AI summaryWest Midlands Combined Authority Investment Board notes the December 2025 Investment Programme dashboard: 84 schemes monitored, 48 rated green, and no new business case approvals under delegated authority since the previous meeting.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedDelegated approvals, funding status, and delivery update noted
MoneyNo new approvals or sums decided at this meeting
What happens nextNone specifiedDecision is a note only, no actions directed
Who it affects84 Investment Programme schemesTransport, regeneration, land, skills and innovation projects
What was decided
The Board noted that no business cases had been approved under delegated authority by WMCA Officers since the previous sitting of the Investment Board.
The Board noted the Investment Programme funding status and current affordable limit, as outlined in Section 4 of the report.
The Board noted the Regional Investment Programme delivery update, including the project-level summary in the WMCA Investment Programme dashboard at Appendix 2.
Why
The report is the December 2025 Investment Programme dashboard, a standing update on scheme status, spend and milestones. Report P1, P9
It sets out 84 schemes: 48 green, 2 amber, 0 red, with 34 completed in the current reporting period. Report P9
What happens next
The decision itself directs no new actions; it only records the Board noting the contents of the report.
Several change requests are being appraised or are awaiting resubmission, including Kingshurst Village Centre (12-month time extension), Chelmsley Wood Town Centre (24-month extension for the OBC) and the Solihull Town Centre Public Realm Improvement OBC. Report P30, P31, P32
The money
£5m Ringfenced Investment Programme funding for capital pressures linked to Covid-19 construction risks Report P71
£0.8m Approved from capital pressures to reimburse Midland Metro Limited for additional lines into use Report P71
£5.75m Previous funding award withdrawn on formal closure of HS2 Parallel Designs Automated People Mover Report P13
£510k IP residual funds transferred to the approved SOC for HS2 Parallel Designs Hub and M42 Bridge project Report P14
£809,000 IP OBC development phase funding utilised for A452 Chelmund's Cross project Report P25
£308,100 Remaining IP funding reallocated to support FBC development for the A452 Chelmund's Cross project Report P26
£248,000 CRSTS Capital Funding approved to complete the OBC for Dickens Heath to Solihull Town Centre Report P34
£12.24m Additional WMCA Investment Board approval to incorporate a second stair core at Coventry City Centre South Report P47
£107m Additional estimated funding from CRSTS 1 re-prioritisation and HS2 compensation for the Metro Birmingham Eastside Extension Report P66
£44.2m CRSTS 2 pre-commitment towards the Metro Birmingham Eastside Extension period Report P66
Implications
Financial: The report sets out the Investment Programme funding status and current affordable limit; constrained funding has already led to two workstreams being paused pending alternative sources. Report P44
Risk: Projects reported At Risk or Off Track include Coventry City Centre First (At Risk), CRSTS West Coast Mainline M42 Bridge (Off Track), Kingshurst Village Centre, Chelmsley Wood Town Centre, Willenhall Station, and the Metro Birmingham Eastside Extension. Report P20, P31, P32, P46, P66, P72
Risk: An unstable building adjacent to the Willenhall Station worksite has caused health and safety concerns and may require design changes. Report P72
Other: The UKC Interchange change request submitted on 23.12.25 seeks a 36-month extension to the OBC to cover the HS2 Hybrid Act scope and Utilities Under the Trace design and management. Report P12
Who and where
WMCA Investment Programme portfolio of 84 schemes across the West Midlands Report P9
Solihull Metropolitan Borough Council, through multiple UK Central, town centre and housing delivery projects Report P11, P25, P27, P30, P31, P32, P38, P39, P40
Coventry City Council, through City Centre South, Friargate, City Centre First and Very Light Rail projects Report P46, P47, P48, P55, P56
Transport for West Midlands and rail delivery partners on Metro, Sprint, and rail enhancement schemes Report P59, P60, P61, P62, P66, P67, P68, P69, P72, P73
Black Country Consortium and wider brownfield and land remediation projects Report P76, P77
Timeline
December 2025: Reporting period of the Investment Programme dashboard Report P1
