Resolved – That Council be recommended to approve, 1 The revised Capital Programme of £110.316m for 2025/26, including the virements of budget referred to in Appendix 3 of the report; 2 The additional funding for the scheme referred to in section 3.3.4 in the report; 3 The authorisation for the Director of Finance to review the capital programme and identify options to reduce the borrowing requirement to mitigate the forecast overspend on the Central Birkenhead project; and 4 The revised associated Prudential Indicators to be adopted, contained within the report.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
The Policy and Resources Committee is requested to recommend to Council the approval of:
1 the revised Capital Programme of £110.316m for 2025/26, including the virements of budget referred to in Appendix 3 of this report;
2 the additional funding for the scheme referred to in section 3.3.4 in this report;
3 the authorisation for the Director of Finance to review the capital programme and identify options to reduce the borrowing requirement to mitigate the forecast overspend on the Central Birkenhead project; and
4 the revised associated Prudential Indicators to be adopted, contained within this report. SUPPORTING INFORMATION
1.0REASON/S FOR RECOMMENDATION/S
1.1Regular monitoring and reporting of the Capital Programme enable decisions to be taken faster, which may produce revenue benefits and will improve financial control in Wirral Council.
2.0OTHER OPTIONS CONSIDERED
2.1Other reporting frequencies could be considered, but quarterly reporting is a standard practice.
3.0BACKGROUND INFORMATION
3.1Capital Programme 2025/26 Position by Directorate
Table 1: Wirral Council 2025/26 Forecast Position Budget Budget Actuals Variance Programme 1 Apr 25 30 Jun 25 30 Jun 25 £m £m £m £m Adult Care & Health 1.675 0.876 -0.799 - Children, Families & Education 13.992 9.373 -4.619 1.085 Finance 5.883 5.883 0.000 0.665 Neighbourhoods 15.990 17.000 1.010 2.300 Regeneration & Place 89.832 77.184 -12.648 16.998 Total 127.372 110.316 -17.056 21.047
Capital Programme 2025/26 Position by Committee
Table 2: Wirral Council 2025/26 Forecast Position Budget Budget Actuals Variance Programme 1 Apr 25 30 Jun 25 30 Jun 25 £m £m £m £m Adult Social Care & Health 1.675 0.876 -0.799 - Children, Young People & Education 13.992 9.373 -4.619 1.085 Economy, Regeneration & Housing 72.421 68.207 -4.214 16.289 Environment, Climate Emergency & Transport 20.595 17.724 -2.871 2.253 Policy & Resources 15.130 10.926 -4.204 1.369 Tourism, Communities, Culture & Leisure 3.559 3.210 -0.349 0.051 Total 127.372 110.316 -17.056 21.047
3.1.1 Tables 1 and 2 provide an update on the 2025/26 Capital Programme analysed on a Directorate and then Committee basis. A number of variations have arisen since the original Programme was agreed in March 2025. These include the re-profiling of expenditure into and out of financial years, inclusion of additional grant funded schemes and variations to spend forecasts. Appendix 1 of this report provides further analysis of the movement of the forecast programme across directorates during the year to date.
3.1.2 As noted above, the main movements in this year’s Programme so far are in respect of deferrals of budget into future years along with the inclusion of new funding and schemes into the Programme. A full breakdown can be found in Appendix 1.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.