AI summaryWest Midlands Investment Board approved the Full Business Case for Cross City Bus Package 6 West, a bus priority scheme in Birmingham and Sandwell. The total budget is £15.597, with £13.005m approved under this report.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedFor Cross City Bus Package 6 West
Money£13.005m approvedPart of total £15.597 scheme budget
What happens nextOverarching report to WMCA BoardSummer 2026, covering full Cross City Bus Programme
Who it affectsBirmingham and SandwellHighway works in both authorities
What was decided
The Investment Board approved the Full Business Case for Cross City Bus Package 6 West, the full scheme budget of £15.597 (inclusive of £13.005m under this report), and delegated authority to the Director of Delivery for Transport to enter agreements and approve expenditure within the project budget.
Why
An independent Assurance and Appraisal review found the Full Business Case well constructed, evidence-based and clearly articulated, with a BCAT score of 81% indicating high likelihood of successful delivery. Report 9.1, 9.3
The review found robust stakeholder engagement, strong governance, and clear alignment with regional transport objectives, modal shift ambitions, and WMCA Aims 1 and 3. Report 9.2, 9.4
The Inclusive Growth Toolkit assessment scored the bus priority programme 8.59 out of 10, reflecting expected benefits in access to employment, education, healthcare and leisure. Report P20
What happens next
The project team must confirm updated utilities, design-stage and resourcing costs prior to construction to demonstrate affordability within the approved financial envelope. Report 9.6
Any cost changes beyond agreed tolerances must be escalated through the WMCA Single Assurance Framework Change Control Process. Report 9.6
An overarching report on the full Cross City Bus Programme is intended to go to the WMCA Board in Summer 2026.
The money
£15.597 Total approved scheme budget (inclusive of £13.005m under this report)
£13.005m CRSTS funding amount subject to this report Report 9.5
Options considered
Chosen: Contractor-led Design and Build via John Sisk & Son Limited under NEC4 ECC Option E with Early Contractor Involvement. Awarded through the Midlands Highways Alliance Medium Schemes Framework; supports collaborative working through design to construction Report 8.2, 9.7
Rejected: TfWM to procure bus shelter, CCTV and RTI supply and installation via existing or new framework agreements. Currently within John Sisk & Son Limited's scope; approach to be reviewed during detailed design Report 9.8
Implications
Legal: Contract to be let via contractor-led Design and Build using NEC4 ECC Option E (cost reimbursable) with Early Contractor Involvement; works carried out under an agreement between WMCA and Birmingham City Council. Report 8.2, 8.4
Equalities: The Health and Equalities Impact Assessment identifies significant positive impacts for young people, the elderly, disabled people, ethnic minorities and economically disadvantaged groups, who are disproportionately reliant on public transport. Report 9.10, 9.11
Risk: Key risks include political changes causing loss of support, delays from governance including objections to Traffic Regulation Orders, and construction issues leading to increased delivery time and cost. Report P21
Financial: Updated cost confirmation is required before construction; any changes beyond agreed tolerances are escalated through the WMCA Single Assurance Framework Change Control Process. Report 9.6
Staffing: All staff are to be provided by John Sisk & Son Limited, with collaboration and co-location at Summer Lane expected during design and development. Report 8.3
Other: The FBC achieved a BCAT score of 81%, indicating strong alignment with the WMCA Single Assurance Framework and high likelihood of successful delivery. Report 9.3
Who and where
Birmingham City Council (highway works and contracting partner with WMCA) Report 8.4, P22
Sandwell Council (highway works in the authority) Report P22
Transport for West Midlands Delivery Directorate (contract manager) Report 8.5
Bus users, including groups identified in the HEIA as benefiting from the scheme Report 9.11
Timeline
Summer 2026: Overarching report on the full Cross City Bus Programme intended to be presented to the WMCA Board
Prior to construction: Updated utilities, design-stage and resourcing costs to be confirmed to demonstrate affordability within the approved financial envelope Report 9.6
Plain English for the jargon
BCAT: Score used in the independent Assurance and Appraisal review; the scheme scored 81%
CRSTS: City Region Sustainable Transport Settlement, the funding source for this scheme
ECI: Early Contractor Involvement, used to develop and agree scope and prices before construction
HEIA: Health and Equalities Impact Assessment, completed for the scheme
NEC4 ECC Option E: New Engineering Contract cost-reimbursable contract option used for the design and build partnership
RTI: Real Time Information equipment at bus stops
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item155
Resolved
Resolved that: 1. The Full Business Case for Cross City Bus Package 6 West be approved. 2. The full budget for the scheme totalling £15.597 (inclusive of £13.005m which is subject to this report) be approved. 3. Authority be delegated to the Director of Delivery for Transport to enter into the relevant agreements and approve expenditure within the overall project budget for delivery of the scheme. 4. It is intended that overarching report encompassing the full Cross City Bus Programme is presented to the WMCA Board in Summer 2026 be noted.
Word for word from the decision West Midlands Combined Authority published for this meeting.Source: governance.wmca.org.uk
Follow this further
Built from West Midlands Combined Authority's papers
Report title: Cross City Bus Package 6 West Full Business Case Jo Shore, Director of Delivery Transport, Transport for the Responsible Director: West Midlands Report author: Martin Pyne, Project Sponsor
Key Decision? Yes
Is the ability for the Combined Authority to make a decision internally reliant on Constituent or Non-Constituent Councils making a formal decision first?
☐Yes ☒No
(If Yes – please contact the Member Relationship Manager to manage this process)
Recommendations (1) Approve the Full Business Case for Cross City Bus Package 6 West.
(2) Approve the full budget for the scheme totalling £15.597m (inclusive of £13.005m which is subject to this report).
(3) Delegate to the Director of Delivery for Transport, authority to enter into relevant agreements and approve expenditure within the overall project budget for delivery of the scheme.
(4) Note that it is intended that an over-arching report encompassing the full Cross City Bus Programme is presented to WMCA Board in summer 2026.
Voting Requirements A majority of voting members, in attendance in the meeting room and indicating their preference, are required to vote in favour of any recommendation/proposition for it to become a decision of the committee.
1. Executive Summary 1.1 Review and approve the Full Business Case for Cross City Bus Package 6 West, releasing £13.005m from CRSTS to enable construction to improve bus journeys on route 74, on the A41 Soho Road corridor between West Bromwich and Birmingham. 1.2 This will be achieved through the delivery of bus lanes with enforcement, improved bus shelters and customer experience, junction and crossing improvements and supporting changes to remove delays from the network.
2. Matters for Consideration
2.1Cross City Bus is a CRSTS funded scheme programme for the delivery of bus priority measures within the West Midlands region, being delivered as part of the Bus Priority Programme. Package 6 is one of the six work packages within the scheme programme. Package 6 West provides bus priority measures between Birmingham city centre and West Bromwich to support bus service 74 which operates along this corridor. This will lead to improved bus journey times and improved journey time reliability. It will link with Package 6 East, currently also preparing for delivery, to provide new Cross City bus services increasing journey opportunities and destination accessibility across the region.
2.2The A41 Soho Road, a key local centre is also part of the West Midlands Key Route Network and is a major link between Birmingham, West Bromwich and the wider Black Country. The proposed scheme for the A41 corridor aims to improve bus journey times and reliability and encourage modal shift away from private vehicles to more sustainable modes of travel. This will support enhanced connectivity and accessibility by public transport which is crucial to reducing congestion, air pollution and encouraging more sustainable and healthier lifestyles.
2.3Within the Birmingham City Council boundary, works will be delivered by TfWM through the Bus Priority Programme contractor, John Sisk and Sons. These works include a new bus gate at Island Road/Holyhead Road, 2.1km of new peak hour bus lanes, junction improvements, pedestrian crossing improvements, and enhanced passenger facilities at bus stops. Each bus stop location has been individually reviewed and will receive the required upgrades which may differ from stop to stop. 15 bus shelters will be provided with new CCTV coverage.
2.4In Sandwell works including pedestrian crossing improvements and improved passenger facilities at bus stops will be delivered by Sandwell MBC. Some bus stops have already been upgraded by TfWM’s asset team.
2.5The scheme aims to reduce bus journey time by at least 2 minutes with at least a 5% increase in bus patronage and a 2% increase in passenger satisfaction with the upgraded facilities.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor Mike BirdCommittee Member - Voting, present, as expected, virtual
CB
Councillor Christopher BurdenCommittee Member - Voting, present
SC
Councillor Steve ClarkCommittee Member - Voting, present
MM
Councillor Majid MahmoodCommittee Member - Voting, present
JO
Councillor Jim O'BoyleCommittee Member - Voting, present
SS
Sue SummersCommittee Member - Non-Voting, apologies
Hear about the next one first
Follow Investment Board at West Midlands Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.