23 December 2025: Change request submitted for a 36-month UKC Interchange OBC extension Report P12
19 January 2026: WMCA Investment Board meeting at which the dashboard was noted Report P1
31 March 2026: UKC Interchange project completion date (and West Midlands Rail Package 1/2 revised delivery) Report P11, P72, P73
Plain English for the jargon
IP: Investment Programme (the WMCA funding programme covered by the dashboard)
SOC: Strategic Outline Case, the earliest stage of a project business case
OBC: Outline Business Case, the middle stage of a project business case
FBC: Full Business Case, the final stage before delivery
CRSTS: City Region Sustainable Transport Settlement, a government transport funding allocation
WMCA: West Midlands Combined Authority
TfWM: Transport for West Midlands, the WMCA's transport arm
DSO: Directorate Sign-Off, an internal WMCA governance approval level
SLT: WMCA Senior Leadership Team, an internal business case approval route
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item114
Resolved
Resolved that: 1. Since the previous sitting of the WMCA Investment Board there has been no approvals of any business cases under delegated authority by WMCA Officers be noted. 2. The WMCA Investment Programme funding status and current affordable limit, as outlined in Section 4 of the report be noted. 3. The Regional Investment Programme delivery update detailed within the report and appendices (including the project-level summary within the WMCA Investment Programme dashboard at Appendix 2) be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Total number of schemes being reported to 84 Of the 84 schemes being reported against: 48 schemes report Green status 41 schemes report a Green status. 2 schemes continue to report Amber status 1 scheme reports an Amber status 0 schemes report Red status 6 schemes report a Red status 34 schemes completed 36 schemes completed
1 IN FLIGHT: Committed Projects (with committed funding)
Business Actual Approved Forecast / Current Next BC & Committed Approved Case BC Approval WMCA Forecast / Actual Completion Actual Project Business Date Sum (£m) Start Date: Budget Status Delivery Status Comment Approval Date Spend to Start Date Date: Completion Case Stage Expected BC / FA Level Nov-25 (£m) BC / FA Date UKC Interchange UGC Business Plan. UGC Operating Costs - 8 Investment SOC 13/02/2018 N/A 11.04 10.40 01/04/2016 01/04/2016 31/03/2026 31/03/2026 On Track On Track Years to 31/03/24. Board
Change Request submitted 23.12.25 for an OBC Investment extension of 36 months to include the extension HS2 Hybrid Act Change (HS2 Parallel Designs) 13/02/2018 N/A 9.80 7.91 13/02/2018 13/02/2018 31/12/2025 31/12/2028 On Track Off Track Board of scope of the Design and management of Utilities Under The Trace (UTX).
HS2 Parallel Designs - Automated People Mover Investment Project formally closed. Previous funding award Alignment and Capacity Upgrade FBC 10/08/2020 N/A - - 10/08/2020 10/08/2020 31/12/2029 31/12/2029 Completed Completed Board of £5.75m withdrawn.
£510k of IP residual funds have been transferred to the approved SOC CRSTS - HS2 Parallel Designs - Hub Movement and OBC SOC SLT 26/08/2020 1.48 0.83 26/08/2020 26/08/2020 30/06/2027 30/06/2027 On Track On Track West Coast Mainline M42 Bridge project. Connectivity TBC Change Request approved (11/08/2025) extending the date to 30/06/2027.
Birmingham International Station - Integrated Investment FBC OBC 30/04/2018 6.67 6.67 30/04/2018 30/04/2018 31/12/2022 31/12/2022 Completed Completed Project formally closed. Transport Hub Board Dec-22
Strategy: Utilities, Land Value, Car Parking SOC SLT 23/05/2017 OBC TBC 0.24 0.24 16/02/2017 16/02/2017 31/03/2023 31/03/2023 Completed Completed Project complete and benefits being monitored.
The Project Sponsor has reported that the completion of the OBC has been further delayed CRSTS - West Coast Mainline M42 Bridge SOC DOS 26/02/2024 OBC 0.51 - TBC TBC 30/09/2025 03/04/2026 On Track Off Track from the expected November/December 2025 to now April 2026. UKC Infrastructure
Management cost incurred by Solihull during the 2016/17 UKC PMO Expenditure SOC 0.44 0.44 2016/17 2016/17 2016/17 2016/17 Completed Completed inception of UKC Infrastructure SOC Phase 1 and 2. Project closure process ongoing.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Investment Board at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.