That the Committee agree: 1. to note the outcome of the procurement process for a residential developer for the former Sansome Walk Swimming Pool site and agrees to award the development agreement to the bidder identified in the confidential appendix to this report; 2. that the Council will let the remediation works contract using its appointed demolition and remediation contractor DSM Demolition Limited; 3. to delegate authority to the Director of Place, Director of Finance and Resources and Deputy Director - Governance to negotiate and enter into the above contracts; and 4. to recommend to Council that the capital programme is revised in the sum of £454k to allow for the cost of the remediation works.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1Notes the outcome of the procurement process for a residential developer for the former Sansome Walk Swimming Pool site and agrees to award the development agreement to the bidder identified in the confidential appendix to this Report;
1.2Agrees that the Council will let the remediation works contract using its appointed demolition and remediation contractor DSM Demolition Limited;
1.3Delegates authority to the Director of Place, Director of Resources and Deputy Director Governance to negotiate and enter into the above contracts; and
1.4Recommends to Council that the capital programme is revised in the sum of £454k to allow for the cost of the remediation works.
Background
2.1At its meetings in July 2019 and December 2019 the Committee agreed a series of steps to bring about the demolition, ground remediation and redevelopment of the Sansome Walk former swimming pool site (“the Site”). The Committee authorised the commencement of two parallel procurement processes to secure: (i) a contractor to undertake the demolition of the swimming pool and (ii) a developer to undertake a subsequent residential development of the Site. The Committee resolved that the decision as to which party should undertake the ground remediation of the Site, between the demolition and residential phases, should be assessed once the outcome of these two procurements was understood.
2.2Following a successful procurement process which concluded in October 2020, the Council appointed DSM Demolition Limited as the demolition contractor with a tendered fixed price for these works in the sum of £1,395,666. This price was able to be confirmed because of the amount of pre-survey work which had been undertaken by the Council’s previous project management team. 2.3 The contractor was also required to tender a price for the remediation works to the Site, under a mechanism which gives the Council the option to call upon the contractor to undertake these works subject to the Council agreeing with the contractor final costs and method statements. The exact remediation works required and the costs of these are subject to a better understanding of the requirements of the residential developer.
2.4The necessary Party Wall Act agreements with neighbours who have a legal interest in the shared boundary structures which are being removed have been concluded. The contractor took possession of the site at the end of November and has started stripping out the interior. The demolition of the building is programmed to be completed in September 2021.
2.5This Report updates the Committee on the outcome of the procurement process to select a residential developer and the recommended course of action to ensure the Site is remediated to the correct standard once the demolition phase has been completed.
3. Residential developer procurement
3.1The Committee at its meeting in December 2019 noted the Site provided a significant city centre development opportunity but that it involved a number of constraints, including contamination, rights of way, mature trees and the existence of a small but valued level car parking provision for residents on the neighbouring streets. The Committee reaffirmed its earlier choice of residential as the end use for the Site bearing in mind the planning policy context, the financial implications of bringing the Site back into use and the Council’s policy imperatives for the end use, including the need for affordable housing and also environmental sustainability.
3.2A set of criteria and weightings were agreed by the Committee as the basis for the procurement of a residential development partner, which were then developed into detailed criteria by the Council’s project team and evaluation panel:
Price 40%
Place-making and 20% design Sustainability 20%
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.