Executive, Thursday 12 March 2026 at 7.30pm

Project Monitoring Report EXE26-005

Noted Executive 2 papers

AI summaryWoking Borough Council Executive notes quarterly project monitoring report, with 13 live or practically complete projects: 11 green, 1 amber, 1 red, as at end of January 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQuarterly project monitoring report, no action required
MoneyNo financial exceptionsNo project exceeded approved budget by £10k or 5%
What happens nextNext quarterly reviewOngoing monitoring by CLT via Corporate Programme Board
Who it affectsCouncil project managers and projectsAll WBC capital and revenue projects

What was decided

The Executive received the Project Monitoring Report covering all Council projects as at the end of January 2026. Report P5, 1.1

The Executive noted the project monitoring information set out in Appendix 1 to the report. Report P6, 3.1

Why

To apply performance management to Council projects and provide assurance they are delivered in line with expectations. Report 2.2, 3.1, 8.1

Monitoring supports the High Performing Council theme of the Woking for All Strategy, with projects reviewed quarterly by CLT via the Corporate Programme Board. Report 4.3, 9.1, 11.4

Officers report there are no specific areas of concern or action required by the Executive from this review. Report 1.2, 7.1

What happens next

The Project Support Office will continue to meet every project manager quarterly to assess progress and assign RAG ratings. Report P17, 5.1, 10.1

Risks and mitigation for any red or amber projects will be discussed at the next Corporate Programme Board meeting. Report 11.4, 4.3

A further monitoring report will be brought to the Executive on the standard quarterly cycle. Report 10.1, 9.1

The money

  • greater of £10k or 5% Threshold above which budget overruns must be reported as financial exceptions Report 6.1

Options considered

  • Chosen: Apply robust quarterly project monitoring as set out in the report. Ensures Council resources are used effectively and supports continuous improvement Report 8.1, P7
  • Rejected: Not apply robust monitoring. Not considered a viable alternative Report 8.1

Implications

  • Financial: No specific financial implications; project monitoring is carried out within existing staff resources and each project has its own funding arrangements. Report 11.2, 11.3, 6.1
  • Legal: No specific legal implications arising from this report. Report 11.1
  • Equalities: An Equality Impact Assessment must be completed for every project at initiation and is reviewed and authorised by CLT. Report 11.5, 11.6
  • Climate: A Sustainability Appraisal must be completed for every project at initiation and is reviewed and authorised by CLT. Report 11.7
  • Risk: Each project is assigned a RAG rating for risk, reviewed quarterly by CLT at the Corporate Programme Board, where mitigation measures are agreed. Report 11.4, P37
  • Other: The ongoing monitoring of projects will have no bearing on Local Government Reorganisation. Report 11.8

Who and where

  • Officers leading on Council projects, supported by the Project Support Office Report 4.2, P17
  • Corporate Leadership Team and the Corporate Programme Board Report 4.3, 11.4
  • Woking Borough Council residents, as beneficiaries of project delivery Report 4.1, 9.1

Timeline

  • End of January 2026: Status date for the projects covered by the monitoring report Report 1.1
  • Quarterly: Corporate Programme Board reviews all Council projects Report 4.3, 10.1

Plain English for the jargon

  • RAG rating: Red, Amber or Green status used to flag project risk and performance
  • CLT: Corporate Leadership Team of Woking Borough Council
  • CPB: Corporate Programme Board, the quarterly forum that reviews Council projects
  • Woking for All Strategy: The Council's corporate strategy, which includes a High Performing Council theme
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item18

Resolved

The Executive Resolved That (i) the report be received; and (ii) the project monitoring at Appendix 1 to the report be noted. Reason: To apply performance management to Council projects.
Word for word from the decision Woking published for this meeting. Source: moderngov.woking.gov.uk

Follow this further

Built from Woking's papers

What the report saysPro

Report to Executive

Purpose of report

1.1The Executive receives regular reports on the progress of the Council’s key projects, so that it can review the status of these and consider any action that may be necessary to secure their delivery. A monitoring report detailing the status of every Council project (as at the end of January 2026), incorporating both capital and revenue projects, is attached at Appendix 1. The monitoring report provides a status update, and an assessment against project risks, issues, schedule, and budget.

1.2There are no specific areas for concern or action required by the Executive as a result of this latest review.

