Shrub Hill Quarter Regeneration Programme

Noted Committee 1 paper

AI summaryWorcester City Council Place and Economic Development Committee notes progress on the Shrub Hill Quarter regeneration and approves a revised Towns Fund business case, including Isaac Maddox House, with a new delivery deadline of 31 March 2028.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedIncluding Isaac Maddox House and new Long Stop date
MoneyNot stated
What happens nextPublic realm route opens late February 2026Contractor mobilises June 2026; completion July 2027
Who it affectsShrub Hill Quarter, Cathedral wardLargest Opportunity Zone in South Worcestershire Development Plan

What was decided

The Committee noted progress on the Shrub Hill Quarter Regeneration Programme as set out in the report. Report 1.1

The Committee approved the revised Towns Fund business case covering Shrub Hill including Isaac Maddox House and the extended Grant Agreement Long Stop date of 31 March 2028. Report 1.2, P22

Approval covers revised floor space outputs for Isaac Maddox House, treated as value for money under new MHCLG Towns Fund flexibilities. Report 3.6, P22

Why

Towns Fund spending deadline has been extended to 31 March 2028, and MHCLG has given councils more flexibility to approve project changes themselves. Report P22

A limited refurbishment of Isaac Maddox House within the original grant would have produced insufficient lettable space and left much of the building in poor condition, undermining lettings and follow-on redevelopment. Report 3.4

The County Council resolved on 15 January 2026 to add £2 million of its own funding, enabling full exterior repair and refurbishment of two thirds of the building to provide 2068m2 of lettable space. Report 3.5

What happens next

Speller Metcalfe will mobilise on Isaac Maddox House for a June 2026 start, with practical completion expected in July 2027. Report 3.7

The County Council will seek a principal developer later in 2026, with an early priority being a planning application for new housing on the Lower Yard. Report 4.1

Both Councils will monitor external funding opportunities for further site preparation and station improvements, and engage landowners in the Quarter. Report 4.2

The money

  • £10,000,000 Total Towns Fund grant allocated across the programme Report 3.1, P21
  • 2,172,663 Towns Fund allocation for Public Realm Report P21
  • 7,252,337 Towns Fund allocation for Isaac Maddox House Report P21
  • 575,000 Towns Fund allocation for OPEX Programme Management Report P21
  • £2 million Additional County Council funding for Isaac Maddox House refurbishment Report 3.5

Options considered

  • Rejected: Limited refurbishment of Isaac Maddox House within the original Towns Fund grant. Would have produced lettable space well short of credible outputs to meet the original Towns Fund business case and left much of the building in poor condition. Report 3.4
  • Chosen: Refurbish two thirds of Isaac Maddox House with £2m additional County Council funding, delivering 2068m2 of lettable space. Supported by Savills lettability advice, the Joint City and County Steering Group, and City Council officers; meets value for money test under new MHCLG flexibilities. Report 3.5, 3.6

Implications

  • Financial: City Council capital investment in the Quarter is funded by Towns Fund grant, which also supports officer programme management time. Report P44
  • Legal: Legal advice has been obtained for the Compulsory Purchase Order used to deliver the new public realm route. Report P46
  • Risk: A shared Programme Risk Register is maintained by the two councils and reviewed by the Steering Group, with each project also having its own risk register. Report P47
  • Equalities: An equalities assessment has been undertaken and concludes that no groups or persons are unequally affected by the SPD proposals. Report P50
  • Staffing: There are no significant human resource implications associated with the initiatives outlined in the report. Report P52
  • Other: The regeneration is expected to have significant social, environmental and economic implications through land use change and new housing and employment opportunities. Report P56

Who and where

  • Residents and businesses in the Cathedral ward and the wider Shrub Hill Quarter Report P57
  • Future tenants of Isaac Maddox House, with potential for 400 jobs at full occupancy Report 3.5, 3.6
  • Pedestrians and cyclists using the new shared route between the canal and Pheasant Street Report 3.1, 3.2
  • Businesses previously located on the Industrial Estate, all of whom have found alternative premises with County Council support Report 3.9
  • Prospective developers responding to the future search for a principal development partner Report 3.10, 3.11, 4.1

