Place and Economic Development Committee, Monday 26 January 2026 at 7.00pm

Quarter 3 Performance Report 2025/26

Noted Committee 2 papers

AI summaryWorcester City Council's Place and Economic Development Committee noted the council's quarter 3 2025/26 performance, removed the major planning appeals KPI from the scorecard, and pushed back three project deadlines.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedThree actions agreed at 26 January 2026 meeting
MoneyNot stated
What happens nextApply revised dates and updated scorecardWorcester Show, Shrub Hill and SWDP due dates change
Who it affectsPerformance monitoring and project timelinesPlanning appeals KPI dropped; three project deadlines reset

What was decided

The committee noted the council's quarter 3 2025/26 performance across projects and KPIs. Report P2, P3

The committee agreed to remove the KPI for Appeals of major planning decisions allowed from the performance scorecard, on the grounds it is no longer fit for purpose and is covered by the P152 quality KPI. Report P70, P71, P72

The committee agreed to amend the due dates for Worcester Show 2025, Town Investment Plan Shrub Hill regeneration, and Review of the South Worcestershire Development Plan. Report P22, P25, P26, P27, P28

Why

Officers reported that the major appeals KPI is no longer fit for purpose and that performance is already monitored through the Major Planning Applications (Quality) indicator P152. Report P70, P71

Worcester Show needs a Project Board review of final budget out-turn and carbon footprint before closure. Report P22

Shrub Hill regeneration has slipped due to bridge parapet fabrication delays, and the South Worcestershire Development Plan is awaiting the Inspectors' findings after its Main Modifications consultation. Report P25, P27

What happens next

Worcester Show 2025: new project due date of 31 March 2026 for Project Board review of out-turn and carbon footprint. Report P22

Shrub Hill regeneration: project due date amended from March 2027 to July 2027, to reflect refurbishment start in June 2026 and opening in July 2027. Report P25, P26

South Worcestershire Development Plan: project due date amended from December 2025 to March 2026, to allow completion of the Main Modifications consultation ending 17 February 2026 and Inspectors' findings. Report P27, P28, P90

The money

  • £2,186 Startup business grants awarded under UKSPF to date Report P33
  • £31,606 Growth business grants awarded under UKSPF to date Report P33

Options considered

  • Rejected: Retain the KPI for Appeals of major planning decisions allowed on the scorecard. Considered no longer fit for purpose; performance is monitored by the P152 quality KPI Report P70, P71
  • Chosen: Remove the KPI for Appeals of major planning decisions allowed from the scorecard. No longer fit for purpose; performance is monitored by the P152 quality KPI Report P70, P71
  • Rejected: Keep original due dates for Worcester Show, Shrub Hill regeneration and SWDP Review. No reason given in the papers Report P22, P25, P27
  • Chosen: Amend the due dates for Worcester Show, Shrub Hill regeneration and SWDP Review. Reflects current project progress and consultation timetable Report P22, P26, P28

Implications

  • Financial: UKSPF funding ends after 31 March 2026, affecting community and place, local business, and people and skills projects. Report P12, P13, P15
  • Legal: The Main Modifications consultation on the South Worcestershire Development Plan is required to ensure the plan is sound and legally compliant before adoption by 31 March 2026. Report P27, P90
  • Other: Worcester City can demonstrate 2.61 years of housing land supply against a 5-year requirement of 587 dwellings per annum, until the SWDP is adopted. Report P78, P79, P80, P82
  • Other: Performance scorecard will no longer include the major planning appeals KPI; quarterly P152 quality KPI remains the monitor for this area. Report P70, P71, P38, P39

Who and where

  • Businesses receiving UKSPF startup, growth, R&D and decarbonisation grants in Worcester Report P31, P32, P33, P34
  • Applicants and appellants in the Worcester City major and non-major planning application process Report P36, P37, P38, P39, P40, P42, P43, P44
  • Visitors and participants at the Commandery and Worcester City Art Gallery & Museum Report P63, P64, P65, P66, P68, P69
  • Community groups and creative organisations supported through the Cultural Compact and Place Partnership Report P18

