Project Monitoring Report EXE25-041

Noted Executive 2 papers

AI summaryWoking Borough Council Executive noted the quarterly Project Monitoring Report covering 17 live projects, with 10 rated green, 4 amber and 3 red, and no financial exceptions to report.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQuarterly project monitoring report noted by Executive
MoneyNo financial exceptionsNo projects over budget threshold this period
What happens nextNext quarterly monitoring reportOngoing quarterly cycle via Corporate Programme Board
Who it affectsCouncil projects and residents17 live or near-complete Council projects reviewed

What was decided

The Executive received the project monitoring report and noted the project status update at Appendix 1. Report P5, P6

The decision was made to apply ongoing performance management to Council projects, with no further action required at this time. Report P7, 2.2, 1.2

Why

The Executive receives regular reports on the progress of the Council's key projects so it can review their status and consider any necessary action. Report 1.1, 3.1

Strong and effective project monitoring is considered essential to ensure Council resources are used effectively and to capture lessons for continuous improvement. Report 8.1

What happens next

The Project Support Office will continue to meet every project manager to discuss progress, assess performance and assign RAG ratings each quarter. Report 5.1, P17

Outstanding Sheerwater highways and landscaping works are expected to run until July 2026, and a further one-year hoarding licence for the Triangle site will need to be applied for in April 2026. Report 7.1, 7.2

The Improvement and Recovery Programme will continue to focus on digital transformation, organisational development, tax issues, Member engagement and preparing for divestment proposals and unitarisation. Report 7.3

The money

  • greater of £10k or 5% Threshold above which budget overruns are highlighted as financial exceptions Report 6.1

Options considered

  • Chosen: Apply robust quarterly project monitoring. Considered essential to ensure Council resources are used effectively and to support continuous improvement. Report 8.1
  • Rejected: Not applying robust monitoring. Not considered a viable alternative. Report 8.1

Implications

  • Risk: Project risk is discussed with each project manager quarterly and assigned a RAG status reviewed by CLT at the Corporate Programme Board, with mitigation measures applied as necessary. Report 11.5, P40
  • Legal: There are no specific legal implications arising from this report. Report 11.1, P34
  • Financial: Project monitoring is undertaken within existing staff resources; each project has its own funding sources and project management arrangements. Report 11.3, 11.2
  • Equalities: An Equality Impact Assessment must be completed for every project as part of the initiation process and is reviewed and authorised by CLT. Report 11.6, P42
  • Climate: A Sustainability Appraisal must be completed for every project as part of the initiation process and is reviewed and authorised by CLT. Report 11.8, P45
  • Other: The ongoing monitoring of projects will have no bearing on Local Government Reorganisation. Report 11.9, P47

Who and where

  • Woking Borough Council project managers and officers delivering the 17 live or near-complete projects Report P18, 5.1
  • The Corporate Leadership Team, which formally reviews all Council projects quarterly via the Corporate Programme Board Report 4.3
  • Residents and stakeholders of major development schemes including Sheerwater, Victoria Place and the Triangle site Report 7.1, 7.2, 7.4
  • Homes England, as joint decision-maker on closure of the Housing Infrastructure Fund project Report 7.2
  • ThamesWey, as exiting development partner on Sheerwater remaining phases Report 7.1

Timeline

  • May 2022: The Marches residential (build to rent) at Victoria Place opened Report 7.4
  • 2023-10-05: Earlier Executive decision to close the Housing Infrastructure Fund project Report 7.2
  • 2024-10-31: Hilton Hotel at Victoria Place opened Report 7.4
  • December 2024: Deed of Termination between Homes England and WBC signed to close the Housing Infrastructure Fund project Report 7.2
  • end of October 2025: Cut-off date for project status information in the report Report 1.1
  • April 2026: Further one-year hoarding licence for the Triangle site to be applied for Report 7.2
  • July 2026: Outstanding Sheerwater highways and landscaping works expected to complete Report 7.1
  • Spring 2022: Retail and leisure elements of the Victoria Place development opened Report 7.4

Plain English for the jargon

  • RAG rating: Red, Amber, Green status used to flag project risk and performance.
  • Corporate Programme Board (CPB): Quarterly forum of the Corporate Leadership Team that formally reviews all Council projects.
  • CLT: Corporate Leadership Team of Woking Borough Council.
  • IRP: Improvement and Recovery Programme, covering financial recovery, governance, organisational redesign and housing.
  • LGR: Local Government Reorganisation, the move to unitarisation referenced in the report.
  • ThamesWey: Development partner on the Sheerwater Regeneration whose Development Agreement is being brought to an end after current phases.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

The Executive Resolved That ( i ) the report be received; and (ii) the project monitoring at Appendix 1 to the report be noted. Reason: To apply performance management to Council projects.
Word for word from the decision Woking published for this meeting. Source: moderngov.woking.gov.uk

Follow this further

Built from Woking's papers

What the report saysPro

Report to Executive

Purpose of report

1.1The Executive receives regular reports on the progress of the Council’s key projects, so that it can review the status of these and consider any action that may be necessary to secure their delivery. A monitoring report detailing the status of every Council project (as at the end of October 2025), incorporating both capital and revenue projects, is attached at Appendix 1. The monitoring report provides a status update, and an assessment against project risks, issues, schedule, and budget.

