Policy and Resources Committee approved this item on Wednesday 7 September 2022. Below is the council's own wording, with the papers it was decided on.
Resolved – That (1) Council be recommended to approve the revised Capital Programme of £147.6 million for 2022/23, including the addition of the new grant funding referred to in section 3.4. (2) The virements referred to in Appendix D to the report with a value of less than £0.5m be approved.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
POLICY AND RESOURCES COMMITTEE Wednesday, 7 September 2022
REPORT TITLE: CAPITAL MONITORING QUARTER 1 2022/23 REPORT OF: DIRECTOR OF RESOURCES (S151 OFFICER)
REPORT SUMMARY
This report provides an update on the progress of the Capital Programme 2022/23 at the end of June 2022. It recommends that Committee agree the revised 2022/23 Capital Programme of £147.6 million which takes account of re-profiling, virements, additional funding requirements and grant variations identified since the Capital Programme was formally agreed on 28th February 2022.
This matter is a key decision which affects all Wards within the Borough
RECOMMENDATION/S
The Policy and Resources Committee is requested to recommend to Council:
1 the approval of the revised Capital Programme of £147.6 million for 2022/23, including the addition of the new grant funding referred to in section 3.4 in this report.
The Policy and Resources Committee is recommended to:
2 approve the virements referred to in Appendix D in this report with a value of less than £0.5 million. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1Regular monitoring and reporting of the Capital Programme enables decisions to be taken faster, which may produce revenue benefits and will improve financial control in Wirral Council.
2.0OTHER OPTIONS CONSIDERED
2.1Other reporting frequencies could be considered, but quarterly reporting is a standard practice.
3.0BACKGROUND INFORMATION
3.1Capital Programme 2022/23 Position by Directorate
Table 1: Wirral Council 2022/23 Full Year Capital Budget and Forecast Position Forecast Budget Q1 Variance Variance Programme £m £m £m % Adult Care & Health 7.323 4.012 -3.311 -45% Children, Families & Education 16.644 12.144 -4.500 -27% Corporate Schemes 5.904 3.780 -2.124 -36% Neighbourhoods 26.078 34.489 8.411 32% Regeneration & Place 88.315 87.927 -0.388 0% Resources 7.813 5.241 -2.572 -33% Total 152.077 147.593 -4.484 -3% NB: items of significant scheme variation are included in Appendix A of this report.
Capital Programme 2022/23 Position by Committee
Table 2: Wirral Council 2022/23 Full Year Capital Budget and Forecast Position Budget Forecast Variance Variance Programme £m Q1 £m £m % Adult Social Care & Health 7.323 4.012 -3.311 -45% Children, Young People & Education 17.842 13.342 -4.500 -25% Economy, Regneration & Development 49.119 47.135 -1.984 -4% Environment, Climate Emergency & Transport 27.016 35.153 8.137 30% Economy, Regneration & Housing 20.758 22.740 1.982 10% Policy & Resoures 19.378 13.826 -5.552 -29% Tourism, Communities, Culture & Leisure 10.641 11.385 0.744 7% Total 152.077 147.593 -4.484 -3% 3.1.1 Table 1 provides an update on the 2022/23 Capital Programme. A number of variations have arisen since the original programme was agreed at the end of February 2022. These include the re-profiling of expenditure into and out of the 2022/23 financial year, inclusion of additional grant funded schemes and variations to spend forecasts. There have been no new capital schemes seeking funding via this report.
3.1.2 Given the budgetary pressures that the Council faces, a review of the programme continues to try and identify schemes that may no longer be financially viable, essential or deliverable.
3.1.3 As a result of the review carried out within Quarter 1, the following schemes in the 2022/23 programme had their funding allocations reduced:
Transformational Capitalisation £2.124 million, budget realigned in accordance with the budget setting 2022/23, approved at Full Council February 2022
Repurposing of £0.147 million from Health and Safety Condition Survey to Ashton Park to replace new Council borrowing.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.