Resolved
That the report be noted.
Audit and Risk Management Committee noted this item on Monday 24 January 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
The Audit and Risk Management Committee is recommended to note the report. SUPPORTING INFORMATION 1.0 REASON/S FOR RECOMMENDATION/S
1.1To enable the committee to understand the Authority’s most significant risks, the associated mitigating controls, and the risk management framework to fulfil its role of providing independent assurance of the Council’s Risk Management Framework.
2.0OTHER OPTIONS CONSIDERED
2.1No other options considered appropriate as failure to report this information would demonstrate ineffective governance and non-compliance with professional best practice.
3.0BACKGROUND INFORMATION
3.1Due to the short reporting timescale between this meeting and the last update to the Committee and the postponement of the session with the Senior Leadership Team in December there has been limited change in the Corporate Risk Register.
3.2Work continues on developing the Improvement Plan in response to the two reports from the Department of Levelling Up, Housing and Communities (DLUHC). A draft plan is to go to the first meeting of the Independent Panel in mid-January and following that on to committee before the end of March.
3.3More information on the project, within the Improvement Plan, specifically related to risk management will be shared with this Committee at a future date.
3.4One of the first actions to be completed is the training session on risk management for all members.
Risk Management Training for Members 3.5 A training session open to all councillors is scheduled for 19th January. At the time of writing this report over 20 councillors had accepted the invitation to attend. A verbal update on attendance figures will be available at the committee meeting.
ARMC Risk Sub-Group 3.6 The next meeting of the group is scheduled for 16th February.
Corporate Risk Register (CRR) 3.7 As reported at the last Committee a face-to-face focus session with the Senior Leadership Team was planned for 6th December 2021 to review the risks in more detail and challenge their position on the CRR and mitigating activity. Unfortunately, this session was postponed and will now take place on 2nd March 2022.
Other Risk Management Activity 3.8 During the discussion of the risk management report at the last Committee meeting there were several questions relating to the flow of risk information and the scoring mechanism for risks within risk registers. In order to reassure the Committee of the processes and methodology in operation additional detail for both areas are outlined below. Scoring Process 3.9 Risks are scored for both likelihood of the risk occurring and the impact if the risk were to occur. Both scores are out of 5 and a chart defining the different levels is part of the corporate risk register template and associated guidance. The scoring definition charts are attached at Appendix 1.
3.10Currently the Council uses a 5x5 scoring matrix and a three-tiered colour coding system; red, amber, green. See tables below showing the combined total of the likelihood multiplied by the impact scores and associated colour banding.
Table 1. Scoring Matrix
Impact → 1 2 3 4 5 Very Low Low Medium High Very High 5 Very High 5 10 15 20 25 Likelihood→
4 High 4 8 12 16 20 3 Medium 3 6 9 12 15 2 Low 2 4 6 8 10 1 Very Low 1 2 3 4 5
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Risk Management UpdateReport | 100 KB | DownloadRead as text |
PDF |
Enc. 1 for Corporate Risk Management UpdateReport | 37 KB | Download |
Follow Audit and Risk Management Committee at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jun 2026 | External Audit Plan for Wirral Council 2025-26Resolved – That the external audit plan for Wirral Council’s Statutory financial statements for 2025/26 as prepared b... | Noted | Open |
| 24 Jun 2026 | External Audit Plan for Merseyside Pension Fund 2025-26Resolved – That the external audit plan for the Merseyside Pension Fund’s Statutory financial statements for 2025/26 ... | Noted | Open |
| 24 Jun 2026 | Annual governance statement 2025/26Resolved – That the draft Annual Governance Statement for 2025/26, including the actions planned in 2026/27 to addres... | Approved | Open |
| 24 Jun 2026 | Birkenhead town centre management action plan updateResolved – That 1. The progress made to date in implementing the Birkenhead Town Centre Management Action Plan recomm... | Noted | Open |
| 24 Jun 2026 | Annual cctv surveillance activity reportResolved – That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.