CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Worcester City Council
Policy and Resources Committee, Monday 25 January 2021 at 7.00pm

Sansome Walk Former Swimming Pool Site: Appointment of Residential Developer

Agreed Committee 1 paper

Policy and Resources Committee agreed this item on Monday 25 January 2021. Below is the council's own wording, with the papers it was decided on.

Item106

Resolved

That the Committee agree: 1. to note the outcome of the procurement process for a residential developer for the former Sansome Walk Swimming Pool site and agrees to award the development agreement to the bidder identified in the confidential appendix to this report; 2. that the Council will let the remediation works contract using its appointed demolition and remediation contractor DSM Demolition Limited; 3. to delegate authority to the Director of Place, Director of Finance and Resources and Deputy Director - Governance to negotiate and enter into the above contracts; and 4. to recommend to Council that the capital programme is revised in the sum of £454k to allow for the cost of the remediation works.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Policy and Resources Committee, 8 pages

Recommendation

That the Committee:

1.1Notes the outcome of the procurement process for a residential developer for the former Sansome Walk Swimming Pool site and agrees to award the development agreement to the bidder identified in the confidential appendix to this Report;

1.2Agrees that the Council will let the remediation works contract using its appointed demolition and remediation contractor DSM Demolition Limited;

1.3Delegates authority to the Director of Place, Director of Resources and Deputy Director Governance to negotiate and enter into the above contracts; and

1.4Recommends to Council that the capital programme is revised in the sum of £454k to allow for the cost of the remediation works.

Background

2.1At its meetings in July 2019 and December 2019 the Committee agreed a series of steps to bring about the demolition, ground remediation and redevelopment of the Sansome Walk former swimming pool site (“the Site”). The Committee authorised the commencement of two parallel procurement processes to secure: (i) a contractor to undertake the demolition of the swimming pool and (ii) a developer to undertake a subsequent residential development of the Site. The Committee resolved that the decision as to which party should undertake the ground remediation of the Site, between the demolition and residential phases, should be assessed once the outcome of these two procurements was understood.

2.2Following a successful procurement process which concluded in October 2020, the Council appointed DSM Demolition Limited as the demolition contractor with a tendered fixed price for these works in the sum of £1,395,666. This price was able to be confirmed because of the amount of pre-survey work which had been undertaken by the Council’s previous project management team. 2.3 The contractor was also required to tender a price for the remediation works to the Site, under a mechanism which gives the Council the option to call upon the contractor to undertake these works subject to the Council agreeing with the contractor final costs and method statements. The exact remediation works required and the costs of these are subject to a better understanding of the requirements of the residential developer.

2.4The necessary Party Wall Act agreements with neighbours who have a legal interest in the shared boundary structures which are being removed have been concluded. The contractor took possession of the site at the end of November and has started stripping out the interior. The demolition of the building is programmed to be completed in September 2021.

2.5This Report updates the Committee on the outcome of the procurement process to select a residential developer and the recommended course of action to ensure the Site is remediated to the correct standard once the demolition phase has been completed.

3. Residential developer procurement

3.1The Committee at its meeting in December 2019 noted the Site provided a significant city centre development opportunity but that it involved a number of constraints, including contamination, rights of way, mature trees and the existence of a small but valued level car parking provision for residents on the neighbouring streets. The Committee reaffirmed its earlier choice of residential as the end use for the Site bearing in mind the planning policy context, the financial implications of bringing the Site back into use and the Council’s policy imperatives for the end use, including the need for affordable housing and also environmental sustainability.

3.2A set of criteria and weightings were agreed by the Committee as the basis for the procurement of a residential development partner, which were then developed into detailed criteria by the Council’s project team and evaluation panel:

Price 40%

Place-making and 20% design Sustainability 20%

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sansome Walk Former Swimming Pool Site: Appointment of Residential DeveloperReport 8 pages DownloadRead as text

At this meeting

Whole meeting
104MinutesApproved 105Town Investment PlanApproved
106Sansome Walk Former Swimming Pool Site: Appointment of Residential DeveloperThis decision
108Item Involving the Disclosure of Exempt InformationDecided

On this subject at Worcester

Search all
  1. Sansome Walk Former Swimming Pool Site: Appointment of Residential DeveloperThis decision
  2. Sansome Walk Former Swimming Pool Site- Procurement of Redevelopment PartnerAgreed
  3. Sansome Walk Decommissioning Lessons LearntNoted
  4. Demolition of the Former Sansome Walk Swimming Pool and the Future Use of the SiteAgreed
  5. Decommissioning of Sansome WalkNoted
  6. Application P18A0338 - Sansome Walk Swimming Pool and Fitness Centre, Sansome WalkDecided

More from Worcester Policy and Resources Committee

All decisions
MeetingDecisionOutcome
30 Jun 2026 MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. Approved Open
30 Jun 2026 Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... Agreed Open
30 Jun 2026 Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... Agreed Open
30 Jun 2026 Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... Agreed Open
30 Jun 2026 Town Investment Plan UpdateThat the Committee agree to note the contents of this report. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies