Management Action Plan: Contract Governance Review Birkenhead Town Centre Movement Scheme
ApprovedFinance2 papers
AI summaryWirral's Audit and Risk Management Committee approved a Management Action Plan responding to a contract governance review of the Birkenhead Town Centre Movement Scheme, with costs met from current resources. The committee expressed regret and pledged to keep holding officers to account.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedManagement Action Plan in Appendix 1 approved
MoneyMet from current resourcesNo new funding; training and structural changes from existing budgets
What happens nextFuture committee updatesRegular reports on action plan delivery
Who it affectsCouncil officers and membersStrengthened accountability for town centre scheme
What was decided
The committee approved the Management Action Plan set out in Appendix 1 of the report. Report P32
A further update on the action plan will be provided to members at future meetings. Report 8.3
The committee expressed regret at the issues arising from the Birkenhead Town Centre Movement Scheme and will continue to hold officers to account.
Why
Internal Audit assessed the organisational risk rating as Major in respect of the contract governance review. Report 7.1
The action plan mitigates delivery, financial and governance risks through stronger design assurance, enhanced cost control, transparent committee reporting and increased project management capacity. Report 7.1
Failing to act would leave the council exposed to continuing or escalating financial, governance, legal, operational, strategic and cultural risks. Report 7.2, P15, P16, P17, P18, P19, P20
What happens next
Progress will be kept under regular review and reported through the Power BI reporting framework to departmental management teams and the Senior Leadership Team. Report 8.2
The Audit and Risk Management Committee will receive regular updates on delivery and implementation of the recommendations. Report 8.3
Costs associated with the project will continue to be reported through routine Capital Monitoring to the Policy and Resources Committee. Report 4.2
Implications
Risk: Internal Audit rated the organisational risk as Major before mitigations are applied. Report 7.1
Financial: Risk of budget overspends, emergency funding requests and reduced capacity to deliver corporate priorities if actions are not implemented. Report P15
Legal: Potential breaches of Contract Procedure Rules or procurement regulations, leading to legal challenge or reputational harm. Report P17
Risk: Operational risk of delayed capital projects and further disruption to town centre regeneration timelines. Report P18
Risk: Strategic risk of erosion of public, funder and partner confidence and reduced access to external grant funding. Report P19
Staffing: Cultural risk of staff disengagement, increased turnover and inability to embed a unified council-wide approach. Report P20
Legal: The Accounts and Audit Regulations require the council to undertake effective internal audit of risk management, control and governance. Report 5.1, 5.2, P5, P6, P7
Who and where
Council officers in Regeneration and Highways Report P16
Members and senior officers with oversight of capital projects Report P16
Town centre residents and businesses affected by regeneration timelines Report P18
External funders and partners of the Birkenhead Town Centre Movement Scheme Report P19
Timeline
7 June 2022: Officer Decision Notice: Appointment of Design Consultants for Birkenhead Town Centre Movement Projects Report P33
26 January 2023: Economy, Regeneration and Housing Committee: Utilisation of Procure Partnership Framework Report P34, P46
24 July 2023: Officer Decision Notice: Birkenhead Town Centre Movement Schemes Report P36
22 January 2024: Economy, Regeneration and Housing Committee: Utilisation of Procure Partnerships Framework Report P35, P47
7 March 2024: Officer Decision Notice: Acceptance of Tender and Contract Award Report P37
12 March 2025: Economy, Regeneration and Housing Committee: Simplification Pathfinder Pilot Programme Review Report P38, P48
26 June 2025: Policy and Resources Committee: 2024-25 Capital Outturn Report Report P39, P49
21 July 2025: Council: 2024-25 Capital Outturn Report Report P40, P50
2 September 2025: Audit and Risk Management Committee: Contract Governance Review Report P40, P51
10 September 2025: Policy and Resources Committee: Central Birkenhead Programme Report P41, P52
15 September 2025: Economy, Regeneration and Housing Committee: Birkenhead Central Works Update Report P42, P53
4 November 2025: Audit and Risk Management Committee: Management Action Plan considered and approved
Plain English for the jargon
Power BI: A Microsoft business intelligence tool used to report progress against the action plan.
Procure Partnerships Framework: A framework used by the council to procure services for the Birkenhead Waterfront Programme and movement projects.
Capital Monitoring: The routine process by which the Policy and Resources Committee tracks spending on capital projects.
Design assurance: Checks that project designs are complete and adequate before construction, intended to reduce cost overruns.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item27
Resolved
Resolved – That 1. the Management Action Plan as set out in Appendix 1 of the report be approved; 2. a further update on the action plan be provided to Members at future meetings, as set out in paragraph 8.3 of the report; and 3. the Committee regrets the issues arising from the Birkenhead Town Centre Movement Scheme and will continue to hold officers to account.
Word for word from the decision Wirral published for this meeting.Source: democracy.wirral.gov.uk
4.1Revenue costs in respect of training and staff structural changes emanating from the Management Action Plan will be managed via current resources.
4.2As part of the routine Capital Monitoring process undertaken by the Policy & Resources Committee, costs associated with the project will continue to be reported on, with approval sought for necessary budget amendments, including any compensatory amendments to other capital works in order to mitigate the financial impact on the Council.
Legal implications
5.1Paragraph 5(1) of the Accounts and Audit Regulations required the Council to “undertake an effective internal audit to evaluate the effectiveness of its risk management, control, and governance processes, taking into account public sector internal auditing standards or guidance.”
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Annual governance statement 2025/26Resolved – That the draft Annual Governance Statement for 2025/26, including the actions planned in 2026/27 to addres...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.