2016/17 Corporate Risk Register – Q1 Update Report
Risk Number and Unmanaged Risk Original Key Existing Controls Current Risk Rating Current Risk Description Rating Risk Score Score 1.Financial Resilience Impact 20 Financial planning, management and reporting Impact 12 Management of demand
Likelihood
Likelihood Programmes to reduce costs Programmes to increase revenue
Lead Responsibility Director of Finance / S151 Officer Additional Controls – Improving financial management - Accountability statements issued to all Chief Officers and Senior Managers with budget Quarter 1 update responsibility. All were signed and returned. Progress against delivery of the budget and savings is being monitored and reported.
Reducing costs Integration with Health – Work has continued towards implementation of Integrated Community Hubs for Adults and Older People Services and the development of an integrated commissioning hub which will see the implementation of a single pooled budget. Enhanced Transformation Programme - programme is developing, with two sub programmes which align activity from the Medium Term Financial Strategy themes to support the delivery of the Strategy. Further activity to deliver savings for 2017/18 is underway. Working across the Liverpool City Region (LCR) - Partners are developing a number of approaches to improve financial resilience and generate efficiencies whilst also delivering improved outcomes. This includes a shared services initiative. Outline business cases for a number of services have been developed and a full business case for a joint LCR Procurement service will be produced later in the Summer.
Increasing revenue Business Rates Retention Pilot - The LCR’s submission to be a pilot was sent to the government in June. A response is awaited. Commercialisation - On 27 June Cabinet approved a report to develop our approach to be more commercial. Work is underway to identify specific areas of the Council which could benefit from a more commercial approach and where it may be possible to yield some financial benefits, both in-year and in future years. Implementation of Growth Plan - Market engagement has taken place as a first stage for implementing the Wirral Health Related Worklessness programme. Key Wirral projects have been included in the LCR’s Land and Property Development pipeline. The International Festival for Business which took place in the City region in June showcased Wirral’s key investment assets and businesses. There has been a refresh of the Council’s collaboration agreement with the Chamber of Commerce which aims to ensure that the number of businesses operating within the Borough continues to increase. Risk Number and Unmanaged Risk Original Key Existing Controls Current Risk Rating Current Risk Description Rating Risk Score Score 2.Organisation Impact 20 Performance appraisals Impact 16 Development and Pace Accountability statements
Likelihood
Likelihood of Transformational Ad-hoc initiatives -e.g. Children’s Social Work Change HR involvement in development of business cases for Alternative Delivery Models
Lead Responsibility Strategic Director – Transformation & Resources Additional Controls – Capacity and Expertise - Work to develop a culture action programme and action plan for the organisation is progressing. The Quarter 1 update establishment, initial structure and resources for the development of a Transformation Office have been agreed. Internal recruitment has been completed and additional recruitment initiated. A procurement exercise has been completed for interim support from a partner to develop and resource transformational change.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2016/17 CRR Controls 300616Report | 111 KB | DownloadRead as text |
PDF |
CORPORATE RISK REGISTER: Q1 2016/17 UPDATEReport | 146 KB | Download |
Follow Audit and Risk Management Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jun 2026 | External Audit Plan for Wirral Council 2025-26Resolved – That the external audit plan for Wirral Council’s Statutory financial statements for 2025/26 as prepared b... | Noted | Open |
| 24 Jun 2026 | External Audit Plan for Merseyside Pension Fund 2025-26Resolved – That the external audit plan for the Merseyside Pension Fund’s Statutory financial statements for 2025/26 ... | Noted | Open |
| 24 Jun 2026 | Annual governance statement 2025/26Resolved – That the draft Annual Governance Statement for 2025/26, including the actions planned in 2026/27 to addres... | Approved | Open |
| 24 Jun 2026 | Birkenhead town centre management action plan updateResolved – That 1. The progress made to date in implementing the Birkenhead Town Centre Management Action Plan recomm... | Noted | Open |
| 24 Jun 2026 | Annual cctv surveillance activity reportResolved – That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.