Resolved
The Executive Resolved That ( i ) the report be received; and (ii) the project monitoring at Appendix 1 to the report be noted. Reason: To apply performance management to Council projects.
AI summaryWoking Borough Council Executive noted the quarterly Project Monitoring Report covering 17 live projects, with 10 rated green, 4 amber and 3 red, and no financial exceptions to report.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
The Executive Resolved That ( i ) the report be received; and (ii) the project monitoring at Appendix 1 to the report be noted. Reason: To apply performance management to Council projects.
1.1The Executive receives regular reports on the progress of the Council’s key projects, so that it can review the status of these and consider any action that may be necessary to secure their delivery. A monitoring report detailing the status of every Council project (as at the end of October 2025), incorporating both capital and revenue projects, is attached at Appendix 1. The monitoring report provides a status update, and an assessment against project risks, issues, schedule, and budget.
1.2There are no specific areas for concern or action required by the Executive as a result of this latest review.
2.1The Executive is requested to:
Resolve That
(i) The report be received; and
(ii) The project monitoring at Appendix 1 to the report be noted.
Reason(s) for Decision
2.2To apply performance management to Council projects.
EXE25-041 Project Monitoring Report
3.0Proposal and Outcome
3.1The Executive is asked to review Appendix 1 and note the current status of the Council’s projects. Projects are subject to ongoing monitoring to provide assurance that they are delivered in line with expectations and to ensure that stated benefits are realised.
4.1The undertaking of projects is an integral part of Woking Borough Council (WBC) business delivery, and significant resources are allocated to their successful completion. Project management processes have been developed to bring consistency to how projects are managed, and to aid the project manager in delivering projects on time, to budget, and to the desired standard.
4.2The process has been structured to be flexible so it can meet the specific needs of the Council. It is designed to add value to officers who are leading on projects and provide a common standard against which all projects can be assessed. Every project, regardless of size or type, is required to follow the corporate process.
4.3All Council projects are formally reviewed by CLT via the Corporate Programme Board (CPB) which meets quarterly. The CPB provides a forum where project risks, issues, and other areas of concern are discussed; this approach facilitates clear and accountable decision-making.
5.0Activity in the reporting period
5.1Since the last report to the Executive:
• The Project Support Office has met with every project manager to discuss project progress, assess performance, and assign RAG ratings. • A detailed update for each project has been produced (Appendix 1) and presented to CLT as part of the quarterly CPB meeting. • Key points to note from the monitoring report are:
o There are 17 projects classified as live or at practical completion, of which: o 59% (10) projects are green. o 24% (4) projects are amber. o 17% (3) projects are red.
• There are 5 projects that have been closed in the period. Projects that have been closed during the period are not RAG rated as this rating relates to projects in delivery.
6.0Financial Exception Items
6.1In accordance with Financial Regulations, projects will be highlighted where actual spend exceeds the approved budget by the greater of £10k or 5%. There are no project(s) that fall into this category for this reporting period. Project Monitoring Report
7.0Items of Note
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
EXE25-041 Appendix 1: Project Monitoring with spend to the end of October 2025Appendix | 223 KB | Download |
PDF |
Project Monitoring Report EXE25-041Report | 118 KB | DownloadRead as text |
Follow Executive at Woking and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Foundation Strategic Authority (FSA) EXE26-093The Executive Resolved That (i) the current position regarding the proposed establishment of a Foundation Strategic A... | Noted | Open |
| 16 Sep 2026 | Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra... | Approved | Open |
| 16 Sep 2026 | Lakeview Estate Refurbishment Scheme EXE26-057The Executive Resolved That ( i ) the contract for the Lakeview Estate Refurbishment Project works be awarded to the ... | Decided | Open |
| 16 Sep 2026 | Revenue Refunds, Credit Balances and Write-Back Policy EXE26-101The Executive Resolved That (i) the Revenue Refunds, Credit Balances and Write-Back Policy be approved; (ii) the Head... | Approved | Open |
| 16 Sep 2026 | Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.