Resolved – That Council be recommended to approve: 1. the revised Capital Programme of £100.996 million for 2024/25, including the virements of budget referred to in Appendix 3 of this report. 2. additional funding for Capitalisation of Regeneration Salaries, to be funded by new borrowing, as referred to in section 3.7 in this report.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
The Policy and Resources Committee is requested to recommend to Council the approval of:
1 the revised Capital Programme of £100.996 million for 2024/25, including the virements of budget referred to in Appendix 3 of this report.
2 additional funding for Capitalisation of Regeneration Salaries, to be funded by new borrowing, as referred to in section 3.7 in this report. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1Regular monitoring and reporting of the Capital Programme enable decisions to be taken faster, which may produce revenue benefits and will improve financial control in Wirral Council.
2.0OTHER OPTIONS CONSIDERED
2.1Other reporting frequencies could be considered, but quarterly reporting is a standard practice.
3.0BACKGROUND INFORMATION
3.1Capital Programme 2024/25 Position by Directorate
Table 1: Wirral Council 2024/25 Forecast Position Budget Forecast 1 April 24 Q1 Variance Variance Programme £m £m £m % Adult Care & Health 4.404 4.404 0.000 0% Children, Families & Education 18.886 18.886 0.000 0% Neighbourhoods 25.757 18.484 -7.273 -28% Regeneration & Place 79.637 54.893 -24.744 -31% Finance 4.329 4.329 0.000 0% Total 133.013 100.996 -32.017 -24%
Capital Programme 2024/25 Position by Committee
Table 2: Wirral Council 2024/25 Forecast Position Budget Q1 1 April 24 Forecast Variance Variance Programme £m £m £m % Adult Social Care & Health 4.404 4.404 0.000 0%
Children, Young People & Education 18.886 18.886 0.000 0% Economy, Regneration & Housing 68.815 45.341 -23.474 -34% Environment, Climate Emergency & Transport 27.332 20.091 -7.241 -26% Policy & Resoures 10.251 10.251 0.000 0% Tourism, Communities, Culture & Leisure 3.325 2.023 -1.302 -39% Total 133.013 100.996 -32.017 -24% 3.1.1 Tables 1 and 2 provide an update on the 2024/25 Capital Programme analysed on a Directorate and then Committee basis. A number of variations have arisen since the original Programme was agreed at the end of February 2024. These include the re- profiling of expenditure into and out of financial years, inclusion of additional grant funded schemes and variations to spend forecasts. Appendix 1 of this report provides further analysis of the movement of the forecast programme across directorates during the year to date.
3.1.2 As noted above, the main movements in this year’s Programme so far are in respect of deferrals of budget into future years along with the inclusion of new funding and schemes into the Programme.
3.1.3 It is anticipated that further reductions and/or deferrals of budget will be made in future quarters. Such deferrals reduce the borrowing costs incurred during the year (2024/25) and also delays the resultant Minimum Revenue Provision (MRP) charges into future years.
3.1.4 Given the budgetary pressures that the Council faces, a review of the Programme continues to try and identify schemes that may no longer be financially viable, essential, or deliverable.
3.2Reprofiling of expenditure
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.