1.2There are no specific areas for concern or action required by the Executive as a result of this latest review.

Recommendations

2.1The Executive is requested to:

Resolve That

(i) The report be received; and

(ii) The project monitoring at Appendix 1 to the report be noted.

Reason(s) for Decision

2.2To apply performance management to Council projects.

EXE25-041 Project Monitoring Report

3.0Proposal and Outcome

3.1The Executive is asked to review Appendix 1 and note the current status of the Council’s projects. Projects are subject to ongoing monitoring to provide assurance that they are delivered in line with expectations and to ensure that stated benefits are realised.

Background

4.1The undertaking of projects is an integral part of Woking Borough Council (WBC) business delivery, and significant resources are allocated to their successful completion. Project management processes have been developed to bring consistency to how projects are managed, and to aid the project manager in delivering projects on time, to budget, and to the desired standard.

4.2The process has been structured to be flexible so it can meet the specific needs of the Council. It is designed to add value to officers who are leading on projects and provide a common standard against which all projects can be assessed. Every project, regardless of size or type, is required to follow the corporate process.

4.3All Council projects are formally reviewed by CLT via the Corporate Programme Board (CPB) which meets quarterly. The CPB provides a forum where project risks, issues, and other areas of concern are discussed; this approach facilitates clear and accountable decision-making.

5.0Activity in the reporting period

5.1Since the last report to the Executive:

• The Project Support Office has met with every project manager to discuss project progress, assess performance, and assign RAG ratings. • A detailed update for each project has been produced (Appendix 1) and presented to CLT as part of the quarterly CPB meeting. • Key points to note from the monitoring report are:

o There are 17 projects classified as live or at practical completion, of which: o 59% (10) projects are green. o 24% (4) projects are amber. o 17% (3) projects are red.

• There are 5 projects that have been closed in the period. Projects that have been closed during the period are not RAG rated as this rating relates to projects in delivery.

6.0Financial Exception Items

6.1In accordance with Financial Regulations, projects will be highlighted where actual spend exceeds the approved budget by the greater of £10k or 5%. There are no project(s) that fall into this category for this reporting period. Project Monitoring Report

7.0Items of Note

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EXE25-041 Appendix 1: Project Monitoring with spend to the end of October 2025Appendix 223 KB Download
PDF
Project Monitoring Report EXE25-041Report 118 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 14 attended
AB
Councillor Ann-Marie BarkerChair, present
EN
Councillor Ellen NicholsonVice-Chair, present
SG
Councillor Steve GreentreeCommittee Member, present
IJ
Councillor Ian JohnsonCommittee Member, present
LL
Councillor Liam LyonsCommittee Member, apologies
LM
Councillor Louise MoralesCommittee Member, present
DR
Councillor Dale RobertsCommittee Member, present
RC
Richard CarrOfficer, present
SF
Stephen FitzgeraldOfficer, present
KF
Kevin FosterOfficer, present
BK
Beverley KucharOfficer, present
AO
Adesuwa OmoregieOfficer, present

All 14 on the meeting page

On this subject at Woking

Search all
  1. Project Monitoring Report EXE25-041This decision
  2. Project Monitoring Report EXE26-033Noted
  3. Project Monitoring Report EXE26-005Noted
  4. Project Monitoring Report EXE25-026Noted
  5. Project Monitoring Report EXE25-005Noted
  6. Project Monitoring Report EXE24-066Noted

More from Woking Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Foundation Strategic Authority (FSA) EXE26-093The Executive Resolved That (i) the current position regarding the proposed establishment of a Foundation Strategic A... Noted Open
16 Sep 2026 Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra... Approved Open
16 Sep 2026 Lakeview Estate Refurbishment Scheme EXE26-057The Executive Resolved That ( i ) the contract for the Lakeview Estate Refurbishment Project works be awarded to the ... Decided Open
16 Sep 2026 Revenue Refunds, Credit Balances and Write-Back Policy EXE26-101The Executive Resolved That (i) the Revenue Refunds, Credit Balances and Write-Back Policy be approved; (ii) the Head... Approved Open
16 Sep 2026 Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies