Risk Management and Business Continuity Annual Report EXE26-031
NotedExecutive2 papers
AI summaryWoking Executive notes 2025/26 risk management and business continuity progress, endorses continued review, with an internal audit due in summer 2026.
Written from the decision and the officer reportPDF Pro
OutcomeNotedNo new spending or policy change
MoneyNot stated
What happens nextInternal audit in summer 2026Plus continued quarterly CLT oversight
Who it affectsWhole council and residentsSupports resilience of all critical services
What was decided
The Executive noted the Risk Management and Business Continuity Annual Report and the progress made in 2025/26. Report P9
Members endorsed the continued review and improvement of the arrangements through existing governance and monitoring. Report P10
Why
Ongoing development is needed so the Council can manage its risks, keep critical services running during disruption, and support informed decisions. Report 3.2
Officers judged that doing nothing was not workable, as it would weaken oversight, reduce preparedness and increase exposure to unmanaged risk. Report 6.1, 6.2
What happens next
An internal audit in summer 2026 will provide independent assurance on business continuity. Report 9.3
CLT will keep reviewing both risk management and business continuity each quarter, and the Risk Management Policy is being updated. Report 5.3, 9.2, P37
A rolling testing programme of business continuity Action Cards is being introduced for all 20 critical functions. Report P55, P56, P57
Options considered
Chosen: Continue to improve the risk and business continuity framework. Needed to maintain oversight, preparedness and resilience, and to align with best practice. Report 6.1, 6.2
Rejected: Do nothing. Would weaken oversight, reduce preparedness and increase exposure to unmanaged risk. Report 6.1
Implications
Legal: No direct legal implications, though the arrangements support compliance with duties including business continuity requirements. Report 11.1
Financial: No new costs; strong arrangements help reduce avoidable financial loss and service disruption. Report 11.2, 11.3
Risk: No new risks created; report summarises how existing risks are managed. No strategic risks are currently at the highest level, compared with three in 2024/25, though company divestment and statutory housing compliance remain above appetite. Report 7.3, 7.5, 11.6, 11.7
Equalities: No direct equality impacts, though the arrangements support resilience for services used by residents including vulnerable groups. Report 11.8, 11.9, 11.10
Climate: No direct environmental or climate implications; severe weather is covered by wider risk and continuity planning. Report 11.14, 11.15
Staffing: Delivered through existing corporate and service management arrangements, with no additional resources required. Report 11.4, 11.5
Who and where
The Council as a whole, through corporate-wide governance and service resilience Report 10.3
Residents, including vulnerable groups, who rely on the Council's critical services Report 8.1, 11.9
Timeline
2025/26: Period covered by the annual report; risk framework, risk appetite statements, Strategic Risk Register and all 20 business continuity Action Cards were refreshed. Report 1.2, 7.1, P54, P55, P56
Summer 2026: Internal audit of business continuity arrangements is planned to give independent assurance. Report 9.3
Each quarter: CLT reviews risk management and business continuity. Report 5.3, 9.2
Plain English for the jargon
CLT: Corporate Leadership Team, which has overall oversight of risk and business continuity and reviews them each quarter.
Action Card: A document for each critical function setting out key contacts, dependencies, alternative arrangements and priority activities during an incident.
LGR: Local Government Reorganisation, treated in the Strategic Risk Register as a specific risk.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17
Resolved
The Executive Resolved That (i) the Risk Management and Business Continuity Annual Report, and the progress made over 2025/26 in embedding effective risk management and business continuity arrangements, be noted; and (ii) the continued review and improvement of the arrangements in line with agreed governance and monitoring processes be endorsed. Reason: Continuous development of risk management and business continuity is essential to ensure the Council can manage its risks effectively, maintain critical services during disruptions, and support informed decision-making and resilience in delivering Council objectives.
Word for word from the decision Woking published for this meeting.Source: moderngov.woking.gov.uk
1.1This report provides the Executive with assurance on the Council’s risk management and business continuity arrangements in 2025/26.
1.2During the year the Council strengthened its risk framework, introduced updated risk appetite statements and scoring guidance, refreshed the Strategic Risk Register, reviewed and updated the business continuity management arrangements, updated all 20 critical business continuity action cards, and strengthened governance through quarterly CLT review.
1.3No strategic risks are currently rated at the highest level, although some remain above appetite and continue to require close management.
Purpose of report
2.1The purpose of this report is to provide the Executive with assurance on the effectiveness and development of the Council’s risk management and business continuity arrangements during 2025/26.
2.2It sets out the main improvements made over the year, the current level of assurance, and the next steps planned to strengthen these arrangements further.
EXE26-031 Risk Management and Business Continuity Annual Report
Recommendations
3.1The Executive is requested to:
Resolve That
(i) The Risk Management and Business Continuity Annual Report, and the progress made over 2025/26 in embedding effective risk management and business continuity arrangements, be noted; and
(ii) The continued review and improvement of the arrangements in line with agreed governance and monitoring processes be endorsed.
Reason for decision
3.2Continuous development of risk management and business continuity is essential to ensure the Council can manage its risks effectively, maintain critical services during disruptions, and support informed decision-making and resilience in delivering Council objectives.
4.0Proposal and Outcome
4.1During 2025/26 the Council maintained and strengthened its risk management and business continuity arrangements to improve oversight, accountability and organisational resilience to:
i. Support clearer identification and management of strategic and operational risk within the Council’s agreed risk appetite.
ii. Maintain up-to-date continuity plans and a proportionate testing programme for critical services.
4.2These improvements provide stronger assurance through clearer risk reporting, more consistent governance and up-to-date continuity planning. This is evidenced by:
i. A more mature risk framework, including refreshed risk appetite statements and an improved register format.
ii. Reduction or mitigation of some significant risk exposures during the year.
iii. Current continuity plans for all 20 critical functions.
iv. Regular CLT review.
Background
5.1Risk management and business continuity are core elements of good governance and service resilience.
i. Risk management supports informed decisions by identifying, assessing and controlling uncertainty. Risk Management and Business Continuity Annual Report
ii. Business continuity helps the Council maintain critical services during disruption.
5.2Both require regular review and are overseen corporately to ensure they remain aligned to the Council’s operating environment and priorities.
5.3CLT has overall oversight and reviews both areas quarterly.
5.4This governance cycle has supported improvements during 2025/26, see below.
Options considered
6.1Maintaining robust risk management and business continuity arrangements is essential to resilient Council operations. A do-nothing approach is not considered viable because it would weaken oversight, reduce preparedness and increase exposure to unmanaged risk.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra...
Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.