Resolved (64:0) – That the recommendations contained within minute 51 of the Policy and Resources Committee of 1 September, 2021, be agreed and that the following be approved: (1) additional funding for the schemes referred to in section 3.5 of the report; (2) a revised Capital Programme of £79.7 million for 2021-22, including the virements referred to in Appendix 3 of the report.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
POLICY AND RESOURCES COMMITTEE Wednesday, 1 September 2021
REPORT TITLE: CAPITAL MONITORING QUARTER 1 2021/22 REPORT OF: DIRECTOR OF RESOURCES (S151 OFFICER)
REPORT SUMMARY
This report provides an update on the progress of the Capital Programme 2021/22 at the end of June 2021. It recommends that Committee agree the revised 2021/22 Capital Programme of £79.7 million which takes account of re-profiling, virements, additional funding requirements and grant variations identified since the Capital Programme was formally agreed on 1st March 2021.
This matter is a key decision which affects all Wards within the Borough.
RECOMMENDATION/S
The Policy and Resources Committee recommends to Council:
1 the approval of additional funding for the schemes referred to in section 3.5 in this report.
2 the approval of the revised Capital Programme of £79.7 million for 2021-22, including the virements referred to in Appendix 3 in this report. Also, that the Policy and Resources Committee agrees that the on-going review and reprofiling of the Capital Programme is reported to members in the next quarterly capital monitoring report. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1Regular monitoring and reporting of the Capital Programme enables decisions to be taken faster, which may produce revenue benefits and will improve financial control in Wirral Council.
2.0OTHER OPTIONS CONSIDERED
2.1Other reporting frequencies could be considered, but quarterly reporting is a standard practice.
3.0BACKGROUND INFORMATION
3.1Capital Programme 2021/22 Position by Directorate
Table 1: Wirral Council 2021/22 Full Year Capital Budget and Forecast Position Budget Forecast Variance Variance Programme £m £m £m % Adult Care & Health 6.561 3.494 -3.067 -47% Children, Families & Education 9.304 5.504 -3.800 -41% Corporate Schemes 11.327 12.071 0.744 7% Neighbourhoods 23.046 23.584 0.538 2% Regeneration & Place 59.872 32.696 -27.176 -45% Resources 6.459 2.368 -4.091 -63% Total 116.569 79.717 -36.852 -32%
NB: items of significant scheme variation are included below.
Capital Programme 2021/22 Position by Committee
Table 2: Wirral Council 2021/22 Full Year Capital Budget and Forecast Position Budget Forecast Variance Variance Programme £m £m £m % Adult Social Care & Health 8.408 3.621 -4.787 -57% Children, Young People & Education 10.504 5.534 -4.970 -47% Economy, Regneration & Development 30.702 17.564 -13.138 -43% Environment, Climate Emergency & Transport 22.697 23.840 1.143 5% Housing 8.552 7.976 -0.576 -7% Policy & Resoures 25.316 15.706 -9.610 -38% Tourism, Communities, Culture & Leisure 10.390 5.476 -4.914 -47% Total 116.569 79.717 -36.852 -32%
3.1.1 Table 1 provides an update on the 2021/22 capital Programme. A number of significant variations have arisen since the programme was agreed in March 2021. These include the re-profiling of expenditure into and out of the 2021/22 financial year, inclusion of additional grant funded schemes, variations to spend forecasts and the inclusion of potential new capital schemes that are seeking funding via this report. Further detail is provided below.
3.1.2 Given the budgetary pressures that the Council faces, which have been exacerbated by the COVID-19 outbreak, a review of the programme continues to try and identify schemes that may no longer be financially viable, essential or deliverable. This review has resulted in the reprofiling of budget into future years of £54.371 million. It is anticipated that further reductions and/or deferrals of budget will be made as the review continues. Such deferrals will reduce the borrowing costs incurred during 2021/22 and also delays the resultant Minimum Revenue Provision (MRP) charges into future years.
3.1.3 Appendix 1 of this report categorises the movement in the forecast programme.
3.2Scheme Updates
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Appointment of Independent PersonsResolved – That the appointment of the following Independent Persons of the Constitution and Standards Committee be a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.