Timeline

  • 23 January 2023: Committee approved setting up the Shrub Hill Quarter regeneration programme Report 2.1
  • January 2024: Committee approved launch of consultation on a draft Supplementary Planning Document (SPD) Report 2.5
  • September 2024: Council adopted the Shrub Hill Quarter SPD; planning permission granted for Isaac Maddox House refurbishment (24/00247/FUL) Report 2.5, 3.3
  • 11 December 2024: Towns Fund Board approved revised business case removing partial demolition of Unit 17 and a 90-space Upper Yard parking area Report P19
  • January 2025: DHLUC approved the Project Adjustment Request; previous update report to this Committee on 27 January 2025 Report P19, 2.7
  • May 2025: Public realm scheme works started after CPO notices were served Report 3.2
  • September 2025: MHCLG confirmed Towns Fund simplifications, extending the spending deadline to 31 March 2028 Report P22
  • 15 January 2026: County Council resolved to add £2m of its own funding to Isaac Maddox House Report 3.5
  • 26 January 2026: Place and Economic Development Committee considered this report
  • End of February 2026: New public realm route due to open for public use and be adopted as public highway Report P25
  • June 2026: Speller Metcalfe due to mobilise on Isaac Maddox House refurbishment Report 3.7
  • Later in 2026: County Council to seek a principal developer for the Quarter Report 4.1
  • July 2027: Practical completion of Isaac Maddox House refurbishment expected Report 3.7
  • 31 March 2028: Extended Towns Fund Grant Agreement Long Stop date Report 1.2, P22

Plain English for the jargon

  • Towns Fund: A government grant programme administered by MHCLG (formerly DHLUC) to help towns invest in regeneration projects.
  • Long Stop date: The final deadline by which Towns Fund grant must be spent under the Grant Agreement.
  • Benefit Cost Ratio: A measure used in business cases to compare the value of benefits against the costs of a project; a ratio above 1 indicates positive value.
  • RIBA 4: Royal Institute of British Architects Work Stage 4, the Technical Design stage of a construction project.
  • BLRF: Brownfield Land Release Fund, government grant used to prepare previously developed land for housing.
  • SPD: Supplementary Planning Document, a council document that adds detail to planning policies in the local plan.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item36

Resolved

That the Committee: 1. note the progress in the as detailed in the report; and 2. approve the business case for revised Towns Fund outputs for Shrub Hill including Isaac Maddox House and the extended delivery Grant Agreement Long Stop date of 31st March 2028.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Place and Economic Development Committee, 7 pages

Recommendation

That the Committee:

1.1Notes the progress in the Shrub Hill Quarter Regeneration Programme as detailed in the report; and

1.2Approves the business case for revised Towns Fund outputs for Shrub Hill including Isaac Maddox House and the extended delivery Grant Agreement Long Stop date of 31 March 2028.

Background

2.1At its meeting of 23 January 2023, this Committee approved the setting up of a Shrub Hill Quarter regeneration programme, noting that Shrub Hill is the largest Opportunity Zone defined in the South Worcestershire Development Plan for Worcester with the potential for significant numbers of new jobs and housing arising out of the redevelopment of underutilised brownfield land and buildings, many of which are in poor condition.

2.2The area benefits from being situated close to the town centre and the railway station and can build on its past in the form of several important heritage and listed buildings as well as its canal side setting. Committee approved objectives for the programme noting that the City Council would be working in collaboration with the County Council to prepare the framework for public and private investment in the area, leveraging external funding and delivering the first phases of new development on the Shrub Hill Industrial Estate which the County had recently acquired.

2.3Six long-term place ‘foundations’ have been identified in the work undertaken to date by County and City to shape the purpose of development and help to establish ‘the place’ over the coming decades:

• Connected: Shrub Hill will be a welcoming and integrated station gateway which Worcester is proud of, and which connects the city’s neighbourhoods and communities. Transformed and modernised rail services will bring Worcester closer to the nation and underpin regeneration and investment across the city.