Timeline

  • 31-Mar-2026: Revised due date for Worcester Show 2025 Project Board review Report P22
  • 31-Jul-2027: Revised due date for Shrub Hill regeneration: opening of Isaac Maddox House and shared use link Report P25, P26
  • 31-Mar-2026: Revised due date for adoption of the South Worcestershire Development Plan Report P27, P28, P90
  • 17-Feb-2026: End of the six-week Main Modifications consultation on the SWDP Review Report P27
  • 31-Mar-2026: End of UK Shared Prosperity Fund allocations and project delivery Report P12, P13, P15

Plain English for the jargon

  • UKSPF: UK Shared Prosperity Fund, a central government fund supporting community, business and skills projects; allocations end after 31 March 2026.
  • SWDP / SWDPR: South Worcestershire Development Plan (Review), the joint local plan covering Worcester City and other South Worcestershire councils.
  • KPI: Key Performance Indicator, a measurable value used on the council's performance scorecard.
  • LDS: Local Development Scheme, the timetable for preparing planning policy documents.
  • 5YHLS: Five-Year Housing Land Supply, the measure of deliverable housing sites against a five-year requirement.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item42

Resolved

That the Committee: 1. note the Council’s quarter 3 performance for 2025/26; 2. agree the removal of KPI for Appeals of major applications decisions allowed from the performance scorecard; and 3. agree the amendment of the due dates for the Town Investment Plan - Shrub Hill regeneration, Review of the South Worcestershire Development Plan and Worcester Show projects.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Place and Economic Development Committee, 20 pages

Appendix 1

Place & Economic Development Performance Report

PED Projects & Actions 2025/26

Future High Streets Fund - Public Realm The remaining works on Angel Street are now programmed Sponsor Duncan to be undertaken towards the end of the Scala and Corn Rudge; Sian Exchange works, this is to ensure that no conflict occurs Stroud with two contractors on site nor damage to newly laid Due Date 31-Mar-2027 surfaces. Original Due 31-Mar-2025 Date Current Status Expected Outcome

Future High Streets Fund - Angel Place The delivery of the works will come towards the end of the Sponsor Sian Stroud Scala and Corn Exchange development, as has been Due Date 31-Mar-2027 indicated previously, as the site compound currently occupies a significant area of the northern section of Angel Original Due 31-Mar-2025 Place. Date Current Status Initial considerations will be given towards protective measures to ensure that the space by the Scala is Expected Outcome protected and available for use by the future users/events. Initial surveys have been undertaken which will inform the works.

Town Investment Plan - Heritage and Riverside Destinations Works at the Cathedral are complete with the exception of Sponsor David Blake interpretation and wayfinding infrastructure. All areas are Due Date 31-Dec-2026 open and fully operational, and the Town Investment Plan element of the overall project is therefore complete. Original Due 31-Mar-2025 Date St Andrews Gardens landscaping works are complete. Some Current Status minor work remains to be completed on the entrance ironwork. Expected Outcome

The Museums project has created a new shop and reception at the Commandery as well as a new gallery space that is hosting an interim spotlight exhibition on Victorian

2 Worcester. Preparation is underway for a new British Impressionism Gallery at the Art Gallery and Museum.

Building on the Town Investment Plan project the Council is supporting the Mercian Regiment Museum Worcestershire and the Worcestershire Yeomanry Trust to develop their new Worcestershire Soldier exhibition for this space due to open in 2027 supported by a significant grant by the National Lottery Heritage Fund.

The refurbishment of the Art Gallery & Museum permanent art gallery is progressing well.

Towns Investment Plan - Community Skills Works to WCT reception areas and BB2 are complete. Sponsor Sian Stroud Due Date 31-Mar-2026 St Peters Village Hall and Fairfield are nearing completion. Original Due 31-Mar-2024 The contingency fund is being developed in line with the Date projects identified within July 2025 P&R report. Current Status Expected Outcome

UKSPF - Community and Place Allocations of UKSPF were made to support larger Sponsor Sian Stroud community organisations which had previously been funded Due Date 31-Mar-2026 through Council base budget. A separate small grants scheme for community and arts was established. Original Due 30-Mar-2025 Date There is no UKSPF beyond the end of March 2026. Current Status Expected Outcome

UKSPF - Local Business Two business grant schemes were established and are Sponsor Sian Stroud being administered. Due Date 31-Mar-2026 There is no UKSPF beyond the end of March 2026. Original Due 30-Mar-2025 Date Current Status Expected Outcome

3 UKSPF - People and Skills Projects are being delivered through funding of Sponsor Sian Stroud Due Date 31-Mar-2026 Worcestershire Growth Hub - Skills Boost Original Due 30-Mar-2025 Worcestershire County Council - Careers Worcestershire Date Current Status Worcester Community Trust - Life Skills Expected Outcome

There is no UKSPF beyond the end of March 2026.

Economic Development Strategy Due date amended from March 2026 to August 2026 as Sponsor Sian Stroud agreed at PED committee in November 2025. Due Date 31-Aug-2026 Original Due 30-Jun-2023 Date Current Status Expected Outcome

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
202526Q3 PEDQuarterlyPerformanceReport: for publication 2Report 20 pages DownloadRead as text
PDF
Quarter 3 Performance Report 2025/26Report 2 pages Download

At this meeting

Whole meeting

Who was there

11 of 12 attended
MA
Councillor Mel AllcottCommittee Member, present
JB
Councillor Jenny BarnesCommittee Member, present
KC
Councillor Katie CollierCommittee Member, present
HC
Councillor Hannah CooperVice-Chair, in the Chair, expected
LD
Councillor Lynn DenhamCommittee Member, present as substitute
JD
Councillor Jill DesayrahCommittee Member, present
AG
Councillor Adrian GregsonCommittee Member, present
EK
Councillor Ed KimberleyCommittee Member, present
RN
Councillor Robyn NorfolkChair, apologies, sent representative
TP
Councillor Tor PingreeCommittee Member, present
ER
Councillor Elena RoundCommittee Member, present
EW
Councillor Elaine WillmoreCommittee Member, present

On this subject at Worcester

Search all
  1. Quarter 3 Performance Report 2025/26This decision
  2. Quarter 4 and Annual Key Performance Indicator Report for 2025/26Agreed
  3. Quarter 4 and Annual Performance Report for 2025/26Noted
  4. Quarter 4 and Annual Performance Report for 2025/26Agreed
  5. Quarters 2 and 3 Performance Report 2025-26Decided
  6. Quarter 3 Performance Report For 2025/26Agreed

More from Worcester Place and Economic Development Committee

All decisions
MeetingDecisionOutcome
16 Mar 2026 MinutesThat the minutes of the meeting held on 26 th January 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Mar 2026 Review of the Shrub Hill Quarter Supplementary Planning DocumentThat the Committee: 1. approves the draft Shrub Hill Quarter Supplementary Planning Document, as set out in appendix ... Approved Open
16 Mar 2026 Review of the Air Quality Supplementary Planning DocumentThat the Committee: 1. approves the draft Air Quality Supplementary Planning Document, as set out in appendix 1, for ... Approved Open
16 Mar 2026 Review of the Affordable Housing Supplementary Planning DocumentThat the Committee: 1. approves the draft Affordable Housing Supplementary Planning Document, as set out in appendix ... Approved Open
16 Mar 2026 Review of A Guide to Shopfronts and Signage Supplementary Planning DocumentThat the Committee: 1. approves the draft Shopfronts Guide Supplementary Planning Document, as set out in appendix 1,... Approved Open