Sansome Walk Decommissioning Lessons Learnt

Noted Finance 2 papers

Audit and Governance Committee noted this item on Wednesday 18 September 2019. Below is the council's own wording, with the papers it was decided on.

Item28

Resolved

That the Committee note the report, subject to any actions the Committee wish to take as a result of the extraordinary meeting.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Audit and Governance Committee, 2 pages

Recommendation

1.1The Committee note the report.

Background

2.1To report on lessons learnt from the decommissioning of Sansome Walk Swimming Pool project.

2.2During the 20th March 2019 meeting of the Audit and Governance Committee a paper was presented by the Deputy Director – Governance and Monitoring Officer which, in part, requested the internal audit service undertake a lessons learnt review of Sansome Walk Swimming Pool decommissioning project. This request cited a number of potential areas for consideration as part of the review.

3. Governance Issues 3.1 In view of the fact that the Council is expecting to deliver a number of significant capital projects in the next period, the work was undertaken as a priority during quarter 1 of 2019/20 municipal year. Areas taken into consideration as part of the review included the implications of decommissioning, project budget and mechanisms for reviewing, risk management, appointment of specialist providers and best practice procurement for construction services. The review approach was an over-arching view of the project as a whole, rather than majoring on specific areas.

3.2There were a number of areas of learning identified e.g. project focus, risk management, project scope, housekeeping, business continuity and project involvement, which have been acknowledged and are included at Appendix 1.

3.3The review identified although there had been regular inspections of the building during the time it was operational and open to the public these would have not been sufficiently detailed to unearth the deep fabric of the building and the real extent of the asbestos contamination present. This became apparent when a more intrusive inspection was commissioned. It should be noted that the audit review was process focussed and due to the specialist nature of asbestos removal the audit team were not in a position to comment on the adequacy of original specifications drawn up in regard to the asbestos removal. 3.4 Reports show that the decision to decommission Sansome Walk was viewed as an inevitable consequence of the decision to construct a new facility at Perdiswell, but that the decommissioning implications were not fully reported as part of the overall swimming pool project or budget. While the failing condition of the site appeared in the reports to add weight to the Perdiswell preferred option, the detailed options appraisal work and the reports which followed it were principally focused on the development opportunities afforded at the Perdiswell site. However, any use, refurbishment or disposal decision of the Sansome Walk site would have encountered the same issues that the Authority is faced with now; the use of asbestos as a building material in the site was well understood within the Council and common for buildings of its age. This is a consideration in itself for future projects of a similar nature.

4. Current Position

4.1Although there were some clear lessons to be learnt from the Sansome Walk decommissioning, through continuous improvement there have been a number of improvements implemented to strengthen project management. Key changes have included, establishment of a project management team, project gateway assessments, establishment of an asset management strategy, a process for seeking amendments to project budgets and the establishment of the an in house team to directly manage Council assets. These changes will help to ensure the Authority is in a stronger position to continue to achieve successful project outcomes. The report findings have been considered by CLT as well as the Leadership Group.

Appendices

5.1Appendix 1 provides the report with the lessons learnt along with management comment.

5.2Appendix 2 (Legal Advice) contains exempt information and is set out in the report in the confidential part of the agenda.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sansome Walk Decommissioning Lessons Learnt Appendix 1Appendix 10 pages Download
PDF
Sansome Walk Decommissioning Lessons LearntReport 2 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Sansome Walk Decommissioning Lessons LearntThis decision
  2. Sansome Walk Former Swimming Pool Site: Appointment of Residential DeveloperAgreed
  3. Sansome Walk Former Swimming Pool Site- Procurement of Redevelopment PartnerAgreed
  4. Demolition of the Former Sansome Walk Swimming Pool and the Future Use of the SiteAgreed
  5. Decommissioning of Sansome WalkNoted
  6. Application P18A0338 - Sansome Walk Swimming Pool and Fitness Centre, Sansome WalkDecided

More from Worcester Audit and Governance Committee

All decisions
MeetingDecisionOutcome
16 Jun 2026 MinutesThat the of the meeting held on 17 th March 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Jun 2026 External Audit Plan 2025/26That the Committee agree to note the External Audit Plan for 2025/26. Agreed Open
16 Jun 2026 Item Involving The Disclosure of Exempt InformationThat under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for th... Decided Open
16 Jun 2026 Corporate Risk Management Report - Quarter 4, 2025-26That the Committee agree to note the updated assessment of corporate risks at the end of Quarter 4 as shown in the la... Agreed Open