Woking Borough Council
Executive, Thursday 11 June 2026 at 7.00pm

Project Monitoring Report EXE26-033

Noted Executive 2 papers

AI summaryWoking Borough Council Executive noted a project monitoring report covering 11 live projects, with nine rated green, one amber and one red, and no financial exceptions as at the end of April 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted11 projects reviewed, no concerns raised
MoneyNo budget exceptionsNo project exceeded approved budget by £10k or 5%
What happens nextQuarterly monitoring cycleNext review by CLT via Corporate Programme Board
Who it affectsWBC capital and revenue projectsAll Council projects are subject to the process

What was decided

The Executive received the report and noted the project monitoring at Appendix 1, to apply performance management to Council projects. Report P5, P6, 2.2

Why

The Executive regularly reviews the status of key Council projects so it can consider any action needed to secure delivery. Report 1.1

No specific areas of concern or action were identified in the latest review. Report 1.2

Strong project monitoring is needed to use Council resources effectively and to capture lessons for continuous improvement; not applying robust monitoring was not considered a viable alternative. Report 8.1

What happens next

All Council projects will continue to be formally reviewed by CLT via the Corporate Programme Board on a quarterly cycle. Report 4.3, 10.1

Any future budget or schedule issues will be highlighted within the monitoring report, and RAG ratings will be reassessed each quarter with mitigation discussed by CLT. Report 11.2, 11.4

The money

  • £10k or 5% Threshold above which projects with actual spend exceeding approved budget are highlighted as financial exceptions Report 6.1

Options considered

  • Chosen: Note the project monitoring report at Appendix 1. To apply performance management to Council projects Report P6, 2.2, 8.1
  • Rejected: Do not apply robust project monitoring. Not considered a viable alternative because it would not ensure Council resources are used effectively or capture lessons for improvement Report 8.1

Implications

  • Legal: No specific legal implications arising from this report. Report 11.1
  • Financial: Project monitoring is undertaken within existing staff resources; each project has its own funding source and budget arrangements. Report 11.2, 11.3
  • Risk: Project risk is discussed with each project manager quarterly and a RAG status assigned; mitigation measures are discussed and applied by CLT at the Corporate Programme Board. Report 11.4
  • Equalities: An Equality Impact Assessment must be completed for every project as part of the initiation process and reviewed by CLT. Report 11.5
  • Climate: A Sustainability Appraisal must be completed for every project as part of the initiation process and reviewed by CLT. Report 11.7
  • Other: The ongoing monitoring of projects will have no bearing on Local Government Reorganisation. Report 11.8

Who and where

  • All Woking Borough Council capital and revenue projects Report 1.1, 4.2
  • Project managers across the Council, who are met with by the Project Support Office each cycle Report P17, 11.4
  • CLT and the Corporate Programme Board, which formally review every project each quarter Report 4.3

Timeline

  • End of April 2026: Cut-off date for the status of every Council project reported in Appendix 1 Report 1.1
  • Quarterly: Cycle on which the Corporate Programme Board reviews all projects Report 4.3, 10.1

Plain English for the jargon

  • RAG: Red, Amber, Green status rating used to indicate project risk and delivery performance.
  • CLT: Corporate Leadership Team, which formally reviews all Council projects via the Corporate Programme Board.
  • CPB: Corporate Programme Board, a quarterly forum where project risks, issues and other concerns are discussed.
  • WBC: Woking Borough Council.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item24

Resolved

The Executive Resolved That ( i ) the report be received; and (ii) the project monitoring at Appendix 1 to the report be noted. Reason: To apply performance management to Council projects.
Word for word from the decision Woking published for this meeting. Source: moderngov.woking.gov.uk

Follow this further

Built from Woking's papers

What the report saysPro

Report to Executive

Purpose of report

1.1The Executive receives regular reports on the progress of the Council’s key projects, so that it can review the status of these and consider any action that may be necessary to secure their delivery. A monitoring report detailing the status of every Council project (as at the end of April 2026), incorporating both capital and revenue projects, is attached at Appendix 1. The monitoring report provides a status update, and an assessment against project risks, issues, schedule, and budget.

1.2There are no specific areas for concern or action required by the Executive as a result of this latest review.

Recommendations

2.1The Executive is requested to:

Resolve That

(i) The report be received; and

(ii) The project monitoring at Appendix 1 to the report be noted.

Reason(s) for Decision

2.2To apply performance management to Council projects.

EXE26-033 Project Monitoring Report

3.0Proposal and Outcome

3.1The Executive is asked to review Appendix 1 and note the current status of the Council’s projects. Projects are subject to ongoing monitoring to provide assurance that they are delivered in line with expectations and to ensure that stated benefits are realised.

Background

4.1The undertaking of projects is an integral part of Woking Borough Council (WBC) business delivery, and significant resources are allocated to their successful completion. Project management processes have been developed to bring consistency to how projects are managed, and to aid the project manager in delivering projects on time, to budget, and to the desired standard.

4.2The process has been structured to be flexible so it can meet the specific needs of the Council. It is designed to add value to officers who are leading on projects and provide a common standard against which all projects can be assessed. Every project, regardless of size or type, is required to follow the corporate process.

4.3All Council projects are formally reviewed by CLT via the Corporate Programme Board (CPB) which meets quarterly. The CPB provides a forum where project risks, issues, and other areas of concern are discussed; this approach facilitates clear and accountable decision-making.

5.0Activity in Reporting Period

5.1Since the last report to the Executive:

• The Project Support Office has met with every project manager to discuss project progress, assess performance, and assign RAG ratings.

• A detailed update for each project has been produced (Appendix 1) and presented to CLT as part of the quarterly CPB meeting.

• Key points to note from the monitoring report are:

There are 11 projects classified as live or at practical completion, of which: o 82% (9) projects are green. o 9% (1) project is amber. o 9% (1) project is red.

• There are 2 projects that have been closed in the reporting period. Projects that have been closed during the period are not RAG rated as this rating relates to projects in delivery.

6.0Financial Exception Items

6.1In accordance with Financial Regulations, projects will be highlighted where actual spend exceeds the approved budget by the greater of £10k or 5%. There are no project(s) that fall into this category for this reporting period. Project Monitoring Report

7.0Items of Note

7.1None.

Options considered

8.1Strong and effective project monitoring is essential to ensure that Council resources are being used effectively. Project monitoring also enables lessons to be captured on a regular basis which supports continuous improvement. The option of not applying robust monitoring is not considered to be a viable alternative.

9.0Corporate Strategy

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EXE26-033 Appendix 1: Project Monitoring Report As End of April 2026Appendix 148 KB Download
PDF
Project Monitoring Report EXE26-033Report 114 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 17 attended
AB
Councillor Ann-Marie BarkerChair, present
DH
Councillor Deborah HughesVice-Chair, present
SG
Councillor Steve GreentreeCommittee Member, apologies
IJ
Councillor Ian JohnsonCommittee Member, present
LM
Councillor Louise MoralesCommittee Member, present
EN
Councillor Ellen NicholsonCommittee Member, present
DR
Councillor Dale RobertsCommittee Member, present
RC
Richard CarrOfficer, present
SF
Stephen FitzgeraldOfficer, apologies
BK
Beverley KucharOfficer, present
AO
Adesuwa OmoregieOfficer, apologies
LS
Louise StrongitharmOfficer, present

All 17 on the meeting page

On this subject at Woking

Search all
  1. Project Monitoring Report EXE26-033This decision
  2. Project Monitoring Report EXE26-005Noted
  3. Project Monitoring Report EXE25-041Noted
  4. Project Monitoring Report EXE25-026Noted
  5. Project Monitoring Report EXE25-005Noted
  6. Project Monitoring Report EXE24-066Noted

More from Woking Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Foundation Strategic Authority (FSA) EXE26-093The Executive Resolved That (i) the current position regarding the proposed establishment of a Foundation Strategic A... Noted Open
16 Sep 2026 Housing Operational Policies EXE26-051The Executive Resolved That (i) the Asbestos Policy be approved; (ii) the Lift Policy be approved; and (iii) the Stra... Approved Open
16 Sep 2026 Lakeview Estate Refurbishment Scheme EXE26-057The Executive Resolved That ( i ) the contract for the Lakeview Estate Refurbishment Project works be awarded to the ... Decided Open
16 Sep 2026 Revenue Refunds, Credit Balances and Write-Back Policy EXE26-101The Executive Resolved That (i) the Revenue Refunds, Credit Balances and Write-Back Policy be approved; (ii) the Head... Approved Open
16 Sep 2026 Enforcement Agent Procurement EXE26-112The Executive Resolved That ( i ) the commencement of a procurement exercise for the provision of Enforcement Agent s... Approved Open