RESOLVED That the report be noted and that Risk Management processes remain sound and that work is ongoing to update Business Continuity arrangements within the Council. Reason: The continuous development of the Council’s Risk Management Strategy and Business Continuity Management Plan is essential to ensure the security of services to citizens.
Word for word from the decision Woking published for this meeting.Source: moderngov.woking.gov.uk
Risk Management and Business Continuity Management are the two main disciplines through which the Council identifies, manages and mitigates its business and operational risks. An annual report is submitted to the Executive to outline any activities or issues that have occurred.
Risk Management is the process whereby the organisation methodically identifies and manages the threats and opportunities that might exist within a Council activity. Business Continuity sets out to enhance the strategic and tactical capability of the organisation to plan for incidents and business disruptions in order to continue operations at an acceptable pre-defined level.
Service plan risks have been updated since the last annual report. Corporate strategic risks have also been reviewed and updated by CMG. The risks that have been identified have been logged, owners have been allocated, and progress to mitigate each risk has been recorded.
The Council adopted a Business Continuity Management Strategy in 2006 and it has been in place ever since. The last report to the Executive outlined the need for a review of the existing strategy to ensure that it remains fit for purpose. Work to review and update Business Continuity arrangements is now well advanced.
The focus of work for the last 6 months has been on implementing an Alternative Premises Plan. It has long been an ambition of the Council to have alternative premises to relocate to, should the Civic Offices be destroyed or inaccessible for any reason. Alternative premises, with full access to ICT, will provide robust resilience for the Council and further bolster our Business Continuity and Emergency Planning capabilities. After analysis of possible options, it was determined that the Leisure Centre would be the most appropriate location to serve as backup premises. Work to install the necessary equipment to ensure that the Leisure Centre is in a permanent state of readiness is almost complete, with testing and sign-off due to be finalised imminently.
Recommendations
The Executive is requested to:
RESOLVE That
the report be noted and that Risk Management processes remain sound and that work is ongoing to update Business Continuity arrangements within the Council.
Reasons for decision
Reason: The continuous development of the Council’s Risk Management Strategy and Business Continuity Management Plan is essential to ensure the security of services to citizens.
The Executive has the authority to determine the recommendation(s) set out above. Risk Management and Business Continuity Annual Report
Date Published: 20 June 2018 Risk Management and Business Continuity Annual Report
1.0Introduction
1.1The purpose of this report is to provide Members with an update on Risk and Business Continuity Management arrangements that are in place within the Council. The status of both of these functions is reported on an annual basis.
1.2The Risk Management and Business Continuity Strategies provide the framework, through which the Council identifies, manages and mitigates its business and operational risks. The key elements of this framework are designed to:
ensure that Risk Management and the adoption of Business Continuity becomes part of the culture of the whole organisation; manage risk in accordance with best practice; prevent injury and damage and reduce the cost of risk; consider legal compliance as a minimum standard; and anticipate and respond to changing social, economic, environmental and legislative requirements.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra...
Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.