Resolved – That (1) the revised Capital Programme of £100 million for 2023/24, including the virements of budget referred to in Appendix C of the report be approved. (2) the additional funding for the schemes referred to in section 3.7 in the report be approved.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
The Policy and Resources Committee is requested to recommend to Council the approval of:
1 the revised Capital Programme of £100 million for 2023/24, including the virements of budget referred to in Appendix C of this report.
2 additional funding for the schemes referred to in section 3.7 in this report. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1Regular monitoring and reporting of the Capital Programme enable decisions to be taken faster, which may produce revenue benefits and will improve financial control in Wirral Council.
2.0OTHER OPTIONS CONSIDERED
2.1Other reporting frequencies could be considered, but quarterly reporting is a standard practice.
3.0BACKGROUND INFORMATION
3.1Capital Programme 2023/24 Position by Directorate
Table 1: Wirral Council 2023/24 Forecast Position Budget Forecast 1 April 23 Q2 Variance Variance Programme £m £m £m % Adult Care & Health 3.884 1.729 -2.155 -55%
Budget 1 Q2 April 23 Forecast Variance Variance Programme £m £m £m % Adult Social Care & Health 3.884 1.729 -2.155 -55% Children, Young People & Education 16.929 9.310 -7.619 -45% Economy, Regneration & Housing 102.351 53.863 -48.488 -47% Environment, Climate Emergency & Transport 31.008 23.283 -7.725 -25% Policy & Resoures 16.541 7.413 -9.128 -55% Tourism, Communities, Culture & Leisure 7.345 4.708 -2.637 -36% Total 178.058 100.306 -77.752 -44% 3.1.1 Tables 1 and 2 provide an update on the 2023/24 Capital Programme analysed on a Directorate and then Committee basis. A number of variations have arisen since the original programme was agreed at the end of February 2023 and subsequently revised via the Q1 Capital Monitoring Report. These include variations to spend forecasts and inclusion of additional grant funding and external contributions. There is one new capital funding request and a repurposing of previously approved budget, see 3.7 of this report. Within Quarter 2 there has been a net increase of £13 million of budget forecast as required in 2023/24. Appendix A of this report provides further analysis of the movement of the forecast programme across directorates during the year to date.
3.1.2 As noted above, the main movements in this year’s programme so far are in respect of deferrals of budget into future years along with the inclusion of new funding and schemes into the programme.
3.1.3 It is anticipated that further reductions and/or deferrals of budget will be made in future quarters. Such deferrals reduce the borrowing costs incurred during 2023/24 and also delays the resultant Minimum Revenue Provision (MRP) charges into future years.
3.1.4 Given the budgetary pressures that the Council faces, a review of the programme continues to try and identify schemes that may no longer be financially viable, essential, or deliverable.
3.2Reprofiling of expenditure
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Appointment of Independent PersonsResolved – That the appointment of the following Independent Persons of the Constitution and Standards Committee be a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.