CAPITAL MONITORING QUARTER 1 2022/23

Approved Committee 1 paper

Policy and Resources Committee approved this item on Wednesday 7 September 2022. Below is the council's own wording, with the papers it was decided on.

Item47

Resolved

Resolved – That (1) Council be recommended to approve the revised Capital Programme of £147.6 million for 2022/23, including the addition of the new grant funding referred to in section 3.4. (2) The virements referred to in Appendix D to the report with a value of less than £0.5m be approved.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Policy and Resources Committee

POLICY AND RESOURCES COMMITTEE Wednesday, 7 September 2022

REPORT TITLE: CAPITAL MONITORING QUARTER 1 2022/23 REPORT OF: DIRECTOR OF RESOURCES (S151 OFFICER)

REPORT SUMMARY

This report provides an update on the progress of the Capital Programme 2022/23 at the end of June 2022. It recommends that Committee agree the revised 2022/23 Capital Programme of £147.6 million which takes account of re-profiling, virements, additional funding requirements and grant variations identified since the Capital Programme was formally agreed on 28th February 2022.

This matter is a key decision which affects all Wards within the Borough

RECOMMENDATION/S

The Policy and Resources Committee is requested to recommend to Council:

1 the approval of the revised Capital Programme of £147.6 million for 2022/23, including the addition of the new grant funding referred to in section 3.4 in this report.

The Policy and Resources Committee is recommended to:

2 approve the virements referred to in Appendix D in this report with a value of less than £0.5 million. SUPPORTING INFORMATION

1.0REASON/S FOR RECOMMENDATION/S

1.1Regular monitoring and reporting of the Capital Programme enables decisions to be taken faster, which may produce revenue benefits and will improve financial control in Wirral Council.

2.0OTHER OPTIONS CONSIDERED

2.1Other reporting frequencies could be considered, but quarterly reporting is a standard practice.

3.0BACKGROUND INFORMATION

3.1Capital Programme 2022/23 Position by Directorate

Table 1: Wirral Council 2022/23 Full Year Capital Budget and Forecast Position Forecast Budget Q1 Variance Variance Programme £m £m £m % Adult Care & Health 7.323 4.012 -3.311 -45% Children, Families & Education 16.644 12.144 -4.500 -27% Corporate Schemes 5.904 3.780 -2.124 -36% Neighbourhoods 26.078 34.489 8.411 32% Regeneration & Place 88.315 87.927 -0.388 0% Resources 7.813 5.241 -2.572 -33% Total 152.077 147.593 -4.484 -3% NB: items of significant scheme variation are included in Appendix A of this report.

Capital Programme 2022/23 Position by Committee

Table 2: Wirral Council 2022/23 Full Year Capital Budget and Forecast Position Budget Forecast Variance Variance Programme £m Q1 £m £m % Adult Social Care & Health 7.323 4.012 -3.311 -45% Children, Young People & Education 17.842 13.342 -4.500 -25% Economy, Regneration & Development 49.119 47.135 -1.984 -4% Environment, Climate Emergency & Transport 27.016 35.153 8.137 30% Economy, Regneration & Housing 20.758 22.740 1.982 10% Policy & Resoures 19.378 13.826 -5.552 -29% Tourism, Communities, Culture & Leisure 10.641 11.385 0.744 7% Total 152.077 147.593 -4.484 -3% 3.1.1 Table 1 provides an update on the 2022/23 Capital Programme. A number of variations have arisen since the original programme was agreed at the end of February 2022. These include the re-profiling of expenditure into and out of the 2022/23 financial year, inclusion of additional grant funded schemes and variations to spend forecasts. There have been no new capital schemes seeking funding via this report.

3.1.2 Given the budgetary pressures that the Council faces, a review of the programme continues to try and identify schemes that may no longer be financially viable, essential or deliverable.

3.1.3 As a result of the review carried out within Quarter 1, the following schemes in the 2022/23 programme had their funding allocations reduced:

 Transformational Capitalisation £2.124 million, budget realigned in accordance with the budget setting 2022/23, approved at Full Council February 2022

 Repurposing of £0.147 million from Health and Safety Condition Survey to Ashton Park to replace new Council borrowing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CAPITAL MONITORING QUARTER 1 2022/23Report 630 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 29 attended
JW
Councillor Janette WilliamsonChair, present
TA
Councillor Tom AndersonSpokesperson, present
PG
Councillor Phil GilchristSpokesperson, present
PC
Councillor Pat ClearySpokesperson, present
EG
Councillor Elizabeth GreyCommittee Member, present
TJ
Councillor Tony JonesCommittee Member, present
YN
Councillor Yvonne NolanCommittee Member, present
JR
Councillor Jean RobinsonVice-Chair, present
PS
Councillor Paul StuartCommittee Member, present
HC
Councillor Helen CameronCommittee Member, present
LR
Councillor Lesley RennieCommittee Member, apologies, sent representative
AH
Councillor Andrew HodsonDeputy, present

All 29 on the meeting page

On this subject at Wirral

Search all
  1. CAPITAL MONITORING QUARTER 1 2022/23This decision
  2. Capital Monitoring Quarter 1 (2026/27)Approved
  3. Capital Monitoring Quarter 3 2025/26Approved
  4. Capital Monitoring Quarter 3 2025/26Approved
  5. 2025-26 capital monitoring quarter 2Approved
  6. 2025-26 Capital Monitoring Quarter 2Approved

More from Wirral Policy and Resources Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 New Wirral PlanResolved – That the Policy and Resources Committee endorsed the new Wirral Plan for 2027 to 2031 and recommended it f... Approved Open
22 Jul 2026 Strategic Land Disposals for Affordable HousingResolved – that 1. the disposal of Council-owned land through a Strategic Housing Partnership, under the Wirral Affor... Approved Open
22 Jul 2026 Network Strategic Partner for Wide Area Network delivery and supportDecision affecting all wards. Resolved – That Policy and Resources Committee authorises the award of a contract to Th... Decided Open
22 Jul 2026 Transport for the City Region Resource FundingResolved – that, 1. the request that had been submitted to the Liverpool City Region to support the delivery of the T... Noted Open
22 Jul 2026 Parking Strategy RefreshResolved – that the Policy & Resources Committee, 1. Notes the resolution of the Environment, Climate Change and Tran... Agreed Open