Quarter 1 Budget Monitoring Report - Capital

Noted Executive 1 paper

Cabinet noted this item on Monday 16 July 2018. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

That (1) the spend at Quarter 1 of £5.0 million, with 25% of the financial year having elapsed be noted; (2) the additional funding for the 7 schemes set out below be approved: · Pensby Wood fit out costs (£172,000) · Beechwood Recreation Centre Additional Works (£430,000) · Frankby Cemetery Extension (£90,000) · Floral Pavilion Audio Mixing Desk Replacement (£35,000) · BAMN Commercial Settlement (£305,000) · Floral Pavilion Chiller Unit (£55,000) · The Oval Grandstand Structural Works (£55,000) (3) the revised Capital Programme of £86.4 million set out below be agreed and referred to the Council: Capital Programme 2018/19 at 30 June 2018 Capital Strategy Revised Programme Actual Spend June 2018 £000 £000 £000 Adult Care & Health 7,912 8,543 143 Children & Families 19,099 20,852 2,200 Environment 225 50 0 Finance and Resources 5,213 4,287 130 Highways & Transport 13,787 20,409 1,954 Housing & Planning 7,542 7,791 375 Jobs & Growth 16,785 18,697 0 Law & Order 0 83 38 Leisure & Recreation 3,998 5,679 117 Total expenditure 74,561 86,391 4,957 and (4) the additional grants detailed below be agreed: Significant Variations (> £0.2m) to the 2018/19 Programme Scheme £000 Adult Care & Health Pensby Wood - re-profiling from 2017/18 £0.310m; additional requirement £0.172m. Children & Families Primary Places - re-profiling from 2017/18 Healthy Pupils Fund - additional grant allocation Special Educational Needs and Disabilities (SEND) - additional grant allocation. Improvement Plan funded by the flexible use of capital receipts - re-profiling Environment Cemetery extensions and improvements - re-profiling from 2017/18 Finance and Resources Windows 10 rollout - re-profiling - £0.1m carried forward from 2017-18 and £1.0m brought forward from 2019/20 Data Centre - re-profiling from 2017/18 Improvement Plan - originally to be funded from capital receipts but now from revenue Fund to assist land assembly - re-profiling from 2017/18 Highways & Transport Bridges - re-profiling from 2017/18 £0.707m and additional grant notification £0.150m. Dock bridges – re-profiling from 2017/18 £0.610m; additional ... view the full minutes text for item 11.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Cabinet

Recommendations

1 To note the spend at Quarter 1 of £5.0 million, with 25% of the financial year having elapsed.

2 To approve additional funding for the 7 schemes referred to in paragraph 3.10. 3 To agree and refer to Council the revised Capital Programme of £86.4 million (Table 1).

4. To agree the additional grants detailed in section 3.1.2. SUPPORTING INFORMATION

Reasons for recommendations

1.1Regular monitoring and reporting of the Capital Programme enables decisions to be taken faster which may produce revenue benefits and will improve financial control of the Programme.

2.0OTHER OPTIONS CONSIDERED

2.1No other options have been considered.

3.0BACKGROUND INFORMATION

ORIGINAL AND PROPOSED CAPITAL PROGRAMME FOR 2018/19

3.1The Programme for 2018/19 is subject to change. It presently reflects the following changes which are then detailed in Tables 1 and 2.

£000 Programme agreed by Cabinet on 19 February 2018 74,561 Year end re-profiling for 2017/18 10,482 Additional grants and contributions 7,740 Additional requirements 1,142 Reduced requirements (2,700) Net re-profiling to 2019/20 (4,834) Revised 2018/19 Programme 86,391

Table 1: Capital Programme 2018/19 at 30 June 2018

Capital Revised Actual Strategy Programme Spend June 2018 £000 £000 £000 Adult Care & Health 7,912 8,543 143 Children & Families 19,099 20,852 2,200 Environment 225 50 0 Finance and Resources 5,213 4,287 130 Highways & Transport 13,787 20,409 1,954 Housing & Planning 7,542 7,791 375 Jobs & Growth 16,785 18,697 0 Law & Order 0 83 38 Leisure & Recreation 3,998 5,679 117 Total expenditure 74,561 86,391 4,957

3.2Followings reviews reported and agreed by the Investment and Change Board and the Technical Design Authority a number of schemes that were previously classed as deferred are now included in the Capital Strategy figure above. These total £3.7 million. The other significant variances which have arisen since the Budget was set are shown in Table 2.

Table 2: Significant Variations (> £0.2m) to the 2018/19 Programme

Scheme £000 Adult Care & Health Pensby Wood - re-profiling from 2017/18 £0.310m; 482 additional requirement £0.172m.

Children & Families Primary Places - re-profiling from 2017/18 742 Healthy Pupils Fund - additional grant allocation 245 Special Educational Needs and Disabilities (SEND) - 206 additional grant allocation. Improvement Plan funded by the flexible use of capital receipts - re-profiling 1,100

Environment Cemetery extensions and improvements - re-profiling from 226 2017/18

Finance and Resources Windows 10 rollout - re-profiling - £0.1m carried forward from 1,100 2017-18 and £1.0m brought forward from 2019/20 Data Centre - re-profiling from 2017/18 339 Improvement Plan - originally to be funded from capital (2,700) receipts but now from revenue Fund to assist land assembly - re-profiling from 2017/18 246

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Quarter 1 Budget Monitoring Report: CapitalReport 335 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
PD
Councillor Phil DaviesCommittee Member, present
PB
Councillor Phillip BrightmoreCommittee Member, apologies
AD
Councillor Angela DaviesCommittee Member, present
GD
Councillor George DaviesCommittee Member, present
CJ
Councillor Chris JonesCommittee Member, present
BM
Councillor Bernie MooneyCommittee Member, present
MP
Councillor Matthew PatrickCommittee Member, present
PS
Councillor Paul StuartCommittee Member, present
SW
Councillor Stuart WhittinghamCommittee Member, present
JW
Councillor Janette WilliamsonCommittee Member, present

On this subject at Wirral

Search all
  1. Quarter 1 Budget Monitoring Report - CapitalThis decision
  2. 2026/27 Revenue Budget Monitoring for Quarter One (The Period to 30 June 2026)Noted
  3. 2026/27 Budget Monitoring for Quarter One (the period to 30 June 2026)Agreed
  4. 2026-27 budget monitoring report quarter 1Decided
  5. 2025/26 Budget Monitoring for Quarter ThreeNoted
  6. 2025/26 Budget Monitoring for Quarter Three (the period to 31 December 2025)Noted

More from Wirral Cabinet

All decisions
MeetingDecisionOutcome
27 Jul 2020 MinutesThat the Minutes of the meetings of the Cabinet held on 17 and 24 February 2020 be confirmed as a correct record. Decided Open
27 Jul 2020 Executive Key Decisions Taken Under Delegated PowersThat the following Key Decisions taken under delegated authority for the period 21 February 2020 to the date of publi... Noted Open
27 Jul 2020 Capital Monitoring Quarter 1 2020/21That (1) the Cabinet recommends to the Council the approval of additional funding for the schemes referred to in para... Approved Open
27 Jul 2020 Financial Monitoring Outturn 2019-20That (1) Revenue (a) it be noted that the gross expenditure has been balanced to gross income with the appropriate al... Noted Open
27 Jul 2020 Treasury Management Annual Report 2019/20That (1) the 2019/20 Treasury Management Annual Report be agreed and recommended to the Council for approval at its m... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies