Resolved
That the revised be formally adopted.
Cabinet approved this item on Monday 6 November 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That the revised be formally adopted.
That the revised Corporate Risk Management Policy be formally adopted. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION
1.1The adoption of a revised Risk Management Policy is a key element of the Council’s approach to managing risk.
1.2In line with the governance arrangements for risk management Cabinet is responsible for formally adopting any updated version of the Policy.
2.0OTHER OPTIONS CONSIDERED
2.1The Council has committed itself to an annual refresh of the policy. Changes within the Council and in risk management practice also make it appropriate to update the document.
3.0BACKGROUND INFORMATION
INTRODUCTION
3.1Like all organisations the Council has to deliver its objectives in the face of a complex and increasingly dynamic environment. The uncertainty created by that environment presents it with both opportunities and threats. So having a robust and effective framework for addressing risk and uncertainty is vital to the authority’s success.
3.2A key value for the Council is to be ‘risk aware, not risk averse’. This makes the need for an effective approach to handling risk even more important.
3.3The purpose of a risk management policy is to set out an organisation’s overall attitude to risk and uncertainty to confirm its commitment to managing risk to provide a high level view of the risk management process itself and to set out corporate requirements around how risk is to be handled. It is a key element of an organisation’s overall risk management framework.
THE PROCESS
3.4Under the governance structure for risk management any update to the Policy is considered by the Strategic Leadership Team (SLT) then by Audit & Risk Management Committee before being put to Cabinet for formal adoption. The Corporate Governance Group also has a specific responsibility for considering changes to the Council’s risk management framework.
3.5A number of significant changes were made to the Policy document in 2016 reflecting the adoption of the Wirral Plan the New Operating Model and the revised governance arrangements for the Transformation Programme. The more modest changes in the structure and governance of the Council since then have been confirmed through meetings which the Senior Risk and Insurance officer has held with the Intelligence Team, Transformation Office and Internal Audit. These have been incorporated into the revised draft document. 3.6 Recommendations from the annual Internal Audit investigation into the Council’s risk management framework published in June 2017 have been taken into account in the revised Policy.
3.7The revised document was considered by the Corporate Governance Group on 16 August and by SLT on 5 September. It was subsequently approved by Audit & Risk Management Committee on 25 September.
PROPOSED CHANGES
3.8All amendments are highlighted in shaded text within the body of the document.
GOVERNANCE REVIEW
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Risk Management PolicyReport | 104 KB | DownloadRead as text |
PDF |
Risk Management Policy 2017Report | 313 KB | Download |
Follow Cabinet at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jul 2020 | MinutesThat the Minutes of the meetings of the Cabinet held on 17 and 24 February 2020 be confirmed as a correct record. | Decided | Open |
| 27 Jul 2020 | Executive Key Decisions Taken Under Delegated PowersThat the following Key Decisions taken under delegated authority for the period 21 February 2020 to the date of publi... | Noted | Open |
| 27 Jul 2020 | Capital Monitoring Quarter 1 2020/21That (1) the Cabinet recommends to the Council the approval of additional funding for the schemes referred to in para... | Approved | Open |
| 27 Jul 2020 | Financial Monitoring Outturn 2019-20That (1) Revenue (a) it be noted that the gross expenditure has been balanced to gross income with the appropriate al... | Noted | Open |
| 27 Jul 2020 | Treasury Management Annual Report 2019/20That (1) the 2019/20 Treasury Management Annual Report be agreed and recommended to the Council for approval at its m... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.