Wirral Borough Council
Policy and Resources Committee, Wednesday 23 July 2025

Capital Monitoring Quarter 1 2025/26

Approved Committee 6 papers

Policy and Resources Committee approved this item on Wednesday 23 July 2025. Below is the council's own wording, with the papers it was decided on.

Item30

Resolved

Resolved – That Council be recommended to approve, 1 The revised Capital Programme of £110.316m for 2025/26, including the virements of budget referred to in Appendix 3 of the report; 2 The additional funding for the scheme referred to in section 3.3.4 in the report; 3 The authorisation for the Director of Finance to review the capital programme and identify options to reduce the borrowing requirement to mitigate the forecast overspend on the Central Birkenhead project; and 4 The revised associated Prudential Indicators to be adopted, contained within the report.
Word for word from the decision Wirral published for this meeting. Source: democracy.wirral.gov.uk

Follow this further

Built from Wirral's papers

What the report saysPro

Report to Policy and Resources Committee

Recommendations

The Policy and Resources Committee is requested to recommend to Council the approval of:

1 the revised Capital Programme of £110.316m for 2025/26, including the virements of budget referred to in Appendix 3 of this report;

2 the additional funding for the scheme referred to in section 3.3.4 in this report;

3 the authorisation for the Director of Finance to review the capital programme and identify options to reduce the borrowing requirement to mitigate the forecast overspend on the Central Birkenhead project; and

4 the revised associated Prudential Indicators to be adopted, contained within this report. SUPPORTING INFORMATION

1.0REASON/S FOR RECOMMENDATION/S

1.1Regular monitoring and reporting of the Capital Programme enable decisions to be taken faster, which may produce revenue benefits and will improve financial control in Wirral Council.

2.0OTHER OPTIONS CONSIDERED

2.1Other reporting frequencies could be considered, but quarterly reporting is a standard practice.

3.0BACKGROUND INFORMATION

3.1Capital Programme 2025/26 Position by Directorate

Table 1: Wirral Council 2025/26 Forecast Position Budget Budget Actuals Variance Programme 1 Apr 25 30 Jun 25 30 Jun 25 £m £m £m £m Adult Care & Health 1.675 0.876 -0.799 - Children, Families & Education 13.992 9.373 -4.619 1.085 Finance 5.883 5.883 0.000 0.665 Neighbourhoods 15.990 17.000 1.010 2.300 Regeneration & Place 89.832 77.184 -12.648 16.998 Total 127.372 110.316 -17.056 21.047

Capital Programme 2025/26 Position by Committee

Table 2: Wirral Council 2025/26 Forecast Position Budget Budget Actuals Variance Programme 1 Apr 25 30 Jun 25 30 Jun 25 £m £m £m £m Adult Social Care & Health 1.675 0.876 -0.799 - Children, Young People & Education 13.992 9.373 -4.619 1.085 Economy, Regeneration & Housing 72.421 68.207 -4.214 16.289 Environment, Climate Emergency & Transport 20.595 17.724 -2.871 2.253 Policy & Resources 15.130 10.926 -4.204 1.369 Tourism, Communities, Culture & Leisure 3.559 3.210 -0.349 0.051 Total 127.372 110.316 -17.056 21.047

3.1.1 Tables 1 and 2 provide an update on the 2025/26 Capital Programme analysed on a Directorate and then Committee basis. A number of variations have arisen since the original Programme was agreed in March 2025. These include the re-profiling of expenditure into and out of financial years, inclusion of additional grant funded schemes and variations to spend forecasts. Appendix 1 of this report provides further analysis of the movement of the forecast programme across directorates during the year to date.

3.1.2 As noted above, the main movements in this year’s Programme so far are in respect of deferrals of budget into future years along with the inclusion of new funding and schemes into the Programme. A full breakdown can be found in Appendix 1.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Movement Between Opening Budget and Quarter 1 Forecast PositionAppendix 1 52 KB Download
PDF
Scheme UpdatesAppendix 2 86 KB Download
PDF
Virements Within Quarter 1Appendix 3 57 KB Download
PDF
Revised Capital Programme 2025/26Appendix 4 157 KB Download
PDF
Future ActivityAppendix 5 58 KB Download
PDF
Capital Monitoring Quarter 1 2025/26Report 164 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

20 of 20 attended
PB
Councillor Paula BasnettChair, present
JM
Councillor Julie McManusVice-Chair, apologies, sent representative
JG
Councillor Jeff GreenSpokesperson, present
EL
Councillor Ed LambSpokesperson, present
PG
Councillor Phil GilchristSpokesperson, present
KH
Councillor Kathy HodsonSpokesperson, present
SB
Councillor Stephen BennettCommittee Member, present
GC
Councillor Graeme CooperCommittee Member, present
AD
Councillor Angela DaviesCommittee Member, present
EG
Councillor Elizabeth GreyCommittee Member, present
PM
Councillor Paul MartinCommittee Member, present
MS
Councillor Mark SkillicornCommittee Member, present

All 20 on the meeting page

On this subject at Wirral

Search all
  1. Capital Monitoring Quarter 1 2025/26This decision
  2. Capital Monitoring Quarter 1 (2026/27)Approved
  3. Capital Monitoring Quarter 3 2025/26Approved
  4. Capital Monitoring Quarter 3 2025/26Approved
  5. 2025-26 capital monitoring quarter 2Approved
  6. 2025-26 Capital Monitoring Quarter 2Approved

More from Wirral Policy and Resources Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 New Wirral PlanResolved – That the Policy and Resources Committee endorsed the new Wirral Plan for 2027 to 2031 and recommended it f... Approved Open
22 Jul 2026 Strategic Land Disposals for Affordable HousingResolved – that 1. the disposal of Council-owned land through a Strategic Housing Partnership, under the Wirral Affor... Approved Open
22 Jul 2026 Network Strategic Partner for Wide Area Network delivery and supportDecision affecting all wards. Resolved – That Policy and Resources Committee authorises the award of a contract to Th... Decided Open
22 Jul 2026 Transport for the City Region Resource FundingResolved – that, 1. the request that had been submitted to the Liverpool City Region to support the delivery of the T... Noted Open
22 Jul 2026 Parking Strategy RefreshResolved – that the Policy & Resources Committee, 1. Notes the resolution of the Environment, Climate Change and Tran... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies