Resolved
Resolved (unanimously) – That the revised Capital Programme of £147.6 million for 2022/23, including the addition of the new grant funding referred to in section 3.4 of the report be approved.
Council approved this item on Monday 10 October 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved (unanimously) – That the revised Capital Programme of £147.6 million for 2022/23, including the addition of the new grant funding referred to in section 3.4 of the report be approved.
MINUTE EXTRACT
POLICY AND RESOURCES COMMITTEE
7 SEPTEMBER 2022
47 CAPITAL MONITORING QUARTER 1 2022/23
The Director of Resources introduced the report which provided an update on the progress of the Capital Programme 2022/23 at the end of June 2022 and recommended that Committee agree the revised 2022/23 Capital Programme of £147.6 million taking account of re-profiling, virements, additional funding requirements and grant variations identified since the Capital Programme was formally agreed on 28th February 2022.
Following the setting of the budget in February 2022, a number of schemes remained unspent and the funding had been reprofiled into the capital programme as detailed in the report. The report further detailed the new grant funded schemes including the Better Care Fund Disabled Facilities Grant, the City Region Sustainable Transport Settlement and Basic and High Needs school provision. The report sought the Committee’s approval of the proposed virements within the gift of Policy and Resources Committee and the recommended approval of the revised Capital Programme to Council.
Members discussed the detail of a number of the Capital Programmes including the cost for the works to the Dock Road Bridge and the liability for the increased costs for the West Kirby Flood Alleviation Scheme. Following a detailed discussion in relation to the Secretary of State’s request to see the Council’s plan to generate additional capital receipts, the Director of Resources undertook to report back to the Committee on the proposed phasing of repaying the capitalisation funding based on the timing of capital receipts.
Resolved – That
(1) Council be recommended to approve the revised Capital Programme of £147.6 million for 2022/23, including the addition of the new grant funding referred to in section 3.4.
(2) The virements referred to in Appendix D to the report with a value of less than £0.5m be approved.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Monitoring Quarter 1 2022/23Report | 193 KB | DownloadRead as text |
Follow Council at Wirral and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jul 2026 | MINUTESResolved – That the minutes of the meetings held on 13 May 2026 and 20 May 2026 be approved as a correct record. | Approved | Open |
| 20 Jul 2026 | 2025-26 Capital OutturnResolved – That 1. the virements of budget referred to in Appendix F of the report be approved; and 2. the bids in Ap... | Approved | Open |
| 20 Jul 2026 | Revisions to the ConstitutionResolved – That the amendments to the Constitution, as detailed in sections 3.2 to 3.7 of the report, be approved. | Approved | Open |
| 20 Jul 2026 | Appointment of Independent PersonsResolved – That the appointment of the following Independent Persons of the Constitution and Standards Committee be a... | Approved | Open |
| 20 Jul 2026 | Annual Report of the Audit and Risk Management CommitteeResolved – That the ARMC Annual Report for 2025-26 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.