
Legal: No direct legal implications arise; funding must be used in accordance with the Annual Devolution Deal grant terms from the Department for Levelling Up, Housing and Communities. Report 11.1
Risk: Five schemes are at RED status for completion dates, including Accelerated Housing Delivery, Playing Pitch Implementation Strategy, Middlewood House, Rowood Drive and Balsall Common Multimodal Transport Package. Report 4.18, P28, P29
Risk: WMCA Officers are reviewing the UK Government Autumn Budget statement for any impact on the region's Investment Programme. Report P48
Equalities: No equalities implications arise from this report. Report P50
Staffing: No direct implications for constituent or non-constituent local authority members arise from this report. Report P52
Who and where
Eighty-four projects that have passed the WMCA Assurance Process and received a financial commitment Report 4.17
Project sponsors responsible for the five RED status schemes, including the UKC Infrastructure Programme Report P27, P28, P29
Constituent and non-constituent member local authorities of the WMCA Report 9.1
Timeline
20 April 2020: Investment Board endorsed enhanced Terms of Reference Report 4.2
24 July 2020: WMCA Board approved the enhanced Terms of Reference Report 4.2
19 March 2021: WMCA Board approved increase to affordable limit from £801 million to £871 million Report 4.5
10 June 2022: WMCA Board approved extending Investment Board role to cover all WMCA projects including CRSTS Report 4.4
27 January 2025: Change Request for UKC Infrastructure Programme was approved Report P27
22 September 2025: Previous full meeting of WMCA Investment Board Report 4.8
30 September 2025: Date of approved grant funding and funding used figures Report 4.6, 4.11
31 March 2026: Requested extension to submit OBCs for viable sites under Accelerated Housing Delivery Report P29
31 August 2026: Target to complete OBC for Dickens Heath to Solihull Town Centre project Report 4.9
Plain English for the jargon
WMCA: West Midlands Combined Authority
CRSTS: City Region Sustainable Transport Settlement, a central government capital funding programme
OBC: Outline Business Case, a stage in the WMCA assurance process for project funding
SOC: Strategic Outline Case, an early stage in the project business case process
RED status: Projects flagged where the original completion date has passed or a time extension is required
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item71
Resolved
Resolved that: 1. Approval under delegated authority by WMCA Officers of the business case submission disclosed at Section 4 of the report be noted; 2. The WMCA’ Investment Programme funding status and current affordable limit, as outlined at Section 4 of the report be noted and 3. The Regional Investment Programme delivery update detailed within the report and appendices (including the project-level summary within the WMCA Investment Programme dashboard at Appendix 2) be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
4.1The Investment Board was established by the WMCA Board as a key element of the approvals process across the Investment Programme.
4.2The Investment Board considered and endorsed an enhanced Terms of Reference at its meeting on 20th April 2020 (approved by WMCA Board 24th July 2020). This set out an enhanced role supporting decision-making, greater post approval controls, performance management and effective delivery of monitoring & evaluation requirements.
4.3The enhanced Terms of Reference included the following:
• To oversee and monitor all investments made through the Investment Programme.
• To add conditions to any funding decision that falls within its delegated authority. Minimum conditions should specify the availability period, conditions to drawdown of funds, conditions for withdrawal of support and terms of clawback, start date and completion date for the project or programme.
• Where oversight of monitoring and evaluation applies to the Investment Board, to consider whether a formal review of project or programme is required, and to consider this review itself or instruct the Investment Panel to do so on its behalf.
4.4On the 10th of June 2022, WMCA Board approved extending the role and remit of WMCA Investment Board to cover all WMCA projects (including the CRSTS programme), allowing investment decisions to be made for values between £5 million and £20 million in line with the Single Assurance Framework.
Investment Programme Affordable Limit & Gateway Status
4.5At the WMCA Board meeting on 19th March 2021, WMCA Board approved an increase to the current WMCA Investment Programme affordable limit of £70 million, from £801 million to £871 million. This remains the current limit of grant funding1 that can be provided by WMCA from the Investment Programme.
Investment Programme Assurance Summary
4.6Approved grant funding awarded and administered by the WMCA to programmes within the Regional Investment Programme totals £844.3 million as 30th September 2025. which is unchanged from the amount reported at the previous sitting of Board.
1 Excluding part of the anticipated recoverable/recyclable commitment to the West Midlands Co-Invest Equity
fund approved by WMCA Board on 23rd July 2021. 4.7 These commitment values above exclude the provisional ‘ear-marked’ allocations agreed by WMCA Board in March 2021 that are yet to obtain formal approval. Commitments for some of these ear-marked items will be confirmed via the approval of further reports to WMCA Board.
4.8Since the previous full meeting of the WMCA Investment Board on 22nd September 2025, one business case submission for grant funding has been approved under delegated authority.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Investment Board at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.