Resolved

Approved Conditions: 1. With the exception of the detailed matters referred to by the conditions of this consent, the development hereby approved shall be carried out in accordance with the details shown on plan reference: · ASME 005 Proposed Site Layout dated 24/02/2011 (received 04.07.2011); · ASME 006 Plan, Elevations and Siting of Portacabin dated 26/03/2011 (received 11.04.2011); and · ASME 007 Plan and Elevations of Workshop dated 26/03/2011 (received 11.04.2011); and document reference: · ASME Welding Services Exterior Yard Lighting dated 16.03.2011 (received 11.04.2011); and · Specification Sheet for Bike Stand (received 04.07.2011). 2. Before any part of the development hereby approved is commenced, particulars/samples of the materials to be used for the external walls and roofs of the buildings shall be submitted to and approved in writing by the Local Planning Authority. The development shall be constructed only in accordance with the approved materials. 3. Before any part of the development hereby approved is commenced, particulars/samples of the materials to be used for the boundary wall and fence shall be submitted to and approved in writing by the Local Planning Authority. The development shall be constructed only in accordance with the approved materials. 4. Prior to the first use of the ancillary training facility, the car park indicated on the approved plan shall be marked out and the cycle stands shall be installed and retained thereafter. 5. Any development of the site shall be drained on separate foul and surface water systems. All foul drainage shall be connected to the foul sewers and only uncontaminated surface water shall be connected to the surface water system. 6. All new hard standing/parking areas should be constructed from porous materials to a specification to be submitted to, and approved in writing by, the Local Planning Authority prior to the commencement of the development. 7. The use hereby permitted shall not be carried out except during the following hours: · Monday to Friday 08:00 - 18:00, · Saturday 09:00 - 17:00, · Sunday/Bank Holidays 10:00 - 16:00. 8. No development shall be started until an investigation and assessment of the nature and extent of any contamination of the site has been submitted to and approved in writing by the Local Planning Authority. The assessment shall identify any remedial measures required to deal with any hazards identified and such measures shall be implemented before the occupation of any of the buildings hereby permitted. 9. The proposed development is within ... view the full minutes text for item 13.
Word for word from the decision Wigan published for this meeting. Source: democracy.wigan.gov.uk

Follow this further

Built from Wigan's papers

What the report saysPro

Report to Planning Committee

Planning Committee

Date: 23rd August 2011 THE LOCAL GOVERNMENT (ACCESS TO INFORMATION) ACT 1985

LIST OF BACKGROUND PAPERS FOR PLANNING AND ADVERTISEMENT APPLICATIONS ON THE AGENDA OF THE PLANNING COMMITTEE

The Background Papers for the Planning and Advertisement Applications are:

1. The Appropriate Development Information Folder: This is a file with the same reference number as that shown on the Agenda for the Application. It contains the following documents:

(a) the application forms; (b) plans of the proposed development; (c) site plans; (d) certificate relating to ownership of the site; (e) consultation letters and replies to and from statutory consultees and bodies; (f) letters and documents from interested parties; (g) memoranda of consultation and replies to and from Departments of the Council.

2. Any previous Development Information Folders referred to in the Schedule or Reports in item 2 on the Agenda for the particular application or in the Development Information Folder specified above.

3. The North West of England Plan – the Regional Spatial Strategy to 2021 forms part of the statutory development plan for the borough. However the Government has announced that it intends to abolish all Regional Spatial Strategies. This abolition is to be implemented through the Localism Bill which was published in December 2010 and is likely to become law during 2011.

4. The Replacement Unitary Development Plan: Adopted April 2006 minus policies R1, R1A and EM1F which have not been saved as part of the Development Plan.

5. The emerging Core Strategy of the Local Development Framework

6. Applications with Background Papers additional to those specified in 1 to 3 above are set out in the following table. These documents may be inspected at the Places Directorate: Economy, Waste and Infrastructure, Civic Buildings, New Market Street, Wigan, Greater Manchester.

APPLICATIONS WITH ADDITIONAL BACKGROUND PAPERS

Application No.: Additional Background Papers

Gillian Bishop Corporate Director Places CRITERIA FOR SITE VISITS AS AGREED 8 FEBRUARY 1994 AND AMENDED ON 12 MARCH 2003

Applications, which raise issues, which are likely to require, detailed first hand knowledge of the site and its surroundings to enable a well-informed decision to be taken.

