Resolved
That the Committee note the report.
Audit and Governance Committee noted this item on Wednesday 18 September 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Committee note the report.
1.1The Committee note the report.
2.1To provide an update on Internal Audit’s progress towards meeting its objectives as set out in the audit plan for 2019/2020 as approved by the Audit Committee on 20th March 2019, and, reporting on 2018/19 completed reviews.
2.2The Council is required under Regulation 5 of the Accounts and Audit Regulations 2015 to “undertake an effective internal audit to evaluate the effectiveness of its risk management, control and governance processes taking into account public sector internal auditing standards or guidance”.
3. Summary of Activity: 3.1 2019/20 Internal Audit Plan.
3.2Progress continues to be made in regard to the 2019/20 plan with the following audits on-going as at the 31st July 2019 and progressing through the testing stage:
Procurement ICT Debtors
3.3The following review is awaiting a management response before completion:
Museums
3.4Confirmation of the level of assurance and summary details of the outturns in each case will be provided for committee perusal when they have been finalised.
3.5A rolling testing programme on Debtors commenced in Q1 and is continuing. Testing results so far do not indicate any new or emerging risks to be brought to the attention of Committee. The rolling testing programme will continue through Q2 and will be reported at the next Committee. 3.6 The report commissioned by the Internal Audit Committee concerning lessons learnt in regard to the Sansome Walk Swimming Pool project has been completed and reported separately.
3.72018/19 Internal Audit Plan.
3.8Reports completed since the 20th March 2019 in regard to the 2018-19 Internal Audit Plan.
3.9Council Tax 3.10 The review found the following areas of the system were working well: The receipt and processing of customer payments. Refunds for accounts with a credit balance. The monitoring of collection rates. Procedures and protocols for identifying new domestic dwellings. The IT systems used outside of the Civica system. The correct protocol is being followed with regards to the first and any subsequent reminders and appropriate suppression is being managed. User profiling and system access rights.
3.11The review found the following areas of the system where controls could be strengthened: Evidencing of supporting documentation Approval of monthly reconciliations back to the general ledger Suspense Accounts Credit Accounts Timeliness of processing Council Tax changes Inaccuracies when processing, exemptions and discounts
3.12There were 2 ‘medium’ and 4 ‘low’ priority recommendations reported.
Type of Audit: Full System Report issued: 25th March 2019 Assurance: Significant
3.13NNDR 3.14 The review found the following areas of the system were working well: The setting up of new accounts is timely with accurate billing taking place Performance and collection monitoring is occurring on a regular basis with subsequent reporting Write off procedures and reports enabling consistent and accurate write offs The correct protocol is being followed with regards to first and subsequent reminders User profiling and access rights are sufficient to provide a good standard of security
3.15The review found that the following areas of the system where controls could be strengthened: The application of reliefs and exemptions on units, and respective billing amounts The reconciliation of cash receipts between the NNDR module and the general ledger.
3.16There were 2 ‘medium’ priority recommendations reported. Type of Audit: Full System Report issued: 25th March 2019 Assurance: Significant
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Delivery against Internal Audit Plan for 2019Appendix 1 | 2 pages | Download |
PDF |
Performance against Key Performance Indicators 2019Appendix 2 | 1 pages | Download |
PDF |
‘HIGH’ AND ‘MEDIUM’ PRIORITY RECOMMENDATIONS 2018-19Appendix 3 | 17 pages | Download |
PDF |
Audit Report Follow Up ProgrammeAppendix 4 | 3 pages | Download |
PDF |
Quality Assurance Improvement PlanAppendix 5 | 2 pages | Download |
PDF |
Internal Audit Progress ReportReport | 8 pages | DownloadRead as text |
Follow Audit and Governance Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2026 | MinutesThat the of the meeting held on 17 th March 2026 be approved as a correct record and signed by the Chair. | Approved | Open |
| 16 Jun 2026 | External Audit Plan 2025/26That the Committee agree to note the External Audit Plan for 2025/26. | Agreed | Open |
| 16 Jun 2026 | Item Involving The Disclosure of Exempt InformationThat under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for th... | Decided | Open |
| 16 Jun 2026 | Corporate Risk Management Report - Quarter 4, 2025-26That the Committee agree to note the updated assessment of corporate risks at the end of Quarter 4 as shown in the la... | Agreed | Open |
| 16 Jun 2026 | Treasury Management Annual Report 2025/26That the Committee: 1. agree to note the 2025/26 Annual Report; 2. agree to refer the Annual Report to full Council f... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.