Recommendations

2.1The Executive is requested to:

Resolve That

(i) The report be received; and

(ii) The project monitoring at Appendix 1 to the report be noted.

Reason(s) for Decision

2.2To apply performance management to Council projects.

EXE26-005 Project Monitoring Report

3.0Proposal and Outcome

3.1The Executive is asked to review Appendix 1 and note the current status of the Council’s projects. Projects are subject to ongoing monitoring to provide assurance that they are delivered in line with expectations and to ensure that stated benefits are realised.

Background

4.1The undertaking of projects is an integral part of Woking Borough Council (WBC) business delivery, and significant resources are allocated to their successful completion. Project management processes have been developed to bring consistency to how projects are managed, and to aid the project manager in delivering projects on time, to budget, and to the desired standard.

4.2The process has been structured to be flexible so it can meet the specific needs of the Council. It is designed to add value to officers who are leading on projects and provide a common standard against which all projects can be assessed. Every project, regardless of size or type, is required to follow the corporate process.

4.3All Council projects are formally reviewed by CLT via the Corporate Programme Board (CPB) which meets quarterly. The CPB provides a forum where project risks, issues, and other areas of concern are discussed; this approach facilitates clear and accountable decision-making.

5.0Activity in the reporting period

5.1Since the last report to the Executive:

• The Project Support Office has met with every project manager to discuss project progress, assess performance, and assign RAG ratings.

• A detailed update for each project has been produced (Appendix 1) and presented to CLT as part of the quarterly CPB meeting.

• Key points to note from the monitoring report are:

o There are 13 projects classified as live or at practical completion, of which: o 84% (11) projects are green. o 8% (1) project is amber. o 8% (1) project is red.

• There are 5 projects that have been closed in the reporting period. Projects that have been closed during the period are not RAG rated as this rating relates to projects in delivery.

6.0Financial Exception Items

6.1In accordance with Financial Regulations, projects will be highlighted where actual spend exceeds the approved budget by the greater of £10k or 5%. There are no project(s) that fall into this category for this reporting period. Project Monitoring Report

7.0Items of Note

7.1None.

Options considered

8.1Strong and effective project monitoring is essential to ensure that Council resources are being used effectively. Project monitoring also enables lessons to be captured on a regular basis which supports continuous improvement. The option of not applying robust monitoring is not considered to be a viable alternative.

9.0Corporate Strategy

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EXE26-005 Appendix 1: Project Monitoring Report for spend to the end of January 2026Appendix 155 KB Download
PDF
Project Monitoring Report EXE26-005Report 114 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 14 attended
AB
Councillor Ann-Marie BarkerChair, present
EN
Councillor Ellen NicholsonVice-Chair, present
SG
Councillor Steve GreentreeCommittee Member, present
IJ
Councillor Ian JohnsonCommittee Member, present
LL
Councillor Liam LyonsCommittee Member, present
LM
Councillor Louise MoralesCommittee Member, present
DR
Councillor Dale RobertsCommittee Member, present
RC
Richard CarrOfficer, present
SF
Stephen FitzgeraldOfficer, present
BK
Beverley KucharOfficer, present
AO
Adesuwa OmoregieOfficer, present
LS
Louise StrongitharmOfficer, present

All 14 on the meeting page

On this subject at Woking

Search all
  1. Project Monitoring Report EXE26-005This decision
  2. Project Monitoring Report EXE26-033Noted
  3. Project Monitoring Report EXE25-041Noted
  4. Project Monitoring Report EXE25-026Noted
  5. Project Monitoring Report EXE25-005Noted
  6. Project Monitoring Report EXE24-066Noted

More from Woking Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Foundation Strategic Authority (FSA) EXE26-093The Executive Resolved That (i) the current position regarding the proposed establishment of a Foundation Strategic A... Noted Open
16 Sep 2026 Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra... Approved Open
16 Sep 2026 Lakeview Estate Refurbishment Scheme EXE26-057The Executive Resolved That ( i ) the contract for the Lakeview Estate Refurbishment Project works be awarded to the ... Decided Open
16 Sep 2026 Revenue Refunds, Credit Balances and Write-Back Policy EXE26-101The Executive Resolved That (i) the Revenue Refunds, Credit Balances and Write-Back Policy be approved; (ii) the Head... Approved Open
16 Sep 2026 Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s... Approved Open