Major proposals which are contrary to UDP policies and proposals but which have significant potential benefit such as job creation or retention, environmental enhancement, removal of non-confirming uses, etc.

Proposals which could significantly affect a town centre or a neighbourhood by reason of economic or environmental impact.

Proposals which would significantly affect the volume or characteristics of road traffic in the area of a site.

Significant proposals in the Green Belt.

Proposals which relate to new or novel forms of development.

Developments which have been undertaken and which, if refused permission would normally require enforcement action to remedy the breach of planning control.

Development which could create significant hazards or pollution. SITE VISITS Members are advised to view the plans of planning applications in the Committee Room in the hour before the meeting Site Visits Index

23rd August 2011

Application No Location Speaking Reference on And Ward Arrangements associated documents A/11/75498 ASME Welding Services One speaker against A (Abram) Unit 1 for 4 minutes One Albert Colliery Estate speaker in favour for Bolton House Road 4 minutes Bickershaw Wigan Council

Report to Planning Committee 23rd August 2011

Application No: A/11/75498

Speaking arrangements:

One speaker against for 4 minutes One speaker in favour for 4 minutes

Applicant: [name removed] Proposed: To use the site as a welding/fabrication contractors with ancillary training facilities together with erection of workshop, portable cabin, erection of 2.4m high fencing, security lighting and new vehicular access thereto.

Location: ASME Welding Services Unit 1 Albert Colliery Estate Bolton House Road, Bickershaw

Ward: Abram

Representations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Planning and related applications:Report 228 KB DownloadRead as text

At this meeting

Whole meeting
12MinutesOn the agenda
13Planning and related applicationsThis decision

Who was there

8 of 21 attended
PP
Councillor Paul PrescottChairman, apologies
BB
Councillor Brendan BowenCommittee Member, present
JE
Councillor Jim EllisCommittee Member, apologies
SJ
Councillor Susan June GreensmithCommittee Member, present
SJ
Councillor Stephen John HellierCommittee Member, present
JH
Councillor John HiltonCommittee Member, present
PL
Councillor Patricia Lynne HollandCommittee Member, apologies
MY
Councillor Mrs Yvonne KlieveCommittee Member, apologies
PA
Councillor Paul A LiptrotCommittee Member, present
JP
Councillor Jeanette PrescottCommittee Member, apologies
MA
Councillor Margaret Ann RamplingCommittee Member, present
RT
Councillor Robert Thompson SplaineCommittee Member, apologies

All 21 on the meeting page

On this subject at Wigan

Search all
  1. Planning and related applicationsThis decision
  2. Planning Related ItemsApproved
  3. Planning Related ItemsApproved
  4. Planning Related ItemsApproved
  5. Planning Related ItemsRefused
  6. Planning Related ItemsApproved

More from Wigan Planning Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 A/25/099558/FULL - Erection of detached dwelling, formation of new shared vehicular access and alterations to existing driveway, following demolition of existing garage.Approved Vote: In Favour (of Approval) 9 Against (Approval) 0 Abstain 1 The Committee approve the planning applicatio... Approved Open
4 Aug 2026 A/26/100488/FULL - Change of use of land to accommodate a short stay holiday let accommodation comprising of a shepherd's hut, gazebo and associated landscape works (Retrospective application).Approved Vote: In Favour (of Approval) 13 Against (Approval) 1 Abstain 0 The Committee approve the planning applicati... Approved Open
7 Jul 2026 A/26/100333/FULL - Erection of a coffee shop drive-thru unit (Sui Generis) with associated landscaping, supporting infrastructure and engineering works.Approved Vote: In Favour (of Approval) 11 Against (Approval) 1 Abstain 1 The Committee approve the planning applicati... Approved Open
7 Jul 2026 A/26/100770/FULL - Conversion of existing premises (Use Class E) to provide two commercial units within Use Class E at ground floor, with new shopfronts and alterations to fenestration, together with two self-contained one-bed flats at first floor (Use Class C3).Approved Vote: In Favour (of Approval) 12 Against (Approval) 1 Abstain 0 The Committee approve the planning applicati... Approved Open
14 Apr 2026 A/25/09945/MAJOR - Change of use of Haigh Hall to a mixed-use cultural venue comprising art galleries, education suite, event spaces, restaurant/café, retail, office and bedroom accommodation, together with a rooftop extension to form a barApproved Vote: In Favour (of Approval) 11 Against (Approval) 0 Abstain 1 The Committee approve the planning applicati... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies