Resolved
Resolved – That the report be noted.
Audit and Risk Management Committee noted this item on Monday 18 November 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the report be noted.
Audit and Risk Management Committee Monday, 18 November 2019
REPORT TITLE: Corporate Risk Management Update
REPORT OF: Director of Finance and Investment
REPORT SUMMARY An update on current risk management arrangements and the plans for work to further embed the arrangements for managing risk across the Council, following the appointment of the Risk, Continuity and Compliance Manager on 1st October 2019.
RECOMMENDATION That the report be noted. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1To enable the committee to understand the Authority’s most significant risks, the associated mitigating controls and the risk management framework in order to fulfil its role of providing independent assurance of the Council’s Risk Management Framework.
2.0OTHER OPTIONS CONSIDERED
2.1No other options considered.
3.0BACKGROUND INFORMATION
3.1It is just over 12 months since the report to this Committee about the improvements needed to the Council’s approach to managing risk. Work has focussed on enhancing arrangements for greater ownership of risk amongst executive and political leaders and greater accountability for the management of risks. This has included creating more capacity to support the risk management process and improved reporting arrangements to ensure that the corporate risk register reflects the most significant risks to delivery of the Council’s objectives
3.2As was reported at the ARMC meeting in September the Corporate, Directorate and Programme Management Office risk registers are being regularly updated. In the case of service departments this has followed the linkage of risk management processes to the service planning process for 2019/20. Information on these risk registers is also included in the performance reporting available to directors and managers via the use of the Power BI tool. The Risk Management Support Officers (RMSO) Group has met on a monthly basis and helps to strengthen of the Council’s risk management arrangements within directorates.
3.3The revised Corporate Risk Register (CRR) has been reported to the last two committee reports in July and September. The latest version is attached as an appendix to this report.
Current Update
3.4The new Risk, Continuity and Compliance (RC&C) Manager started with the Authority on 1st October 2019. During these initial weeks, time is being spent carrying out an appraisal of the current arrangements for managing risk. This has included attending SLT, Corporate Governance Group and the October meeting of the RMSO Group. In addition, the RC&C Manager is holding individual meetings with Directors and the Risk Management Support Officers. Discussions have focussed on understanding the application and operation of the risk framework across the Council. 3.5 One key change recommended has involved the shift from monthly to quarterly update of the Corporate and Directorate Risk Registers. This will allow more time to focus on the content of the risk registers as opposed to merely complying with the process.
3.6Directorates can review their risks more regularly but the reporting of updates to both the CRR and Directorate Risks will be aligned to the ARMC meetings.
3.7Several of the Corporate Risks have seen specific work involving the RC&C Manager:
Corporate Risk 14 Health and Safety - a mechanism for identifying and monitoring the health and safety risks across the Council is in development. A review has been commissioned from Zurich Risk Engineering, with costs to be covered by the existing Risk Management fund held by Zurich Risk Engineering. This includes a comparative gap analysis against relevant legislation alongside a deep dive into key service areas to identify areas of both positive and negative safety compliance and culture.
Corporate Risk 15 Information Management – a risk workshop was held on 30th October to identify the key information risks across the Council which will form the basis of an Information Risk Register monitored and maintained by the Information Governance Board.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Risk Management UpdateReport | 109 KB | DownloadRead as text |
PDF |
Enc. 1 for Corporate Risk Management Update PS (1)Report | 305 KB | Download |
Follow Audit and Risk Management Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jun 2026 | External Audit Plan for Wirral Council 2025-26Resolved – That the external audit plan for Wirral Council’s Statutory financial statements for 2025/26 as prepared b... | Noted | Open |
| 24 Jun 2026 | External Audit Plan for Merseyside Pension Fund 2025-26Resolved – That the external audit plan for the Merseyside Pension Fund’s Statutory financial statements for 2025/26 ... | Noted | Open |
| 24 Jun 2026 | Annual governance statement 2025/26Resolved – That the draft Annual Governance Statement for 2025/26, including the actions planned in 2026/27 to addres... | Approved | Open |
| 24 Jun 2026 | Birkenhead town centre management action plan updateResolved – That 1. The progress made to date in implementing the Birkenhead Town Centre Management Action Plan recomm... | Noted | Open |
| 24 Jun 2026 | Annual cctv surveillance activity reportResolved – That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.