• Distinctive: Shrub Hill will accommodate a highly distinctive mix of spaces, uses and experiences, which build on the area’s unique industrial heritage and assets, and which excite new and existing audiences. • Productive: Shrub Hill will become a recognised and dense hub of employment and enterprise: a networked business ecosystem, which provides a home for socially & environmentally minded companies and institutions.

• Sustainable: Shrub Hill will provide a resilient, adaptive, and high-quality environment, built for future generations and setting the benchmark for a smart and zero carbon city.

• Inclusive: Shrub Hill will be home to a happy, healthy, and prosperous community; where well-being is prioritised, opportunity is created, and participation is enabled.

• Innovative: Shrub Hill will be a testbed for new ideas and approaches, where technological, environmental, economic and social innovation is actively encouraged.

2.4Progress is overseen by a quarterly joint City & County Steering Group comprising the Leader of the City Council, the County Deputy Leader and Cabinet Member with Responsibility for Finance and Corporate Services, the County Member for Business and Skills and the Chair of Place and Economic Development Committee.

2.5In January 2024, Committee approved the launching of public and stakeholder consultation on a draft Supplementary Planning Document (SPD) for the Shrub Hill Quarter. The SPD has been well received and was adopted by the Council in September 2024.

2.6The SPD is based on earlier master planning work and an investigation into the constraints and opportunities for development in the Quarter. It sets out a framework for future planning decisions setting standards for the quality of development and design, provides confidence to developers and landowners and has increased the prominence of the programme with potential investors and government agencies.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Shrub Hill Quarter Regeneration ProgrammeReport 7 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 12 attended
MA
Councillor Mel AllcottCommittee Member, present
JB
Councillor Jenny BarnesCommittee Member, present
KC
Councillor Katie CollierCommittee Member, present
HC
Councillor Hannah CooperVice-Chair, in the Chair, expected
LD
Councillor Lynn DenhamCommittee Member, present as substitute
JD
Councillor Jill DesayrahCommittee Member, present
AG
Councillor Adrian GregsonCommittee Member, present
EK
Councillor Ed KimberleyCommittee Member, present
RN
Councillor Robyn NorfolkChair, apologies, sent representative
TP
Councillor Tor PingreeCommittee Member, present
ER
Councillor Elena RoundCommittee Member, present
EW
Councillor Elaine WillmoreCommittee Member, present

On this subject at Worcester

Search all
  1. Shrub Hill Quarter Regeneration ProgrammeThis decision
  2. Review of the Shrub Hill Quarter Supplementary Planning DocumentApproved
  3. Shrub Hill Quarter Regeneration Programme UpdateNoted
  4. Referral Report from Place and Economic Development Committee 22nd July 2024 - Shrub Hill Quarter Supplementary Planning DocumentAgreed
  5. Shrub Hill Quarter Supplementary Planning DocumentAgreed
  6. Shrub Hill Quarter Supplementary Planning DocumentApproved

More from Worcester Place and Economic Development Committee

All decisions
MeetingDecisionOutcome
16 Mar 2026 MinutesThat the minutes of the meeting held on 26 th January 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Mar 2026 Review of the Shrub Hill Quarter Supplementary Planning DocumentThat the Committee: 1. approves the draft Shrub Hill Quarter Supplementary Planning Document, as set out in appendix ... Approved Open
16 Mar 2026 Review of the Air Quality Supplementary Planning DocumentThat the Committee: 1. approves the draft Air Quality Supplementary Planning Document, as set out in appendix 1, for ... Approved Open
16 Mar 2026 Review of the Affordable Housing Supplementary Planning DocumentThat the Committee: 1. approves the draft Affordable Housing Supplementary Planning Document, as set out in appendix ... Approved Open
16 Mar 2026 Review of A Guide to Shopfronts and Signage Supplementary Planning DocumentThat the Committee: 1. approves the draft Shopfronts Guide Supplementary Planning Document, as set out in appendix 1,... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies