Lakeview Estate Refurbishment Scheme and Housing Fire Safety Remedial Works Procurement EXE26-029
NotedExecutive1 paper
AI summaryWoking Executive awards 24-month fire safety contracts to Amber and Mulalley via the SEC Framework, and notes Lakeview Estate refurbishment progress with main contract award expected June 2026.
Written from the decision and the officer reportPDF Pro
OutcomeNotedAmber and Mulalley get new 24-month contracts
MoneyNot statedNo contract values given in the papers
What happens nextLakeview main contract to ExecutiveExpected June 2026, site start late July/early August
Who it affectsLakeview Estate and 170 blocks borough-wideTenants, leaseholders, new West Surrey authority
What was decided
The Executive noted the procurement status and programme update for the Lakeview Estate Refurbishment Scheme. Report P10
New 24-month contracts will be awarded to Amber Construction Services and Mulalley and Company Limited by Direct Award under the South East Consortium (SEC) Framework. Report P11, 1.3, 7.5
The Head of Housing Assets, with the Strategic Director for People and Communities and the Housing Portfolio Holder, is authorised to finalise and implement the appointments, subject to Legal and Finance sign-off. Report P12
Why
After a self-referral to the Regulator of Social Housing in December 2023, the Council must close outstanding fire safety actions; one contractor is withdrawing and the other two contracts expire on 19 July 2026. Report 1.1, 5.1, 5.2, 7.2, 7.3
Officers say a Direct Award under the SEC Framework is the most proportionate and legally robust way to maintain continuity, avoid programme slippage and discharge statutory landlord duties. Report 7.4, 7.5, 1.4
What happens next
Formal tender returns for the Lakeview main contract are due 30 March 2026, with a preferred contractor expected by early May 2026 and an Executive award decision in June 2026. Report 6.5, 6.7
A Section 20 consultation of 30 days will run for Lakeview before contract award, and six pre-commencement planning and Building Control conditions must be discharged before site start in late July/early August 2026. Report 6.6, 6.8, 6.9
Current FRA remedial actions are expected to be completed by December 2026, with the 24-month contract length allowing for slippage and any new actions from the 2026 round of FRAs. Report 7.6
Options considered
Chosen: Award new contracts to Amber and Mulalley via SEC Framework Direct Award. Maintains continuity and momentum on a live safety-critical programme; SEC allows direct award. Report 7.4, 7.5, 8.1
Rejected: Let the current contracts expire. Inability to complete works and residual health and safety risks. Report P46
Rejected: Run a full procurement exercise for new contractors. Would harm programme delivery, resident safety, quality of works and regulatory compliance. Report P47
Implications
Legal: Procurement is run under the Procurement Act 2023 using the SEC Framework, compliant with the Council's Contract Standing Orders. Works are needed to meet duties under the Building Safety Act 2022. Report 10.1, 10.2, 10.3
Financial: Fire safety works are a priority in the 30-Year HRA Business Plan, and the 2026/27 Housing Asset Management Plan budget includes capital for FRA works and to commence Lakeview, which spans future years. Report 10.4
Risk: Key risks include temporary safety measures failing, programme interruption if contracts lapse, reduced contractor capacity, additional defects inflating cost, and resident disruption during works; mitigations include phased delivery, direct awards, governance and engagement. Report 10.5, 10.6, 10.7, 10.8, 10.9, 10.10
Equalities: Extensive resident and stakeholder engagement has taken place, with formal Section 20 consultation in progress for Lakeview. Report 10.11, P66
Climate: The Lakeview refurbishment is expected to improve energy efficiency, reduce carbon emissions and extend the life of existing housing stock, aligning with the Council's climate objectives. Report 10.12, P68
Other: Works are expected to continue beyond Woking Borough Council's life under Local Government Reorganisation; the new West Surrey authority will need to show the same regulatory compliance. Report 10.13, 10.14, P70
Who and where
Tenants and leaseholders on the Lakeview Estate (14 blocks undergoing major refurbishment) Report 6.1, 6.6, 10.10
Residents across 170 apartment blocks in the borough covered by the FRA remediation programme Report 9.2
The Regulator of Social Housing, to whom the Council must demonstrate compliance Report 1.1, 1.4, 5.2
The incoming West Surrey authority under Local Government Reorganisation Report 10.13, 10.14
Timeline
December 2023: Council received regulatory notice from the Regulator of Social Housing on fire safety remedial actions. Report 1.1, 5.1
2024: Combustible cladding was removed from 14 Lakeview blocks and temporary covering installed; contracts extended to additional contractors Amber and Mulalley. Report 1.2, 6.1, 7.1
November 2025: Executive resolved to procure a single Principal Contractor for Lakeview via the LCP MW24-H Framework (Lot 2.3). Report 6.2
December 2025: Local Planning Authority resolved to grant planning permission for Lakeview (PLAN/2025/0682), subject to a legal agreement. Report 6.3
31 December 2025: Outstanding fire safety remedial actions reduced from over 3,700 to 1,358, including new actions from the 2025 FRAs. Report 1.1, 5.1
26 February 2026: Formal invitations to tender for the Lakeview main contract were issued. Report 6.5
12 March 2026: Executive approved Direct Award contracts to Amber and Mulalley under the SEC Framework. Report P11
30 March 2026: Tender returns for the Lakeview main contract are due. Report 6.5
early May 2026: Preferred Lakeview contractor expected to be selected following evaluation and due diligence. Report 6.5
June 2026: Lakeview contract award decision expected to be presented to the Executive, after tender evaluation and Section 20 consultation. Report 6.6, 6.7
19 July 2026: Current FRA works contracts with Amber and Mulalley expire. Report 5.2, 7.3
late July/early August 2026: Current programme assumes start on site for the Lakeview refurbishment, subject to pre-commencement conditions. Report 6.9
December 2026: Current FRA remedial actions expected to be completed, subject to the 24-month contract length for contingency. Report 7.6
Plain English for the jargon
FRA: Fire Risk Assessment, the formal review that identifies required remedial actions on housing blocks.
SEC Framework: South East Consortium Framework, a procurement framework used by the Council; it allows direct award of call-off contracts to named suppliers.
Direct Award: Awarding a contract to a supplier on a framework without running a competitive tender, permitted here for continuity of service.
LCP MW24-H Framework: London Construction Programme Housing Major Works framework (Lot 2.3), being used to procure the Lakeview Principal Contractor.
Section 20 consultation: A statutory consultation process with leaseholders required before qualifying works are recharged to them.
LGR: Local Government Reorganisation, the restructuring of councils that will create a new West Surrey authority succeeding Woking Borough Council.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
The Executive Resolved That (i) the procurement status and programme update for the Lakeview Estate Refurbishment Scheme be noted; (ii) new contracts be awarded to Amber Construction Services (Amber) and Mulalley and Company Limited (Mulalley) to continue to deliver the ongoing fire safety remediation works programme through a Direct Award using the South East Consortium (SEC) Framework; and (iii) the Head of Housing Assets, in consultation with the Strategic Director – People and Communities and Portfolio Holder for Housing, be authorised to finalise and implement the above appointments and extensions, subject to Legal and Finance sign?off. Reason: To avoid disruption and delay to the Council’s fire safety remediation programme and maintain the Council’s ability to discharge its statutory landlord responsibilities.
Word for word from the decision Woking published for this meeting.Source: moderngov.woking.gov.uk
1.1Following a self-referral to the Regulator of Social Housing, Woking Borough Council received a regulatory notice in December 2023 relating to the number of fire safety remedial actions outstanding. As part of its Housing Improvement Programme, significant effort and works have been undertaken to reduce these from over 3,700 to 1,358 as at 31 December 2025 (inclusive of additional actions identified in the 2025 round of Fire Risk Assessments (FRAs)).
1.2One of the high-risk actions was to remove combustible cladding from 14 blocks at the Lakeview Estate. A temporary external covering and insulation system was installed to maintain weatherproofing and warmth. This report updates the Executive on the procurement status and programme for the permanent solution at Lakeview.
1.3Furthermore, the report seeks approval for a number of time‑critical contract awards required to maintain continuity, momentum and delivery of the Council’s wider Fire Risk Assessment (FRA) remediation programme. Specifically, the report seeks approval to award new contracts to two contractors, known as Amber Construction Services (Amber) and Mulalley and Company Limited (Mulalley) for a further 24 months to allow for contingency.
1.4These approvals are required to avoid loss of programme momentum, mitigate continuity and capacity risks on live safety‑critical programmes, and ensure the Council can demonstrate to the Regulator of Social Housing and residents that it is meeting its statutory duties as a landlord.
EXE26-029 Lakeview Estate Refurbishment Scheme and Housing Fire Safety Remedial Works Procurement
Purpose of report
2.1The purpose of this report is to secure continuity of contractor capacity across the fire safety remediation programme to allow the Council to close FRA actions at pace. In addition, this report seeks to provide an update specifically on the Lakeview Estate Refurbishment Scheme procurement process and programme.
2.2The decisions sought are necessary at this stage due to slippage in the current programme, reduced contractor numbers and the approaching expiry of existing works contracts.
Recommendations
3.1The Executive is requested to:
Resolve That
(i) The procurement status and programme update for the Lakeview Estate Refurbishment Scheme be noted;
(ii) New contracts be awarded to Amber Construction Services (Amber) and Mulalley and Company Limited (Mulalley) to continue to deliver the ongoing fire safety remediation works programme through a Direct Award using the South East Consortium (SEC) Framework; and
(iii) The Head of Housing Assets, in consultation with the Strategic Director – People and Communities and Portfolio Holder for Housing, be authorised to finalise and implement the above appointments and extensions, subject to Legal and Finance sign‑off.
Reason(s) for Decision
3.2To avoid disruption and delay to the Council’s fire safety remediation programme and maintain the Council’s ability to discharge its statutory landlord responsibilities.
4.0Proposal and Outcome
4.1The report seeks approval for a number of time‑critical contract awards required to maintain continuity, momentum and delivery of the Council’s wider Fire Risk Assessment (FRA) remediation programme. It also seeks to update the Executive on the procurement status and programme for the refurbishment of 14 blocks on the Lakeview Estate following partial cladding removal in 2024.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra...
Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.